Cavanagh v. Tyson, Weare & Marshall Co.

116 N.E. 818, 227 Mass. 437
CourtMassachusetts Supreme Judicial Court
DecidedJune 26, 1917
StatusPublished
Cited by19 cases

This text of 116 N.E. 818 (Cavanagh v. Tyson, Weare & Marshall Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cavanagh v. Tyson, Weare & Marshall Co., 116 N.E. 818, 227 Mass. 437 (Mass. 1917).

Opinion

Pierce, J.

These are cross actions of contract arising out of the same transaction. They were tried together before an auditor and before a jury.

The plaintiff Cavanagh declares upon two counts. In the first count he alleges the making of a contract between the plaintiff and the defendant on October 23,1912, for the furnishing and driving of spruce piles for the foundation of the Boston Fish Market building on Pier No. 6, South Boston. In this count the plaintiff alleges in substance that he was induced to enter into this contract by misrepresentations made to him by officers of the defendant company; that relying upon such representations he performed [440]*440a part of the work covered by the contract and continued at work until it was impossible to proceed further by reason of the soil in which the piles were to be driven being of a different character from what it was represented to be by the defendant. The plaintiff further alleges four breaches of the contract on the part of the defendant company, the first of which, namely, “that the defendant agreed to make certain excavations, which it refused and neglected to do,” is the only one argued. He then alleges that because of these breaches of the contract on the part of the defendant company, he has been forced to cease work under said contract and has suffered damages which he seeks to recover in this action. The second count for the same cause of action was amended before the trial in accordance with the terms of the auditor’s report, and now consists of an account for labor and material furnished by the plaintiff to the defendant to the amount of $14,323.12. The defendant’s answer is a general denial.

The plaintiff’s claim in the second action is set forth in a declaration containing two counts. The first alleges the making of a contract between the plaintiff and the defendant, Cavanagh, on November 22, 1912, under the terms of which the defendant undertook to furnish and drive all the piles required for the foundations for two buildings on the Boston Fish Market Pier in South Boston; the abandonment of the contract by- the defendant and an overpayment by the plaintiff to the defendant at the time he abandoned the contract; a specification of the damage which it alleges it sustained in completing the work, and a claim for the penalty provided by the contract in case of delay. The second count for the same cause of action is on an account annexed. The answer of the defendant was a general denial. And he further answered that the contract “was entered into under a mutual mistake of fact in the belief and understanding by both parties that the fill where the plaintiff [in the first action] was to drive piles under said contract was a mud and dirt fill, whereas in fact, unknown to both parties, said fill had been made to a large extent with stone rip-rap, boulders, concrete, brick and other debris, and was unsuitable for driving piles; wherefore this defendant says that in equity he ought to be absolutely and unconditionally relieved against the plaintiff’s claim and cause of action.”

Under the bid and acceptance, Cavanagh began work on Novem[441]*441ber 5, 1912, and continued to perform work under that contract, or under it as modified by the printed formal contract dated November 12 and executed November 22, 1912, until February 5, 1913. On the 'last named day he wrote the company “I decline to further attempt to carry out my contract with you for furnishing and driving piles for the two buildings on Pier No. 6, South Boston, owing to conditions with which you are fully familiar. . . .” and thereupon ceased work and has done nothing further toward the completion of the contract.

