Boomer v. Abbett

315 P.2d 924, 154 Cal. App. 2d 218, 1957 Cal. App. LEXIS 1612
CourtCalifornia Court of Appeal
DecidedOctober 7, 1957
DocketCiv. 17349
StatusPublished
Cited by2 cases

This text of 315 P.2d 924 (Boomer v. Abbett) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boomer v. Abbett, 315 P.2d 924, 154 Cal. App. 2d 218, 1957 Cal. App. LEXIS 1612 (Cal. Ct. App. 1957).

Opinion

BRAY, J.

This action, tried by the court without a jury, grew out of a subcontract entered into by plaintiff copartnership with defendant Abbett under a prime contract between said Abbett and the United States Bureau of Reclamation. The prime contract was to construct a transmission line in *220 northern California. The subcontract was to perform the excavation for and installation of the transmission line towers and certain other work. 1

Question Presented

Mainly, whether the excavation of the eight tower sites in the “dredger tailings” area was included in the prime contract and the subcontract.

Facts

The transmission line was to be approximately 25 miles long. Near the center of said line was a placer gold mining area known as the Clear Creek area, which was covered with dredger tailings consisting of loose rock, earth and some boulders. Plaintiffs claimed and the court found that the excavation of this area contemplated excavation of a type already committed to defendant under the “common excavation” clause of the prime contract. The bureau and defendant claimed otherwise.

The subcontract provided that the subcontractor was to perform all work as per schedule attached for excavation for 230 kilovolt transmission lines, Shasta Dam to Cottonwood-Gas Point Road in accordance with the general conditions of the prime contract and in accordance with its drawings and specifications. The schedule attached to the subcontract listed various items of work, including excavation items described as “common, hand, for footings,” (emphasis added) estimated at a total of 1,420 cubic yards, “common, auger, for footings” estimated at 470 cubic yards and “rock for footings” estimated at 870 cubic yards, for which unit prices of $8.10, $6.30 and $45.90 respectively were provided. The contractor agreed to pay the subcontractor in accordance with these unit prices and the quantities as agreed upon between the bureau, general contractor and subcontractor. The prime contract provided that the quantities noted in the schedule were approximations for comparing bids, and no claim against the bureau “shall be made against the Government for excess or deficiency therein ...” The prime contract listed 225 towers to be constructed but provided that this number was approximate only and “the Government does not guarantee the construction of all or any number of the towers listed.”

Plaintiffs performed the excavation work for 206 towers, for *221 which unit prices were fully paid. The common, hand, excavation exceeded the estimate by about 1,000 cubic yards. Plaintiffs actually received about $24,000 in excess of the contract price mentioned in plaintiffs’ subcontract, including excavation work. The court found that at the time the prime contract and the subcontract were executed, the bureau and all parties knew that part of the excavation work required would be done in the Clear Creek area, and that certain towers would be erected, the excavation for the footings therefor would be made in dredger tailings, and that the bureau breached the prime contract in attempting as it did to reclassify said excavation work, by refusing to pay therefor at the unit prices called for common excavation work in the prime contract and the subcontract respectively, and by refusing to permit plaintiffs to do said excavation work in accordance with the provisions of both contracts; that defendant did not protest the actions of the bureau and therefore breached the subcontract. The court then found that plaintiffs had been damaged in the total sum of $71,404.45, of which plaintiffs were obligated to pay $5,557.12 to a certain concern to whom they had subcontracted a portion of the work to be done and the balance of which was the value of the time, effort ancb materials expended by plaintiffs in preparation for the work they were not permitted to perform, and loss of profits.

Some five months after the contracts were let, the bureau, which had not test drilled the dredger tailings area theretofore, did so. The tests showed that a considerable amount of excavation would be required. In the prime contract the bureau’s contracting officer was entitled to “make changes in the drawings and/or specifications of this contract and within the general scope thereof.” He also had the right to modify the contract “to provide for any increase or decrease of cost” resulting from “subsurface and/or latent conditions at the site materially differing from those shown on the drawings or indicated in the specifications, or unknown conditions of an unusual nature differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the plans and specifications ...” Under these provisions and as the excavation in the dredger tailings area was completely dissimilar to the excavation elsewhere on the transmission lines, the bureau issued revised drawings and made change order Number 2. This ordered changes in the heights of 12 towers in the dredger area and in the nature and depth of the exea *222 vations required. It provided that for excavating “overburden-dredger tailings for footings” of these 12 towers 75 cents per cubic yard would be paid. Thereupon defendant called for new bids on the excavation work covered by the change order. Plaintiffs refused to bid and this new work was awarded to one Draper at 60 cents per cubic yard. Plaintiffs asserted their right under their contract to undertake this newly specified excavation work at the prices set forth in the contract, and vigorously protested to defendant the bureau’s actions, but expressed a willingness to perform the other new work called for in the change order at the new rates. Defendant conveyed these objections to the bureau officials but did not file a formal protest. When plaintiffs were notified that this work had been awarded to another, they protested by letter to defendant. Defendant ordered plaintiffs to perform according to the revised plans the work in this area other than the removal of the dredger tailings overburden. Plaintiffs proceeded to try to comply by purchasing materials and letting a subcontract. The bureau then issued change order Number 3, stopping all work of excavation for 16 towers, 12 of which were in the dredger tailings area and four were not. Plaintiffs were definitely informed that this part of the work would not be performed. The situation then existing as disclosed by the evidence is well expressed in our opinion in Boomer v. Abbett, supra, 121 Cal.App.2d at page 457: “The evidence of the bureau engineers was to the effect that after the prime contract was executed they discovered that it would be dangerous to erect the 12 contemplated towers upon the foundation of the dredger tailings, so that deeper excavations removing the dredger tailings were required. There was much controversy between the parties and their witnesses as to the meaning of ‘overburden.’ Boomer testified that the term had no specialized significance in contracting terminology, but simply signified a stratum of material that was on top of another stratum. He conceded that the overburden of dredger tailings could be removed very cheaply by bulldozer and would not have to be removed by hand or truck-mounted tools, as much of the other work had to be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stroman v. Atchison, Topeka & Santa Fe Railway Co.
200 Cal. App. 2d 418 (California Court of Appeal, 1962)
Russ v. Russ
326 P.2d 595 (California Court of Appeal, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
315 P.2d 924, 154 Cal. App. 2d 218, 1957 Cal. App. LEXIS 1612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boomer-v-abbett-calctapp-1957.