Rowe v. Inhabitants of Peabody

93 N.E. 604, 207 Mass. 226, 1911 Mass. LEXIS 671
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 3, 1911
StatusPublished
Cited by45 cases

This text of 93 N.E. 604 (Rowe v. Inhabitants of Peabody) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rowe v. Inhabitants of Peabody, 93 N.E. 604, 207 Mass. 226, 1911 Mass. LEXIS 671 (Mass. 1911).

Opinion

Sheldon, J.

The plaintiffs in the first action, hereinafter called the contractors, made in July, 1905, an agreement with the town of Peabody for the building of a tunnel from Suntaug Lake for a distance of fifteen hundred and fifty feet, and for the laying of certain pipe and the performance of other specified work. The contractors were to do all the work and supply the materials, so as to furnish to the town a completed tunnel with all its equipment, and were to be paid fixed prices for the different parts of what they were to do. They gave to the town a bond with the defendant in the second action as surety, conditioned for their faithful performance of the contract. The work was to be a timber supported tunnel, in which was to be constructed a masonry conduit thirty inches in diameter. The judge instructed the jury that the contract required as essential conditions “ the construction of a tunnel thirty inches in diameter by the use of timber props, roof supports and lagging. It was not a contract for constructing a suitable tunnel by whatever method should become available. ” He further ruled that •under the contract the officers acting for the town had no power “ to require the contractors, without their consent, to construct a tunnel by pneumatic process forty-eight inches in diameter. Such requirement would not be a mere variation in form and dimensions which the contractors must adopt, . . . but would be the substitution of a different contract.” Both of these rulings were made at the request of the contractors and apparently without objection by any party. They must now be taken [232]*232as correct. MacKnight Flintic Stone Co. v. New York, 160 N. Y. 72.

The contractors began to construct the tunnel as required by the contract, but presently found that owing to the nature of the soil there were serious difficulties, so great, they contended, as to make the construction in that way practically impossible, and certainly so great as to make it impracticable without a very large and disproportionate expense, such as they were not able to incur. Finally, on October 27, after some negotiations with the engineer and with the committee of the town, which so far as necessary will be referred to hereafter, the contractors sent to the committee a letter formally abandoning the contract. The town then completed the tunnel by what is called the pneumatic construction, which necessarily involved a cost of $47,805.12 in excess of the contract price. It was also necessary under this mode of construction to make the diameter of the tunnel forty-eight- inches instead of thirty inches. This mode of construction, as already pointed out, was essentially different from that originally contracted for ; but it does not seem to have been disputed that if not the only practicable method, it was at least the cheapest, most expeditious and most economical method by which the tunnel could be constructed.

The first contention made in behalf of the contractors is that the performance of their contract was impossible, or at least that it might have been found by the jury to be impossible, and that for this reason the contract was no longer binding upon the parties. They argue that a contract to build a particular tunnel of specified dimensions by a described method of construction is like a contract to ship goods by a certain steamer, or to sell potatoes to be raised upon certain specified land, or to account for the proceeds of butter to be made in a certain factory, or to build a bridge by the caisson method, — in each of which cases it has been held that the continued existence of the subject matter of the contract or the continued practicability of the essential details that are stipulated for is an implied condition of the continued validity of the agreement. Krell v. Henry, [1903] 2 K. B. 740. Chandler v. Webster, [1904] 1 K. B. 493. Howell v. Coupland, 1 Q. B. D. 258. Stewart v. Stone, 127 N. Y. 500. Buffalo & Lancaster Land Co. v. Bellevue Land & [233]*233Improvement Co. 165 N. Y. 247. Lovering v. Buckmountain Coal Co. 54 Penn. St. 291. This is the same principle which we recently considered in Hawkes v. Kehoe, 193 Mass. 419. It has frequently been applied in the courts. See, besides the cases already cited, Angus v. Scully, 176 Mass. 357; Butterfield v. Byron, 153 Mass. 517; Elliott v. Crutchley, [1903] 2 K. B. 476; McKenna v. McNamee, 15 Canada S. C. 311. But the question is as to the construction of the contract which the parties have made. This was recognized in most of the cases above cited. One who chooses to contract absolutely for the performance of a certain thing is not to be excused from such performance, in the absence of any other ground, merely because it either was origially or has since become impossible of execution. As was said by Blackburn, J., in the leading case of Taylor v. Caldwell, 3 B. & S. 826, 833, “ where there is a positive contract to do a thing, not in itself unlawful, the contractor must perform it or pay damages for not doing it, although in consequence of unforeseen accidents the performance of his contract has become unexpectedly burdensome or even impossible.” This also has been frequently declared by the courts. Jones v. St. John’s College, L. R. 6 Q. B. 115,127. Paradine v. Jane, Aleyn, 26. Atkinson v. Ritchie, 10 East, 530. Hills v. Sughrue, 15 M. & W. 253. Harvey v. Murray, 136 Mass. 377. Drake v. White, 117 Mass. 10. Stees v. Leonard, 20 Minn. 494. As was said by the present Chief Justice in Butterfield v. Byron, 153 Mass. 517, 520, “ the fundamental question ... is, What is the' true interpretation of the contract ? ”

