United States ex rel. Davies v. Blauner Const. Co.

37 F. Supp. 968, 1941 U.S. Dist. LEXIS 3621
CourtDistrict Court, D. Massachusetts
DecidedMarch 20, 1941
DocketNo. 287
StatusPublished
Cited by5 cases

This text of 37 F. Supp. 968 (United States ex rel. Davies v. Blauner Const. Co.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Davies v. Blauner Const. Co., 37 F. Supp. 968, 1941 U.S. Dist. LEXIS 3621 (D. Mass. 1941).

Opinion

FORD, District Judge.

This suit, involving eight items or claims, is brought under the provisions of Chapter 642, Section 2 of the Act of August 24, 1935, 49 Stat. 794, 40 U.S.C.A. § 270b(a), for the use and benefit of R. Fred Davies (hereinafter referred to as the plaintiff) to recover from the defendant Blauner' Construction Company, a corporation, (hereinafter called Blauner) and the surety on a payment bond to protect all persons supplying labor and material in connection with a contract entered into between Blauner and [969]*969the United States for the construction of a post office in Orange, Massachusetts.

It was agreed between the parties that the plaintiff is entitled to recover on claims represented by items numbered 1, 2, 5, 6, 7, and 8 in exhibit “B” attached to the complaint in the sum of $293.63, inclusive of interest.

The case was tried to the court without a jury and at the close of the plaintiff’s case, the defendants filed motions for dismissal of the plaintiff’s complaint under the provisions of Federal Rules of Civil Procedure 41(b), 28 U.S.C.A. following section 723c, in so far as claims 3 and 4 in exhibit “B” attached to the complaint which relate to work and labor for rock excavation are concerned. These motions were allowed. As required by Rule 52(a) the following facts are found, conclusions of law stated, and the appropriate judgment directed for entry.

Findings of Fact.

The defendants, Blauner and the United States Guarantee Company, executed and delivered to the United States a bond in the penal sum of $23,870, dated July 15, 1937, conditioned to make prompt payment to all persons supplying labor and material in the prosecution of the work provided in the contract referred to above.

On September 16, 1937, Blauner entered into a sub-contract with the plaintiff, a plumbing and heating contractor of twenty-two years’ experience, wherein the latter promised “to furnish labor and material to do plumbing and heating in accordance with plans and specifications (United States Government) Sections 28, 29, 30, pp. 1-16, inclusive, for the sum of $5425”. Before this contract was executed by the plaintiff, Blauner sent to him a complete set of government plans and specifications. The specifications, incorporated into the plaintiff’s contract, required that “the entire plumbing installation shall comply with the requirements of the Standard Specifications for Miscellaneous Plumbing Materials and Labor, March 1, 1937.” The Standard Specification required that all trenches required for soil, waste, vent and drain piping, “must be excavated with bottoms to the proper grade so that pipes will have a solid bearing” (Italics mine) and the “bottom of trenches shall be cut true to grade *.* * The piping was to be of the size noted and indicated on the drawings; catch basins required by plans were to be installed as indicated ; and all work was required to be in accordance with specifications and plans furnished by the government and referred to above.

There was no dispute between the parties that what is set out above comprised the terms of the contract between Blauner and the plaintiff that are material to the issues involved in this case. The dispute was as to its meaning.

The plan entitled “Survey of Post Office Site” disclosed the presence of rock ledge on the site (area of latter 25,550 square feet) at three different places. Also on this plan there was set out the beneath the surface characteristics of soil and other material in, and location of, four test pits, one of which was located practically at each of the four corners of the site and fairly adjacent to the locations where the plaintiff was required to dig his trenches for the piping required for the plumbing and heating. The test pits depicted in the plans disclosed the presence of large boulders and rock ledge at varying elevations and, at some locations, above the depth to which the plaintiff was required by his contract to excavate.

The plaintiff commenced work on September 25, 1937, and on October 15, 1937, when about 55 per cent of his work was completed, he came upon considerable rock, boulders and rock ledge. At this point, he called the attention of these facts to Blauner’s superintendent, who, I find, had complete charge of Blauner’s work and full authority to act for Blauner in the latter’s stead in connection with the construction of the post office. Although the plaintiff admitted he did not intend to relinquish or refuse to go on with his contract, he testified he told Fox in substance that he expected extra compensation for removing the rock and ledge he was about to encounter. The plaintiff further testified that Fox promised him extra compensation for any work performed in connection with the removal of this rock and ledge and that he, Fox, instructed the plaintiff, if necessary, to hire a compressor for breaking the rock. The plaintiff later procured the compressor. The plaintiff testified in substance that a few days later the president of Blauner promised to give him a work order for this work when it was finally completed. The plaintiff did the excavating that was required by the contract partly in October and November of 1937 and finished it in March and April of the following year. Part of the rock encountered was broken up [970]*970by the use of the compressor and part by blasting with explosives. It is for the net cost of removing this rock and rock ledge that was encountered in the excavating that this suit in part was brought, and the claims for it appear in items 3 and 4 of the exhibit attached to the plaintiff’s complaint. ■

The plaintiff maintains that the excavation he was required to do by his contract did not include removal of rock or ledge and he was entitled to compensation for its removal as an extra. He based the claim on the alleged promise of Fox and the president of Blauner.

The evidence shows that when the president of Blauner talked with the plaintiff just before the contract was signed there was no talk whatsoever of rock or rock ledge. The plaintiff made no inspection of the site before signing the contract. He admitted that he observed the notations on the plan revealing the presence of rock ledge before signing his contract with Blauner. In consequence, when the plaintiff signed his contract with Blauner he knew there was considerable rock and rock ledge in or near the locations where the trenches for piping were to be dug, and, further, he should have known from the plans that the rock ledge was above the bottoms of the trenches required by the plans for the installation of the plumbing and heating.

The facts further disclose that when th'e plaintiff started to work on September 25, 1937, Blauner had done considerable excavation on its own account and from it the plaintiff knew that Blauner had struck, some rock, but made no inquiry of Blauner as to what extent rock was present. I find that the plaintiff had equal opportunity to know of the presence of rock and rock ledge as had Blauner and there was no withholding of facts on the part of Blauner in reference to it or any misrepresentation concerning its presence. The surprising thing about the entire affair is that the plaintiff and Blauner both made bids for the work eách was to perform without determining in advance as to. what extent rock and rock ledge was present. Surely, the government itself practised no deceit upon either of them, as the plains testify.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Call v. G. M. Sader Excavating & Paving, Inc.
426 N.E.2d 798 (Ohio Court of Appeals, 1980)
Boomer v. Abbett
315 P.2d 924 (California Court of Appeal, 1957)
United States v. United States Gypsum Co.
67 F. Supp. 397 (District of Columbia, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
37 F. Supp. 968, 1941 U.S. Dist. LEXIS 3621, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-davies-v-blauner-const-co-mad-1941.