Long v. Inhabitants of Athol

82 N.E. 665, 196 Mass. 497, 1907 Mass. LEXIS 1133
CourtMassachusetts Supreme Judicial Court
DecidedNovember 26, 1907
StatusPublished
Cited by68 cases

This text of 82 N.E. 665 (Long v. Inhabitants of Athol) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Long v. Inhabitants of Athol, 82 N.E. 665, 196 Mass. 497, 1907 Mass. LEXIS 1133 (Mass. 1907).

Opinion

Sheldon, J.

The defendant appealed from the interlocutory order overruling its demurrer to the bill, and its counsel have discussed some of the questions naturally arising thereon. As however all these questions are raised, and perhaps more advantageously for the defendant, upon the master’s report and the exceptions thereto, and as the appeal has not been argued specifically, it need not be considered at any great length. We think it plain that the bill as amended sets forth a good cause of action. It is drawn with a double aspect, seeking to obtain a cancellation of the contract of the plaintiffs with the defendant, first upon the ground that it was fraudulently obtained from the plaintiffs by giving to them as a basis for the proposed contract erroneous estimates of the work to be done, which largely understated the amount thereof, and keeping from the files of the town clerk of Athol and concealing from the plaintiffs the maps, drawings, profiles and specifications in accordance with which the contract was to be and in fact was made; and secondly upon the ground that the contract was made under a mutual mistake of both parties arising from the fact that the estimates upon which the plaintiffs made their bid and upon the faith of which they entered into the contract, which estimates were made by an engineer employed by the defendant for that purpose, and were given to the plaintiffs by the defendant as correct, were erroneous and materially underestimated the amount of the work tó be done. If the proof came up to the averments of the bill on either of these grounds it would entitle the plaintiffs to relief. It would be enough if either of the grounds alleged was made out. Redgrave v. Hurd, 20 Ch. D. 1. Davies v. London & Provincial Ins. Co. 8 Ch. D. 469. Newbigging v. Adam, 34 Ch. D. 582. Trail v. Baring, 4 DeG., J. & S. 3168, affirming S. C. 4 Giff. 485. Rawlins v. Wickham, 3 DeG. & J. 304. Daniel v. Mitchell, 1 Story, 172. Goodwin v. Massachusetts Loan & Trust Co. 152 Mass. 189. Motherway v. Wall, 168 Mass. 333. Keene v. Demelman, 172 Mass. 17. Boles v. Merrill, 173 Mass. 491. Paine v. Upton, 87 N. Y. 327. Winnipisseogee Lake Co. v. Perley, 46 N. H. 83. The bill could be maintained both for a cancellation of the contract and for the recovery of what[501]*501ever money might be incidentally necessary to afford full relief. Rackemann v. Riverbank Improvement Co. 167 Mass. 1. Davis v. Peabody, 170 Mass. 397. Weeks v. Currier, 172 Mass. 53. Franklin v. Greene, 2 Allen, 519. Nor does the bill show upon its face that the plaintiffs had such means of ascertaining the real facts or were guilty of such gross negligence in relation thereto as to deprive them of the right to relief for this reason. Conner v. Welch, 51 Wis. 431. The statement of Jessel, M. R. upon this subject in Redgrave v. Hurd, 20 Ch. D. 1, was quoted and followed in Smith v. Land & House Property Corp. 28 Ch. D. 7, 17, and in Karberg’s case, [1892] 3 Ch. 1, 13. Nor does the bill show that the plaintiffs were guilty of such loches as to lose their right to relief. Their right to cancellation depended upon the refusal of the defendant to correct the mistake, so far as the bill rested upon that ground; Keene v. Demelman, 172 Mass. 17, 23 ; and the bill seems to have been brought promptly after the discovery of the mistake and the defendant’s refusal to rectify it. Rawlins v. Wickham, 3 DeG. & J. 304. It does not appear by the bill that the defendant cannot as to all essential matters be put substantially into its original position under the rule of Thayer v. Turner, 8 Met. 550, and Snow v. Alley, 144 Mass. 546. See Drohan v. Lake Shore & Michigan Southern Railroad, 162 Mass. 435 ; Rackemann v. Riverbank Improvement Co. 167 Mass. 1, 4, 5. We cannot doubt that the demurrer was rightly overruled. The cases which hold that without a cancellation of the contract the plaintiffs would be held to performance in conformity to its terms and could not set up the antecedent error are beside the point, and need not be considered.

