John J. Bowes Co. v. Inhabitants of Milton

151 N.E. 116, 255 Mass. 228, 1926 Mass. LEXIS 1109
CourtMassachusetts Supreme Judicial Court
DecidedMarch 4, 1926
StatusPublished
Cited by18 cases

This text of 151 N.E. 116 (John J. Bowes Co. v. Inhabitants of Milton) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John J. Bowes Co. v. Inhabitants of Milton, 151 N.E. 116, 255 Mass. 228, 1926 Mass. LEXIS 1109 (Mass. 1926).

Opinion

Crosby, J.

This is a suit in equity brought to compel the return to the plaintiff of a certified check for $2,500, previously deposited with the defendants. The case was referred to a master who has filed a report. At the annual town meeting held in Milton in March, 1923, the appointment of a committee was authorized to build a school house to be known as the Tucker School. At the meeting the town appropriated $240,000 for the purpose of constructing and furnishing the building, which sum was to be raised by an issue of bonds.

The committee employed a firm of architects, and invitations were sent to certain firms, not including the plaintiff who later asked to be allowed to submit a bid and its request was complied with. The invitation so issued contained the following provision: “As security for giving the contract and bond, a certified check on a Boston Bank for Two Thousand Five Hundred Dollars ($2,500.00), payable to the Town of Milton, must be left with the proposal.” On April 23, 1923, the last date fixed in the invitations for the submission of bids, the plaintiff filed a written proposal with the committee in which it offered to construct the building in accordance with the plans and specifications for $201,784, and also offered to allow $2,600 for the old school house on the lot. With the proposal the plaintiff, in accordance with the invitation, deposited a certified check for $2,500 payable to the order of the town. The plaintiff was the lowest bidder; the next lowest bid was about $20,000 higher than that of the plaintiff. The building committee, after opening the bids, found that the lowest bid together with the amounts required to construct and complete the building was in excess of the amount appropriated by the town. All the bids were taken under advisement and they with the checks accompanying them were placed in the safe of the'School committee. None of the bids was accepted at that time.

It was found necessary to reduce the costs so that the expense of the building would come within the appropriation. [231]*231With that end in view the architects were instructed to make certain changes in the plans and specifications. The architects made said proposed changes, which were submitted to the plaintiff and other bidders. The plaintiff and the architect went over these changes and it was agreed by them that the allowances for them amounted to $15,164, so that by the changes in the original plans and specifications the amount of the plaintiff’s bid would be reduced to $184,020.

Thereafter the plaintiff was notified by the architects there would be a meeting of the committee at the office of the architects on April 30,1923, at 4:30 p.m. ; at this meeting there were present all the members of the committee, Bowes, the president, and Kelly, the treasurer, of the plaintiff company, and various questions relating to the contract, including the time when the building should be completed were discussed. The proposed changes in the original specifications were on typewritten sheets which had been prepared by the architects and entitled “‘Addenda’ — ‘to be considered a part of the plans and specifications of the Tucker School, Milton, Mass. ’ ” It is found that these sheets stated accurately the changes that had been agreed upon between Hopkins, one of the architects, and Bowes at their conferences. These changes were approved by the committee.

The master found that it was the understanding of the committee and of the plaintiff that the latter had modified its original proposal and submitted an amended proposal to perform the work required by the original plans and specifications as modified by the changes in the sheets marked “Addenda” above referred to, for the sum of $184,020; that the original proposal had not been rejected, but that the proposal of the plaintiff to erect the building for $184,020 was an amendment to its original proposal and was so understood by both parties. After the preliminary conference was ended, Bowes and Kelly were requested to retire to another room while the committee conferred. The committee then voted unanimously to award the contract to the plaintiff; thereafter Bowes and Kelly returned to the room and were told that the committee had awarded the contract to the plaintiff, and Bowes appeared pleased [232]*232at the action of the committee. It was agreed that the fulfilment bond should be in the sum of $50,000.

