Franklin A. Snow Co. v. Commonwealth

22 N.E.2d 599, 303 Mass. 511, 1939 Mass. LEXIS 1024
CourtMassachusetts Supreme Judicial Court
DecidedJuly 7, 1939
StatusPublished
Cited by16 cases

This text of 22 N.E.2d 599 (Franklin A. Snow Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franklin A. Snow Co. v. Commonwealth, 22 N.E.2d 599, 303 Mass. 511, 1939 Mass. LEXIS 1024 (Mass. 1939).

Opinion

Lummus, J.

This is a petition under G. L. (Ter. Ed.) c. 258 by a contractor which constructed the east branch baffle at the site of Quabbin Reservoir in the towns of Greenwich and Hardwick in 1936 and early in 1937. It was referred to an auditor whose findings of fact were to be final. [512]*512G. L. (Ter. Ed.) c. 258, § 2. Upon his report the judge ordered a final decision in favor of the petitioner for only $7,554.72, exclusive of interest. The only questions now raised concern items K and L of the petition, in which the petitioner claimed $136,625 and $31,535.69 respectively, and upon which the auditor reported that the petitioner was entitled to $118,131.76 and $15,676.70 respectively, but upon which the judge decided for the respondent. The case comes here on the petitioner’s appeal under G. L. (Ter. Ed.) c. 231, § 96. Royal Paper Box Co. v. Munro & Church Co. 284 Mass. 446, 449. Robinson v. Lyndonville Creamery Association, 284 Mass. 396, 398. Kamberg v. Springfield National Bank, 293 Mass. 24, 25. Edinburg v. Allen-Squire Co. 299 Mass. 206.

Item K is for “additional expense incurred over the original estimates, figures and bid prices caused by a change in the quarry site from the original designated quarry site to the site chosen after the award of bids together with damages caused by delay in getting stone from the second quarry $136,625.00.”

The essence of the claim is that the contract contemplated the use by the petitioner of the Parker quarry, located within the territory to be flooded by the dam, as a source of broken stone or riprap which the contract required the petitioner to procure and use in large quantities, but that the use of that quarry proved impossible because the Commonwealth did not own it and failed to take it by eminent domain, and the petitioner had to resort to another quarry where the cost of procuring and transporting the material was very much greater.

An important point is the date of the contract between the petitioner and the Commonwealth, the latter acting by its metropolitan district water supply commission.

A form of contract was presented to prospective bidders, preceded by “information for bidders,” which stated among other things that the sealed bids or proposals would be publicly opened and read on May 14, 1936. “As a guaranty of the good faith of the bidder, each bid must be accompanied by a certified check acceptable to the commission and pay[513]*513able to the Commonwealth of Massachusetts, for ten thousand dollars ($10,000), such check to be returned to the bidder unless forfeited under the condition herein stipulated.” The "party to whom the contract is awarded” was to furnish a bond with surety for the faithful performance of the contract and the payment for all labor performed or furnished and for all materials used or employed in the carrying out of the contract. "The party to whom the contract is awarded will be required to present forthwith to the commission the name of the surety to be offered, and to execute the contract and the bond” within ten days after being notified that the contract is ready for execution; ‘ ‘ and, in case of his failure or neglect to do so, the commission at its option may determine that the bidder has abandoned the proposed contract, and thereupon, if it so determines, the proposal and acceptance shall be null and void, and the check accompanying the proposal shall be forfeited to the Commonwealth as liquidated damages.”

