England v. State

246 N.W. 628, 61 S.D. 132, 1933 S.D. LEXIS 4
CourtSouth Dakota Supreme Court
DecidedFebruary 6, 1933
DocketFile No. 7230.
StatusPublished
Cited by13 cases

This text of 246 N.W. 628 (England v. State) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
England v. State, 246 N.W. 628, 61 S.D. 132, 1933 S.D. LEXIS 4 (S.D. 1933).

Opinions

WARREN, J.

The plaintiffs are contractors, and some time prior to May, 1929, examined certain plats, specifications, and' plans relating to certain highway work specified in a notice to contractors to 'be performed on State Trunk Highway No. 63 near the Cheyenne River bridge. The notice to contractors provides, among other things, for certain excavations, to wit: “110,067 C. Y. as Unclassified, 127,169 C. Y. Stas. Overhauling of Excavation, and, 144 C. Y. Structure Excavation.” Thereafter the plaintiffs became the successful 'bidders and entered into a contract with the defendant state the latter' part of May of said year, in which it was agreed that they were to receive a certain stipulated price per cubic yard for common excavation and a certain price per cubic yard for shale or loose rock excavation, but the contract is silent as to'the price for solid rock formation excavation. The plaintiffs state that the cross-section of the blueprints show an area by lines and figures to consist of 96,303 cubic yards of common excavation and 10,387 cubic yards of shale or loose rock excavation. The *133 complaint and the various exhibits are before us for the purpose of deciding whether or not the complaint states facts sufficient to constitute a cause of action, it having been demurred to upon that specific ground.

The complaint is quite specific in its charges and alleges in a chronological way the various steps by both parties before entering into the contract and the things that took place after the contract had been executed and' while proceeding with their work. They allege that while performing the excavation large bodies of solid rock were encountered and that the plats, plans, specifications, and contract did not contemplate the encountering of such a substance; that on encountering solid rock, the engineers in charge for the state were notified of this fact and that an additional expense would be incurred in removing this class of excavation. The state engineers countered by contending that the plaintiffs must proceed with their work, that they were bound by the contract, and1 that they would -be compelled to proceed without any additional compensation, and called the plaintiffs’ attention to the fact that there were certain binding specifications for road and bridge work embodied in the contract which would make it imperative that they proceed with the work. The South Dakota Standard Specifications for Road and Bridge Work on State Trunk Highways urged by the defendant as controlling are section 15, par. 16; section 40; and section 42.

The controversy between the plaintiffs and defendant, the state, from the allegation as disclosed by the complaint, is in respect to the necessary excavations which had to be made to complete the contract. The plaintiffs seek to recover the reasonable value for this excavation of 87,560 cubic yards of common excavating at 18 cents per cubic yard, and 70 cents per cubic yard for 22,487 cubic yards of loose rock excavation, and also $2 per cubic yard for 2,390 cubic yards of solid rock excavation, increasing the amount of recovery to $36,281.70 instead of $26,984.08 as allowed and paid for by the defendant.

From the allegations in the complaint it is apparent that the plaintiffs obligated themselves to complete the project for 24 cents per cubic yard, regardless of the kind, character, or classification of such excavation, and that they have never appealed to, com *134 plained ¿f, or objected to proceeding- with their contract at any time during its existence, to the state highway commission.

There are allegations to the effect that complaint was made to the district engineer and the state highway engineer, but it will be readily seen from an inspection of the complaint that the parties to the contract were not notified and that the engineers had no authority to modify the existing contract.

Section 40 of South Dakota Standard Specifications and a part of the contract provides as follows: “ * * * Should any such corrections or modifications of the plans or specifications require a different quality or class of work than that upon which the unit prices in the proposal are based, or if the modifications or corrections are required in parts of the work partially completed and such modifications result in an increased cost to the contractor, a ‘fair and equitable amount in settlement shall be agreed upon before the work is performed, in writing, between the contractor and the commission.’ * * * ”

It will thus -be .seen from the wording of the foregoing section that it is expressly provided that in the event of an)' correction or change where the work had been partially completed and where it would be necessary to modify and make changes which would be of any increased cost to the contractor that a “fair and equitable amount in settlement shall be agreed upon before the work is performed, in writing, between the contractor and the commission.”

This provision is mandatory and was one of the elements in the contract between the parties, and had the plaintiffs so desired they could have availed themselves of the opportunity and obtained the benefits of that provision of the contract by submitting to the commission that a modification of the contract was necessary on account of the extra cost in completing the excavation which had been encountered after partially completing the contract.

The plaintiffs did not rescind promptly upon discovering the facts, and are therefore not now entitled to rescind, having failed to -comply with the rules governing rescission contained in section 906 of the 1919 S. D. Revised Code.

In considering plaintiffs’ right to recovery for additional or extra work, we are met with the provisions of the contract and section 42 of the specifications, which provides that the contractor *135 shall perform extra work for which there is no quantity and price included in the contract, and that when such extra work is deemed necessary and desirable, the extra work will be paid for at a unit price or lump sum to be agreed upon previously in writing between the contractor and commission, and in case the price or sum cannot be agreed upon by both parties, or if the method of payment is impracticable, the commission may order the contractor to do such work on a force account basis. In this case the complaint fails to show any agreement in writing which was contemplated by the parties to the contract. The plaintiffs are clearly foreclosed from asserting any right to extra work under the express provision of the specifications. The authority to perform such work must be given in the manner and in accordance with the terms of the contract, for it is expressly provided that the extra work to be done and the price for said work must be expressed and given in writing in order to bind the parties to the contract. See McQuillan on Municipal Corporations, § 1946, p. 4183; see, also, Wilson v. Salt Lake City, 52 Utah, 506, 174 P. 847.

The plaintiffs contend that they were misled by certain drawing's and plans prepared by the engineer for the state highway department and which, according to the expressed stipulations, were not prepared as a guide to prospective bidders, but were mere esimates for the use of the state highway commission in comparing bids.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northern Improvement Co. v. South Dakota State Highway Commission
25 Cont. Cas. Fed. 82,625 (South Dakota Supreme Court, 1978)
Dave Gustafson & Co. v. S.D. Highway Commission
225 N.W.2d 594 (South Dakota Supreme Court, 1975)
State Highway Commission v. J. H. Beckman Construction Co.
171 N.W.2d 504 (South Dakota Supreme Court, 1969)
Darnall v. State
108 N.W.2d 201 (South Dakota Supreme Court, 1961)
Alexander v. State
57 N.W.2d 121 (South Dakota Supreme Court, 1953)
State Highway Commission v. Green-Boots Const. Co.
1947 OK 221 (Supreme Court of Oklahoma, 1947)
Griffis v. State
11 N.W.2d 138 (South Dakota Supreme Court, 1943)
Kansas City Bridge Co. v. State
250 N.W. 343 (South Dakota Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
246 N.W. 628, 61 S.D. 132, 1933 S.D. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/england-v-state-sd-1933.