Young v. City of Holyoke

225 Mass. 140
CourtMassachusetts Supreme Judicial Court
DecidedNovember 11, 1916
StatusPublished
Cited by4 cases

This text of 225 Mass. 140 (Young v. City of Holyoke) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Young v. City of Holyoke, 225 Mass. 140 (Mass. 1916).

Opinion

Carroll, J.

The plaintiff contracted in writing with the board of water commissioners of the city of Holyoke, acting for the defendant, to build a concrete masonry dam across the Manhan Brook in the town of Southampton at “certain unit quantity prices” for the different kinds of labor and materials involved. He abandoned the work before its completion, and seeks to have the contract cancelled either on the ground of the defendant’s fraud in falsely estimating the quantities of material and labor necessary for the work, or on the ground of the mutual mistake of the parties in relying on these erroneous estimates; and, if this relief is not granted, he seeks to recover the balance due under the contract; and also asks for compensation because the location of the dam as shown on the plan was changed by moving its west end twenty-five feet to the north and by extending its east end seven feet to the east; and for the reason that the gatehouse was built on the upper side of the dam, the plan showing it on the lower side; as well as for changes made in the slope of the dam, in the core wall and in the spillway, so that the amount of excava[142]*142tian and concrete construction was greatly increased; and further because he was required to remove certain concrete laid in accordance with the specifications, and was paid for only one foot thickness of Class A concrete when he should have been paid for four feet.

The defendant does not question the plaintiff’s pleadings. It denies his claims and asks for relief against him under a clause in the contract giving it the right, in case the contract is abandoned, to complete the work deducting the additional expense for so doing from the sum otherwise payable to the plaintiff.

The master found there was no fraud on the part of the defendant; that the plaintiff was not justified in abandoning the contract and was not entitled to recover on a quantum meruit basis for what was done under the contract. After deducting the extra cost of completing the structure, he found the sum due the plaintiff. A decree was entered,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aldrich v. Travelers Insurance
56 N.E.2d 888 (Massachusetts Supreme Judicial Court, 1944)
Kennedy v. City of Boston
189 N.E. 809 (Massachusetts Supreme Judicial Court, 1934)
Martiniello v. Bamel
150 N.E. 838 (Massachusetts Supreme Judicial Court, 1926)
Cavanagh v. Tyson, Weare & Marshall Co.
116 N.E. 818 (Massachusetts Supreme Judicial Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
225 Mass. 140, Counsel Stack Legal Research, https://law.counselstack.com/opinion/young-v-city-of-holyoke-mass-1916.