It sufficiently appears by the master’s report that, although no fraud was practised upon the plaintiffs, their contention that the contract was entered into under a mutual mistake caused by the error of the engineer employed by the defendant to make the estimate that was furnished by the defendant to the plaintiffs and other contractors for them to base bids upon, was proved. The plaintiffs had access also to correct profile maps and drawings and to printed specifications; and it would have been possible for a skilled engineer, by correctly scaling these plans, to ascertain and correct the mistakes made in the estimate furnished by the defendant to the plaintiffs and other [502]*502bidders. It is manifest however and, as we understand, is not disputed, that the mistakes could have been discovered only by one skilled in such matters, and only by careful and accurate scaling and processes of computation. The master has found that the officers of the defendant acted in good faith in furnishing this estimate, and believed that the information given therein was at least approximately correct, and were ignorant that any material errors had been made in compiling it; that the mistakes made were unintentional and that all parties were ignorant of any serious discrepancies in the estimate, but that the plaintiffs were not grossly negligent in not examining the plans more minutely, and had the right to assume that the engineer’s estimate was at least approximately correct, and to rely thereon in making up and submitting their bids. He also has found that the statements of this estimate were not even approximately correct; that the amount of excavation required of the plaintiffs was so much in excess of that shown by the erroneous estimate that the plaintiffs were justified in fact in refusing to proceed further with their contract.

Upon these findings taken by themselves, under the circumstances which appear, here, it is manifest, upon the cases already referred to, that the plaintiffs are entitled to the relief which they seek, unless this should be refused to them by reason of some of the specific objections of the defendant, or unless it should appear, upon some of their exceptions, that there has been material error on the part of the master; and we proceed to consider these questions.

The defendant contends that there was no right of cancellation by reason of the issuing of the paper containing the inaccurate estimates, because this was put forth in good faith and its inaccuracy was unknown and unsuspected by the defendant’s officers until after the plaintiffs had begun their work, and because the plaintiffs in their contract expressly covenanted to do the work in strict accordance with the maps, drawings, profiles and specifications prepared therefor and on file in the office of the town clerk, ... all of which are to be considered as part and parcel of these presents, and to be construed therewith,” and further in the same contract in express terms admitted and agreed “ that the amounts and quantities of materials to be furnished and work to [503]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Francis v. Pinault
7 Mass. L. Rptr. 196 (Massachusetts Superior Court, 1997)
KVS Information Systems, Inc. v. Town of Tisbury
753 F. Supp. 1020 (D. Massachusetts, 1990)
Farnum v. Silvano
540 N.E.2d 202 (Massachusetts Appeals Court, 1989)
Ross v. Friedman
495 N.E.2d 321 (Massachusetts Appeals Court, 1986)
Massachusetts General Hospital v. City of Revere
434 N.E.2d 185 (Massachusetts Supreme Judicial Court, 1982)
D. Federico Co., Inc. v. Commonwealth
415 N.E.2d 855 (Massachusetts Appeals Court, 1981)
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.
205 N.E.2d 239 (Massachusetts Supreme Judicial Court, 1965)
Bruni v. Andre
162 N.E.2d 52 (Massachusetts Supreme Judicial Court, 1959)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Bouchard v. Bouchard
48 N.E.2d 161 (Massachusetts Supreme Judicial Court, 1943)
Peninno v. Woodbridge
7 Mass. App. Div. 31 (Mass. Dist. Ct., App. Div., 1942)
Belezarian's Case
31 N.E.2d 4 (Massachusetts Supreme Judicial Court, 1940)
Corthell v. Great Atlantic & Pacific Tea Co.
291 Mass. 242 (Massachusetts Supreme Judicial Court, 1935)
City of Wheeling v. John F. Casey Co.
74 F.2d 794 (Fourth Circuit, 1935)
Kennedy v. City of Boston
189 N.E. 809 (Massachusetts Supreme Judicial Court, 1934)
Kidder v. Greenman
187 N.E. 42 (Massachusetts Supreme Judicial Court, 1933)
Graustein v. Dolan
185 N.E. 489 (Massachusetts Supreme Judicial Court, 1933)
England v. State
246 N.W. 628 (South Dakota Supreme Court, 1933)
Gold Brand Confectionery, Inc. v. Dimick
177 N.E. 547 (Massachusetts Supreme Judicial Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
82 N.E. 665, 196 Mass. 497, 1907 Mass. LEXIS 1133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/long-v-inhabitants-of-athol-mass-1907.