Denver & S. L. Ry. Co. v. Moffat Tunnel Improvement Dist.

35 F.2d 365, 1929 U.S. Dist. LEXIS 1593
CourtDistrict Court, D. Colorado
DecidedSeptember 20, 1929
DocketNo. 8859
StatusPublished
Cited by5 cases

This text of 35 F.2d 365 (Denver & S. L. Ry. Co. v. Moffat Tunnel Improvement Dist.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denver & S. L. Ry. Co. v. Moffat Tunnel Improvement Dist., 35 F.2d 365, 1929 U.S. Dist. LEXIS 1593 (D. Colo. 1929).

Opinion

The Issues.

SYMES, District Judge.

In brief, the allegations of this hill are that on January 6, 1926, plaintiff railroad, and defendant the, Moffat Tunnel Improvement District, acting by and through the commission, entered into a written contract or lease, whereby the district leased to the plaintiff for a term of 50 years the railway use of the Moffat Tunnel and certain other property, with an option to renew for 49 years more; that the rent agreed to he paid is 66% per cent, of the installments of the principal of the Moffat Tunnel bonds of $6,720,000, and so-called Moffat Tunnel supplemental bonds of $2,500,000, being all the bonds then authorized or issued, plus 66% per cent, of the interest on the said two issues of bonds, beginning on the date the tunnel is ready for use by the railroad; that the plaintiff agreed to maintain the railroad tunnel, pay two-thirds of the cost of the commission, and, further, if the commission found it necessary to incur an indebtedness in addition to that above specified, or to levy and collect an assessment, proceeds to be expended on the railroad tunnel, the lessee bound itself to pay, in addition, the interest on such indebtedness as the same accrues, and to repay the principal in ten equal installments, beginning, January 1, 1974, or so much of the said sum as was expended on the railroad tunnel, provided, however, that this additional payment shall not in any event exceed $1,000,000 and inter[368]*368est; that plaintiff went into possession under the lease and is now operating the railway tunnel as part of its system; and it is alleged that on March 25, 1927, the parties entered into a supplemental contract containing certain modifications of the original lease, not material here.

It is further alleged that the defendant tunnel commission is now claiming as rent a large sum in addition to that specified in the contract, and has served a notice upon the plaintiff, dated January 29, 1929, that the rent called for by the Moffat Tunnel District law was the fair and just proportion of an amount sufficient to pay interest on all the bonds outstanding, and to provide for their retirement; that the railroad was in default of payment thereof, and unless this large increased sum was paid, it would proceed to oust the railroad under the forfeiture clause of the lease; that in reliance upon the lease the plaintiff has caused large sums of money to be expended on its own railroad, has mortgaged its property, expended large sums of money looking to the construction of the Dotsero cut-off, and otherwise changed its position, which it would not have done if the defendants’ claims had been seasonably made. Plaintiff prays that its title in and to the leasehold estate in the tunnel be quieted; (hat the lease be declared valid; and for injunctive and general relief.

Defendants, the improvement district, and the commissioners individually, admit the execution of the lease, and allege that it violates the Constitution and laws of Colorado, particularly section 9, chap. 2, of the Moffat Tunnel Act (Laws 1922, Ex. Sess., p. 99), and is without consideration; that they have demanded an additional sum as rent, and unless restrained will attempt to collect the same. They allege the rent specified is less than that required by the act, and that the lease creates a monopoly of the railway use in favor of plaintiff, in violation of the act. They deny plaintiff is in possession of the tunnel under the lease, but allege it is using the tunnel by the will and sufferance of the district, and is liable for the reasonable value of the use and occupation, and is indebted to the district in the sum of six hundred twenty-eight thousand odd dollars in addition to that paid. They admit the service of the notice and demand. They deny that the plaintiff has in good faith spent large sums of money and done other acts to its detriment in reliance upon the contract.

The second defense is that when the lease was negotiated and signed both parties believed the cost of the Moffat Tunnel would not exceed $9,720,000; that by reason . of unforeseen conditions and contingencies the final cost of the tunnel amounted to $15,470,000, and that bonds, in the amount of $5,750,000, in addition to the $9,720,000. aforesaid, were necessary to complete the tunnel; that the rent specified in the pretended contract was not a just and fair proportion of the amount required to pay interest and principal on the cost, etc., and should be not less than $850,000 a year; that due to a mistake of law the pretended determination of the value of the uses by the commission, as required by said section 9 of the act, was not a compliance therewith; that for all these reasons the contract is illegal and unconstitutional, at least as to the amount of rent to be paid; and asks that even if the lease be sustained, the court require the plaintiff to pay not less than $850,000 a year as rent.

The third defense is that the contract was without consideration, in that the railway is only bound to pay rent in the event it chooses to occupy and use the tunnel. Defendants next set up a counterclaim, alleging that the proportion of the value of the railroad use is 87 per cent, of the total value of all the uses of the tunnel. The defendants ask that the lease, or so much thereof as attempts to fix the rent for the use of the tunnel; the provision therein contained, authorizing the plaintiff to sublet; that part which attempts to create a monopoly in favor of the plaintiff; and the entire instrument — all be held null and void.

In reply plaintiff alleges that the contract is in full compliance with the law, and that the rent was the figure determined by the commission in accordance with the statute; that the defendants turned the railroad tunnel' over to the plaintiff without questioning the validity of the lease, and the tunnel is being used pursuant to said lease; that the' defendants remained silent, and at no time previous to January, 1929, did they in the slightest way intimate that they would assert any of the claims now set up in the answer and counterclaim; that by reason thereof 'the defendants are estopped from asserting the invalidity of the lease, or claiming any rental other than that specified in the contract.

The Pacts.

A brief summary of the material facts found, with a few comments thereon, is necessary to an understanding of the law of the case.

[369]*369The record compels the conclusion that at no time did the commission or its engineers have sufficient data or information upon which a reliable determination of the completed cost of the tunnel could be made. It relied apparently wholly upon estimates of cost made by its engineers, that proved inaccurate and unreliable, both as to time of completion and cost, being millions of dollars under the actual figures. The organization set up was unable to solve efficiently and economically the problems presented by the areas of great pressure, fissures, soft rock, excessive flows of water and mud, etc. Several different methods of getting through this country were tried in turn and discarded, after great expense had been incurred thereby.

The preliminary examination of the site was merely cursory. The few drill holes and test pits dug were superficial, and the meager preliminary data gathered was wholly inadequate as a basis for an accurate forecast of the character of the ground, the engineering, and geological conditions that might be anticipated.

Mr. Lewis and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wisehart v. Zions Bancorporation
49 P.3d 1200 (Colorado Court of Appeals, 2002)
City of Austin v. Cotten
509 S.W.2d 554 (Texas Supreme Court, 1974)
United States v. Idlewild Pharmacy, Inc.
308 F. Supp. 19 (E.D. Virginia, 1969)
Benward v. Automobile Ins.
60 F. Supp. 995 (S.D. New York, 1945)
Herman v. Mutual Life Ins. Co. of New York
108 F.2d 678 (Third Circuit, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
35 F.2d 365, 1929 U.S. Dist. LEXIS 1593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denver-s-l-ry-co-v-moffat-tunnel-improvement-dist-cod-1929.