The architects having previously prepared the contracts to be signed, all the members of the committee executed two copies thereof. It is found that ‘ ‘ Mr. Bowes testified that he was satisfied with the terms of the contract, but Mr. Kelly did not go as far as that in his evidence.” The two copies were handed by the architect to Bowes; about this time Kelly stated that he desired “to check up on his figures,” he and Bowes having learned shortly before on the same day their bid was much lower than that of their nearest competitor. They took the contracts and specifications and went away. The next day they discovered an error in figuring whereby they had omitted two items in their bid aggregating $7,174. The next day Bowes notified the architect that the plaintiff had made a mistake and would have to increase its bid by $16,800, “the total of the mistakes,” which would make the total sum $200,820, and that he would be unable to sign the contract. The master found that “The only inference that can be made from these facts is that the Bowes Company repudiated its proposal to build the Tucker School. It added to its figures after the mistakes in compilation had been corrected more than $9,600. I find that such action on the part of the Bowes Company is not consistent with good faith and honorable conduct.”

It appears that the plaintiff made no objection to any of the terms of the contract which were fully agreed upon, other than the price, previously to the bringing of this suit.

The findings of the master show that the plaintiff’s written offer and the defendant’s acceptance of that offer communicated to the plaintiff constituted a binding preliminary contract between the parties.

The preliminary agreement in connection with which the check was deposited was separate and distinct from the formal contract to erect the building. If the plaintiff had signed the formal contract, the terms of the preliminary contract would have been performed by it, and it would have been entitled to the return of the check. In other words, if the plaintiff had entered into the formal contract and given [233]*233the required bond the terms of the preliminary contract would have been fully performed.

The contract as signed and tendered to the plaintiff contained all the terms on which the proposal had been submitted and had been agreed to by the parties. The changes in the specifications and included in the “Addenda” were agreed upon by the architect and the plaintiff. The master found that the original contract remained in force as a proposal modified by the consent of the parties, and that the changes in the proposal were made to meet corresponding changes in the plans and specifications, including the provision that the work should be completed in twelve months. The bond required by G. L. c. 149, § 29, to be given by the contractor is to be considered by implication as a part of the understanding of the parties even if not expressly referred to in the formal contract tendered for the erection of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R.K. Wheeler, LLC v. Moran Foods, Inc.
18 Mass. L. Rptr. 77 (Massachusetts Superior Court, 2004)
Salisbury Nursing Home, Inc. v. Healy
1988 Mass. App. Div. 190 (Mass. Dist. Ct., App. Div., 1988)
Scirpo v. McMillan
247 N.E.2d 368 (Massachusetts Supreme Judicial Court, 1969)
Poley-Abrams Corp. v. Chaney & James Construction Co.
220 F. Supp. 401 (D. Massachusetts, 1963)
Russell & Pugh Lumber Company v. United States
290 F.2d 938 (Court of Claims, 1961)
FAIR LAWN BD. OF EDN. v. Fair Lawn Plaza Taxi, Inc.
150 A.2d 793 (New Jersey Superior Court App Division, 1959)
Mayor of Baltimore v. DeLuca-Davis Construction Co.
124 A.2d 557 (Court of Appeals of Maryland, 1956)
M. F. Kemper Construction Co. v. City of Los Angeles
235 P.2d 7 (California Supreme Court, 1951)
Rushlight Automatic Sprinkler Co. v. City of Portland
219 P.2d 732 (Oregon Supreme Court, 1950)
Devore v. Good
72 N.E.2d 405 (Massachusetts Supreme Judicial Court, 1947)
Commonwealth v. Albert
40 N.E.2d 21 (Massachusetts Supreme Judicial Court, 1942)
Metropolitan Pipe & Supply Co. v. D'Amore Construction Co.
35 N.E.2d 211 (Massachusetts Supreme Judicial Court, 1941)
United States v. Conti
119 F.2d 652 (First Circuit, 1941)
Franklin A. Snow Co. v. Commonwealth
22 N.E.2d 599 (Massachusetts Supreme Judicial Court, 1939)
Jones v. Jones
7 N.E.2d 1015 (Massachusetts Supreme Judicial Court, 1937)
Daddario v. Town of Milford
5 N.E.2d 23 (Massachusetts Supreme Judicial Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
151 N.E. 116, 255 Mass. 228, 1926 Mass. LEXIS 1109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-j-bowes-co-v-inhabitants-of-milton-mass-1926.