State Highway Commission v. J. H. Beckman Construction Co.

171 N.W.2d 504, 84 S.D. 337, 1969 S.D. LEXIS 116
CourtSouth Dakota Supreme Court
DecidedOctober 22, 1969
DocketFile 10479
StatusPublished
Cited by5 cases

This text of 171 N.W.2d 504 (State Highway Commission v. J. H. Beckman Construction Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Highway Commission v. J. H. Beckman Construction Co., 171 N.W.2d 504, 84 S.D. 337, 1969 S.D. LEXIS 116 (S.D. 1969).

Opinion

RENTTO, Judge.

In this action the state seeks a declaration of rights and duties under a contract awarded after competitive bidding for the building of a highway bridge, the terms of which were altered during the course of construction by agreement of the parties. It is principally interested in the legality of additional compensation allowed the contractor under the modification.

The State of South Dakota accepted the bid of J. H. Beckman Construction Company for the building of the bridge over the Grand River near Mobridge, South Dakota, and entered into a written contract with it for such construction. While the bridge was being built Mr. Beckman was killed in an airplane mishap. The assets of his company, including this contract, were sold to the other defendant G. H. Lindekugel & Sons. The state approved the assignment of the contract to Lindekugel and its assumption of responsibility for completion of the structure.

The superstructure of the bridge was to be supported by two sills, one on either bank of the river, and 31 bents or piers between the sills, in the river. These were to be of steel and reinforced concrete construction. The design of the bents had steel piling driven into the bed of the stream until required firmness was encountered. These supported the concrete footings on which rested the vertical concrete columns poured around the steel pilings. Some of the footings were planned to be built in the river bed and others above it.

The construction of the piers necessitated the use of a cofferdam. In the testimony this is described as a watertight enclosure made of interlocking steel segments driven into the stream bed, in the area where a pier was to be constructed. It was large enough so that when it was excavated and unwatered a pier could be built within it. Apparently after the construction was completed the cofferdam was disassembled and utilized in the building of another bent.

*339 To provide a working area for use in placing the cofferdam and building the structure within it, Beckman utilized a causeway which was extended into the river as the work progressed. This was made by dumping dirt and rocks into the river until the upper surface of the accumulation was above water level and large enough for its purposes. In effect it was a roadway. In some instances contractors doing this kind of work use a floating barge as their working area. The contract did not prescribe the method to be used in this case. That was the choice of the party doing the work.

By utilizing the causeway it was necessary for the contractor in building the piers to sink the cofferdam through the causeway and into the bed of the stream. In order to construct the pier within it, it had to excavate material that had been placed into the causeway and in those situations where the footing was built in the river bed, materials in their natural position, and remove therefrom any water that had seeped into the enclosure. The construction of the piers in descending order from the highest numbered one, proceeded without serious incident until work was being done on bent 22. The cofferdam collapsed while it was being excavated and unwatered. There was some evidence that this was contributed to by a higher than anticipated level of water in the river occasioned by raising the pool level in the Oahe Reservoir.

At the request of the contractor a meeting was held at which this situation and problems arising therefrom were discussed by the contractor and its representatives with representatives of the Department of Highways. This was on May 3, 1963. It was there agreed that the elevation of the footing for bents 19' to 4, both inclusive, would be raised a distance of ten feet from the plan shown elevation, except two of them, which would be raised six feet. After this the parties executed written contract change orders embodying the modifications arrived at in their meeting.

One of these provides that excavation below the plan shown bottom of footing elevations, or bottom of footing elevations as *340 modified, would be paid for at 2 1/2 times the contract unit price paid for structure excavation which was $45 per cubic yard. Another stated that these structure excavations would be measured by the amount of rock used to fill the cofferdams below the footing lines using an agreed conversion factor. In other words, the contractor rather than building a form for the bottom of the concrete footing would utilize rock placed at the bottom of the cofferdams for this purpose. This was authorized for bents 19 — 4, both inclusive, and ratified as to bents 27 — 20, both inclusive. In the latter it had been done before the change order without prior written agreement, but with the knowledge and apparent consent of the state.

After this, work on the bridge progressed according to the original plan as amended. The contractor submitted periodic estimates of work done thereunder which were approved and paid. In due time the project was completed and accepted by the state. Before the final payment was made to the contractor some of the officials in the Department of Highways began to question the legality of payments made under the change order. As a result the final payment was held in abeyance and the question submitted to its legal department. Department counsel recommended the institution of this suit.

The trial court found that the cost of excavation of causeway materials for piers 27 — 20, inclusive, at the rate agreed on in the change order, amounted to $39,981.37, and for piers 19 to 4, inclusive, to $46,679.62. It also found that the cost of excavating natural ground for piers 27 — 20, inclusive, to be $10,-825.88 and for piers 19 to 4, inclusive, $6,937.88. It concluded that payment for excavating natural ground for all the piers involved was provided for in the contract and that the state was liable therefor, but not for excavating materials which the contractor had placed in the causeway because such would be unauthorized as constituting double payment- Judgment was entered accordingly from which the contractor appeals.

The state in its appeal brief complains of being held liable for the excavation of natural ground done before the execution *341 of the change order, claiming that such payment is retroactive in nature in violation of our constitutional provision. Art. XII, § 3. Since it has not cross appealed from any part of the determination and is here only as a respondent, the question which it seeks to raise is not before us. Peter Mintener Lumber Co. v. Janisch, 44 S.D. 42, 181 N.W. 914. No complaint appears to be made of the determination made as to similar excavation done after the execution of the change order.

Constitutional and statutory provisions place limitations on the contracting power and authority of the State Highway Commission of which those who deal with it are charged with notice. Cuka v. State, 80 S.D. 232, 122 N.W.2d 83. One of the most obvious of these is that its contracts must be let upon competitive bidding. SDCL 1967 31-5-10.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northern Improvement Co. v. South Dakota State Highway Commission
25 Cont. Cas. Fed. 82,625 (South Dakota Supreme Court, 1978)
Dave Gustafson & Co. v. S.D. Highway Commission
225 N.W.2d 594 (South Dakota Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
171 N.W.2d 504, 84 S.D. 337, 1969 S.D. LEXIS 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-commission-v-j-h-beckman-construction-co-sd-1969.