In the case at bar the contract expressly stated that the nature of the underground plot had not been investigated, and that the committee of the town denied any responsibility for its character. The contractors also agreed by the twenty-third article of the contract to take all responsibility for the work and to bear all losses resulting on account of its nature or character or because of the nature of the ground being different from what was estimated or expected. The difficulties which it was asserted made the prescribed mode of construction impossible arose wholly from the character of the soil beneath the surface. They were warned that there might be such difficulties, and no one could say in advance that these might not be very great, or even in[234]*234superable. But they chose to make their agreement an absolute one, and the court cannot relieve them from the bargain which they saw fit to make. The case is well within the decisions. Boyle v. Agawam, Canal Co. 22 Pick. 381. Dermott v. Jones, 2 Wall. 1. Eastman v. St. Anthony Falls Water-Power Co. 24 Minn. 437. Thorn v. Mayor of London, L. R. 9 Ex. 163; L. R. 10 Ex. 112; 1 App. Cas. 120. There are three English cases, decided respectively in the House of Lords and in the Court of Appeal, which resemble closely the case at bar. Jackson v. Eastbourne Local Board, 2 Hudson, Building Contracts, (3d ed.) 67 ; Bottoms v. Lord Mayor of York, 2 Ibid. 220; and McDonald v. Mayor of Workington, 2 Ibid. 240.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. McClatchey
17 Mass. L. Rptr. 509 (Massachusetts Superior Court, 2004)
V & V Construction Co. v. McGonagle
42 Mass. App. Dec. 121 (Mass. Dist. Ct., App. Div., 1968)
La Vallee v. Cataldo
21 Mass. App. Dec. 150 (Mass. Dist. Ct., App. Div., 1961)
Boston Plate & Window Glass Co. v. John Bowen Co.
141 N.E.2d 715 (Massachusetts Supreme Judicial Court, 1957)
NEW ENGLAND FOUNDATION CO. INC. v. Commonwealth
100 N.E.2d 6 (Massachusetts Supreme Judicial Court, 1951)
Perreault v. Circle Club, Inc.
95 N.E.2d 204 (Massachusetts Supreme Judicial Court, 1950)
Baetjer v. New England Alcohol Co.
66 N.E.2d 798 (Massachusetts Supreme Judicial Court, 1946)
Conners v. Town of Tewksbury
63 N.E.2d 348 (Massachusetts Supreme Judicial Court, 1945)
Stern v. Ace Wrecking Co.
38 A.2d 626 (District of Columbia Court of Appeals, 1944)
Mohrmann v. Kob
182 Misc. 571 (New York Supreme Court, 1944)
City of Lawrence v. Stratton
45 N.E.2d 460 (Massachusetts Supreme Judicial Court, 1942)
Peninno v. Woodbridge
7 Mass. App. Div. 31 (Mass. Dist. Ct., App. Div., 1942)
United States ex rel. Davies v. Blauner Const. Co.
37 F. Supp. 968 (D. Massachusetts, 1941)
J. F. Fitzgerald Construction Co. v. Southbridge Water Supply Co.
23 N.E.2d 165 (Massachusetts Supreme Judicial Court, 1939)
Povey v. Colonial Beacon Oil Co.
200 N.E. 891 (Massachusetts Supreme Judicial Court, 1936)
G. M. Bryne Co. v. Town of Barnstable
191 N.E. 45 (Massachusetts Supreme Judicial Court, 1934)
Kennedy v. City of Boston
189 N.E. 809 (Massachusetts Supreme Judicial Court, 1934)
Morse v. City of Boston
157 N.E. 523 (Massachusetts Supreme Judicial Court, 1927)
Moreland v. Credit Guide Publishing Co.
152 N.E. 62 (Massachusetts Supreme Judicial Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
93 N.E. 604, 207 Mass. 226, 1911 Mass. LEXIS 671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rowe-v-inhabitants-of-peabody-mass-1911.