Boomer v. Abbett

315 P.2d 924, 154 Cal. App. 2d 218, 1957 Cal. App. LEXIS 1612
California Court of Appeal·Decided October 7, 1957·No. Civ. 17349·Published·Cited by 2 cases

Opinion

BRAY, J.

This action, tried by the court without a jury, grew out of a subcontract entered into by plaintiff copartnership with defendant Abbett under a prime contract between said Abbett and the United States Bureau of Reclamation. The prime contract was to construct a transmission line in *220 northern California. The subcontract was to perform the excavation for and installation of the transmission line towers and certain other work. 1

Question Presented

Mainly, whether the excavation of the eight tower sites in the “dredger tailings” area was included in the prime contract and the subcontract.

Facts

The transmission line was to be approximately 25 miles long. Near the center of said line was a placer gold mining area known as the Clear Creek area, which was covered with dredger tailings consisting of loose rock, earth and some boulders. Plaintiffs claimed and the court found that the excavation of this area contemplated excavation of a type already committed to defendant under the “common excavation” clause of the prime contract. The bureau and defendant claimed otherwise.

The subcontract provided that the subcontractor was to perform all work as per schedule attached for excavation for 230 kilovolt transmission lines, Shasta Dam to Cottonwood-Gas Point Road in accordance with the general conditions of the prime contract and in accordance with its drawings and specifications. The schedule attached to the subcontract listed various items of work, including excavation items described as “common, hand, for footings,” (emphasis added) estimated at a total of 1,420 cubic yards, “common, auger, for footings” estimated at 470 cubic yards and “rock for footings” estimated at 870 cubic yards, for which unit prices of $8.10, $6.30 and $45.90 respectively were provided. The contractor agreed to pay the subcontractor in accordance with these unit prices and the quantities as agreed upon between the bureau, general contractor and subcontractor. The prime contract provided that the quantities noted in the schedule were approximations for comparing bids, and no claim against the bureau “shall be made against the Government for excess or deficiency therein ...” The prime contract listed 225 towers to be constructed but provided that this number was approximate only and “the Government does not guarantee the construction of all or any number of the towers listed.”

Plaintiffs performed the excavation work for 206 towers, for *221 which unit prices were fully paid. The common, hand, excavation exceeded the estimate by about 1,000 cubic yards. Plaintiffs actually received about $24,000 in excess of the contract price mentioned in plaintiffs’ subcontract, including excavation work. The court found that at the time the prime contract and the subcontract were executed, the bureau and all parties knew that part of the excavation work required would be done in the Clear Creek area, and that certain towers would be erected, the excavation for the footings therefor would be made in dredger tailings, and that the bureau breached the prime contract in attempting as it did to reclassify said excavation work, by refusing to pay therefor at the unit prices called for common excavation work in the prime contract and the subcontract respectively, and by refusing to permit plaintiffs to do said excavation work in accordance with the provisions of both contracts; that defendant did not protest the actions of the bureau and therefore breached the subcontract. The court then found that plaintiffs had been damaged in the total sum of $71,404.45, of which plaintiffs were obligated to pay $5,557.12 to a certain concern to whom they had subcontracted a portion of the work to be done and the balance of which was the value of the time, effort ancb materials expended by plaintiffs in preparation for the work they were not permitted to perform, and loss of profits.

Free access — add to your briefcase to read the full text and ask questions with AI

Boomer v. Abbett, 315 P.2d 924, 154 Cal. App. 2d 218, 1957 Cal. App. LEXIS 1612 (Cal. Ct. App. 1957).

315 P.2d 924 (Boomer v. Abbett) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stroman v. Atchison, Topeka & Santa Fe Railway Co.
200 Cal. App. 2d 418 (California Court of Appeal, 1962)
Russ v. Russ
326 P.2d 595 (California Court of Appeal, 1958)