At the trial before the auditor and, before the jury Cavanagh contended, and introduced evidence by which he sought to prove, that the original contract on the bid and acceptance as well as the written contract dated November 12 were void, because of fraud or because of mutual mistake; that all the contracts were abandoned by both parties; and that the contract of November 12, if ever in force, was broken by the company by its failure to make payments to Cavanagh and to excavate as it was required to do by the terms of the contract. At the close of all the evidence the presiding judge ruled that “there was no evidence to warrant submitting the case to the jury on the questions of mistake, abandonment, and breach of contract. . . .” The jury answered in the affirmative the question “Did Cavanagh waive breaches of the contract, if any, in the matter of payments?” The judge thereupon ordered a verdict for the defendant in the first case and for the plaintiff in the second case, and reported the cases to the Supreme Judicial Court upon the following terms and conditions: “ If the rulings made and directions and instructions given are correct, judgments are to be entered upon the verdicts as rendered. If upon all of the evidence the ruling of the court directing the verdicts was wrong, the verdicts are to be set aside and judgment is to be entered for the plaintiff in the case of Cavanagh v. Tyson, Weare & Marshall Co. in the sum of $14,323.12, with interest thereon from the date of the writ and in the case of Tyson, Weare & Marshall Co. v. Cavanagh, judgment is to be •s entered for the defendant. If the court erred in his rulings upon the admission or exclusion of evidence or in his instructions to the jury upon the issue which was submitted, then a new trial is to be had. If the court erred in his ruling upon the matter of variance between the proof and the pleadings in the [442]*442second case, then a new trial is to be had in the second case.” We shall consider the contentions of Cavanagh in the order of his argument.

Upon the question of fraud or mistake the material facts are not in dispute, and are in substance that the Commonwealth of Massachusetts previous to September, 1912, had made a lease of Pier No. 6 to the Boston Fish Market Corporation for the purpose of building a fish market thereon; that in September, 1912, the Fish Market Corporation awarded a contract to the defendant and plaintiff company to build two buildings upon said pier called buildings No. 1 and No. 2; that the company previous to September 26, 1912, had sent to the plaintiff, in common with other pile drivers, a postal card requesting bids on the piling for the Boston Fish Market building with the statement, “plans and specifications at our office;” that bids were wanted before September 27, 1912; that the plaintiff had a conversation with Marshall of the. defendant company; that the plaintiff was told by Marshall that the defendant could get it done for $6.20 per pile, that if he wanted it at that price he could have it; that the plaintiff stated he “wanted to look into the job a little more,” that he wanted to go down and see the architects; that Marshall said “Go ahead down and see them; you know who they are; they are on the plans;” that the plaintiff then went to the office of the architects, Monks and Johnson; that Monies told the plaintiff to go to H. S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Beaudette, Inc. v. Sentry Insurance a Mutual Co.
94 F. Supp. 2d 77 (D. Massachusetts, 1999)
Davis v. Dawson, Inc.
15 F. Supp. 2d 64 (D. Massachusetts, 1998)
LaFleur v. C.C. Pierce Co.
496 N.E.2d 827 (Massachusetts Supreme Judicial Court, 1986)
Brown-McKee, Inc. v. Western Beef, Inc.
538 S.W.2d 840 (Court of Appeals of Texas, 1976)
Lau v. Silva
55 Mass. App. Dec. 13 (Mass. Dist. Ct., App. Div., 1974)
Gilmore v. Acme Taxi Co.
212 N.E.2d 235 (Massachusetts Supreme Judicial Court, 1965)
Ralph Richard Constr. Inc. v. Standard Accident Insurance
233 F. Supp. 785 (D. Massachusetts, 1964)
NEW ENGLAND FOUNDATION CO. INC. v. Commonwealth
100 N.E.2d 6 (Massachusetts Supreme Judicial Court, 1951)
Aldrich v. Travelers Insurance
56 N.E.2d 888 (Massachusetts Supreme Judicial Court, 1944)
Roberts v. Hayes
1 N.E.2d 711 (Appellate Court of Illinois, 1936)
Kennedy v. City of Boston
189 N.E. 809 (Massachusetts Supreme Judicial Court, 1934)
John J. Bowes Co. v. Inhabitants of Milton
151 N.E. 116 (Massachusetts Supreme Judicial Court, 1926)
Martiniello v. Bamel
150 N.E. 838 (Massachusetts Supreme Judicial Court, 1926)
Stadmiller v. Schirmer
248 Mass. 244 (Massachusetts Supreme Judicial Court, 1924)
Costello v. Sykes
172 N.W. 907 (Supreme Court of Minnesota, 1919)
Inland Steel Co. v. Lambert
118 N.E. 162 (Indiana Court of Appeals, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
116 N.E. 818, 227 Mass. 437, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cavanagh-v-tyson-weare-marshall-co-mass-1917.