The form of contract which followed the "information for bidders” and the “proposal” containing the bid, signed by the petitioner, described the work and the terms upon which it should be done. Section 10' provided: “Land and rights of way of the Commonwealth are provided by the commission for the purposes of this contract to the extent shown on the plans, or on other plans on file in the office of the engineer; and the contractor will not be required to enter or build upon any other land, until the necessary additional land or rights of way have been provided.” Section 14 provided: "The contractor may, without charge therefor, open quarries, gravel, sand, soil, or other borrow pits on the lands controlled by the commission at any places permitted by the engineer, but unless shown on the plans or specifically permitted may not borrow from any area above” elevation 530. The work required both "stone fill” (Item 8), estimated at ten thousand cubic yards, and "riprap” (Item 9), estimated at fifty thousand cubic yards. The petitioner’s bid for each was $1 a cubic yard, for furnishing "all materials, equipment and labor required to construct” the stone fills and [514]*514riprap called for by the plans. In general, the same sorts and sizes of stones may be used for both. Section 8.2 of the contract provided that “satisfactory rock from open quarries located as approved may be used in the construction of stone fills.” The word “approved” means “approved by, or acceptable or satisfactory to, the engineer . . . .” The “engineer” means “the person holding the position or acting in the capacity of chief engineer of the metropolitan district water supply commission with respect to the work covered by this contract, acting either directly or through properly authorized agents, such agents acting within the scope of the particular duties entrusted to them.” No similar provision appears as to obtaining rock from quarries for “riprap”; but the material required is so similar that a similar provision may possibly be implied.

On May 6, 1936, the petitioner’s representatives went over the information to bidders, the proposals, and the form of contract, and inspected the location, accompanied by one O’Malley, who for the purposes of the contract was the “engineer” authorized to designate “approved” quarry sites and borrow areas. He showed the petitioner’s representatives the Parker quarry, and told them that the Parker quarry was approved as a source of rock for stone fill and riprap, and that the quality of the rock made it suitable. The petitioner examined no other quarry before bidding. “The Parker quarry site is within the area which will be submerged but projects above the floodline at elevation 530 so that it will above that line constitute an island in the proposed reservoir.” O’Malley believed that the Parker quarry was on land then owned by the Commonwealth, and so did the petitioner. Nothing on the plans indicated the contrary.

On May 14, 1936, the petitioner submitted its bid, with the required certified check, and later on the same day was notified that it was the lowest bidder. On May 19, 1936, the petitioner’s representatives proposed to O’Malley and a superior of his a method of using the Parker quarry, and they approved the method proposed, and thereby approved the use of the quarry. On May 28, 1936, the commission [515]*515awarded the contract to the petitioner, subject to the execution and delivery of a contract and a surety bond, and to the approval of the Governor and Council. It is contended that no such approval was required by law; but it was obtained on June 23, 1936. At any rate, the award was subject to the execution and delivery of the contract and bond; and these were not executed and delivered until June 23, 1936.

The fact that the Commonwealth did not own the Parker quarry first became known to O’Malley and his official superior, and to the petitioner, on June 2, 1936, from information given by one Walker, the custodian of the property of the Commonwealth in that locality.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ry-Tan Construction, Inc. v. Washington Elementary School District No. 6
93 P.3d 1095 (Court of Appeals of Arizona, 2004)
Short v. Sunflower Plastic Pipe, Inc.
500 P.2d 39 (Supreme Court of Kansas, 1972)
Verdugo Highlands, Inc. v. Security Insurance
240 Cal. App. 2d 527 (California Court of Appeal, 1966)
Johnson, Drake & Piper, Inc. v. State
41 Misc. 2d 804 (New York State Court of Claims, 1964)
C. & R. CONSTRUCTION CO. v. Commonwealth
135 N.E.2d 539 (Massachusetts Supreme Judicial Court, 1956)
Ward v. Smith
86 S.E.2d 539 (West Virginia Supreme Court, 1955)
Covington v. Basich Bros. Const. Co.
233 P.2d 837 (Arizona Supreme Court, 1951)
State v. Hartford Accident & Indemnity Co.
70 A.2d 109 (Supreme Court of Connecticut, 1949)
City of Boston v. Commonwealth
76 N.E.2d 121 (Massachusetts Supreme Judicial Court, 1947)
E. J. Albrecht Co. v. New Amsterdam Casualty Co.
163 F.2d 16 (Seventh Circuit, 1947)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Thibault v. Lalumiere
60 N.E.2d 349 (Massachusetts Supreme Judicial Court, 1945)
City of Somerville v. Commonwealth
48 N.E.2d 8 (Massachusetts Supreme Judicial Court, 1943)
Arthur A. Johnson Corp. v. Commonwealth
28 N.E.2d 465 (Massachusetts Supreme Judicial Court, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
22 N.E.2d 599, 303 Mass. 511, 1939 Mass. LEXIS 1024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franklin-a-snow-co-v-commonwealth-mass-1939.