NEW ENGLAND FOUNDATION CO. INC. v. Commonwealth

100 N.E.2d 6, 327 Mass. 587, 1951 Mass. LEXIS 656
CourtMassachusetts Supreme Judicial Court
DecidedJuly 3, 1951
StatusPublished
Cited by12 cases

This text of 100 N.E.2d 6 (NEW ENGLAND FOUNDATION CO. INC. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NEW ENGLAND FOUNDATION CO. INC. v. Commonwealth, 100 N.E.2d 6, 327 Mass. 587, 1951 Mass. LEXIS 656 (Mass. 1951).

Opinion

Spalding, J.

By this petition brought under the provisions of G. L. (Ter. Ed.) c. 258, the New England Foundation Company, Incorporated, hereinafter called the petitioner, seeks to recover for materials furnished and labor performed pursuant to an extra work order issued by the -Commonwealth, hereinafter called the respondent, under a contract entered into between the petitioner and the respondent. The judge made a general finding for the respondent and reported the case to this court upon the agreement of the parties that, if the finding for the respond *588 ent on the single issue 1 involved was warranted as matter of law, the finding is to stand and judgment is to be entered for the respondent; otherwise judgment is to be entered for the petitioner in the sum of $69,843.70, with interest thereon from November 8, 1948.

The facts on which the judge’s general finding was based are contained in the report and numerous exhibits incorporated therein. The pertinent provisions of the contract and the circumstances attending its execution and performance are as follows: On August 12, 1947, the department of public works, hereinafter called the department, mailed to the petitioner and others a “Notice to Contractors” to the effect that the respondent was seeking bids for the construction of the foundations of the apron building which was to be erected at the Logan Airport in East Boston. Plans for the construction, and general and special provisions of the contract were issued. The plans and special provisions were prepared by engineers acting for the public building commission as provided by G. L. (Ter. Ed.) c. 6, § 62, inserted by St. 1947, c. 466, § 2.

The special provisions as appearing in their final form include the following specifications: “Piles 1. All piles shall be steel encased cast in place concrete piles of a safe working load capacity óf 20 tons. . . . Driving . . . The safe value of piles shall be determined by the following formula

P = 2 W^ H S + 0.1

Where P = safe load in pounds, W = weight of the striking part of the hammer in pounds, H = the fall in feet of the striking part of the hammer or stroke, S = average penetration per blow in inches under the last five blows. The Engineers may modify the required value of S on the basis of the load tests.” . This formula “is recognized and accepted in the engineering world as a proper formula for determining the theoretical safe value of piles.” As applied to the facts *589 of this case it is agreed that the value of P was 40,000 pounds, W was 5,000 pounds, H was 3 feet, and S was .65 inches. Thus, a pile driven with a penetration of 3.25 inches or less under the last five blows would be driven in accordance with the formula. It is also agreed that it is mathematically impossible to change the value of S without a resultant change in the value of P.

The contract provided that no pile casing or shell should be driven in the absence of the engineers. An accurate and detailed daily log of each pile was to be kept showing the depth to which each pile was driven, the penetration of each pile under a series of final blows of the hammer, and the “general driving characteristics.” Three copies of these logs were to be given to the engineers daily. Any casing or shell driven improperly or otherwise defective or rejected was to be corrected to the satisfaction of the engineers by removal and replacement of the same, or by driving an additional pile at no cost to the respondent.

In the special provisions relating to load tests it was provided that load tests of test piles of the type specified in the contract had been made adjacent to the site of the contract, that data from those tests were available for examination as information at the engineers’ office, 1 and that load tests would be made (apparently at the extractor’s expense) on three separate piles as selected by the engineers. The method for testing the piles' was set out in detail. Briefly summarized, it provided the maximum subsidence allowable over given periods of time when the piles should be loaded with twenty tons and later with thirty tons. 2 The contractor was to be allowed to drive a number of test piles to determine for himself what lengths and gouge of pile casings to order “to meet the foregoing requirements.” Such test piles, if satisfactory, were to be accepted by the respondent as piles in place for payment. It was also provided that, in addition to the load tests mentioned above, *590 additional piles might be tested on the order of the engineers. These additional tests were to be performed pursuant to an extra work order issued by the department and were to be paid for by the respondent at the rate of $750 per pile tested.

Elsewhere in the special provision's of the contract it was provided that contractors must include in their proposals a written statement of the details of the piles they proposed to use and the methods of driving and filling the same. The respondent reserved the right before awarding the contract to require any contractor to perform load tests on the piles he proposed to use in accordance with the above summarized specifications. The respondent would pay for such tests at the rate of $750 for each test. It was further stated, “The bid will be rejected if the piles fail to comply with the test load requirements ... of the Specifications.”

By a letter of September 22, 1947, the department requested the petitioner to drive three test piles in designated locations and to make load tests as a condition precedent •to the award of a contract. The letter further stated, “The driving of piles and tests thereof shall be done in accordance with these specifications for this work.” In response to an inquiry of the department, the petitioner on October 15, 1947, outlined by its letter the details of the method it proposed for load testing. The proposed method was acceptable to the engineers.

Following the receipt of the department’s letter the petitioner drove eight piles from which it selected three for purposes of testing. A driving record of these three piles was kept by the petitioner and the engineers, showing that the total penetration in inches for each pile under the last five blows of the hammer was less than the maximum allowable 3.25 inches. Load tests were then made on these three piles, and the results showed that two of the piles subsided less than the maximum allowable distance but that one of them did not meet the load test requirements of the specifications. The records of the driving of these three test piles and the results of the three load tests were examined by the petitioner, the department, and the engineers.

*591 Thereafter by letter dated October 27, 1947, the engineers wrote the department saying that the type of pile used by the petitioner could be used to develop the desired load carrying capacity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KRR Pembroke, LLC v. Global Data Systems, Inc.
21 Mass. L. Rptr. 183 (Massachusetts Superior Court, 2006)
Zortman v. Bildman
10 Mass. L. Rptr. 76 (Massachusetts Superior Court, 1999)
Shane v. WINTER HILL FEDERAL SAVINGS & LOAN ASS'N
492 N.E.2d 92 (Massachusetts Supreme Judicial Court, 1986)
N. J. Gendron Lumber Co. v. Great Northern Homes, Inc.
395 N.E.2d 457 (Massachusetts Appeals Court, 1979)
John J. Duane Realty Corp. v. Great Atlantic & Pacific Tea Co.
394 N.E.2d 964 (Massachusetts Appeals Court, 1979)
Rockland Credit Union v. Markola
54 Mass. App. Dec. 162 (Mass. Dist. Ct., App. Div., 1974)
Warren Bros. Co. v. Travi
53 Mass. App. Dec. 141 (Mass. Dist. Ct., App. Div., 1974)
Lexington Insurance v. Seaboard Air Line Railroad
182 F. Supp. 523 (D. Massachusetts, 1960)
Charles E. Burt, Inc. v. Seven Grand Corp.
163 N.E.2d 4 (Massachusetts Supreme Judicial Court, 1959)
M. DeMatteo Construction Co. v. Commonwealth
156 N.E.2d 659 (Massachusetts Supreme Judicial Court, 1959)
Botaish v. Romanos
153 N.E.2d 753 (Massachusetts Supreme Judicial Court, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
100 N.E.2d 6, 327 Mass. 587, 1951 Mass. LEXIS 656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-foundation-co-inc-v-commonwealth-mass-1951.