Atwood v. City of Boston

37 N.E.2d 131, 310 Mass. 70, 1941 Mass. LEXIS 838
CourtMassachusetts Supreme Judicial Court
DecidedOctober 27, 1941
StatusPublished
Cited by51 cases

This text of 37 N.E.2d 131 (Atwood v. City of Boston) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atwood v. City of Boston, 37 N.E.2d 131, 310 Mass. 70, 1941 Mass. LEXIS 838 (Mass. 1941).

Opinion

Dolan, J.

This is an action of contract to recover a balance alleged to be due the plaintiff for services performed under the terms of a written agreement, entered into by the parties on November 12, 1929. The case was tried a jury. At the close of the evidence the defendant moved for a directed verdict in its favor. The judge denied this motion, subject to the defendant’s exception. The jury returned a verdict for the plaintiff in the amount of $34,454.88, and the judge reserved leave, with the assent of the jury, to enter a verdict for the defendant. Thereafter the defendant’s motion that this be done was denied by the judge and the defendant duly excepted. The case comes before us on the report by the judge of the questions raised by these exceptions of the defendant and by its exceptions to the admission of certain evidence, and to the refusal of the judge to grant certain of its requests for in[72]*72structions. Under the terms of the report, if the judge’s rulings and orders were correct, judgment is to be entered for the plaintiff on the verdict, and if his denial of the defendant’s motion for a directed verdict or of its motion for entry of a verdict for it under leave reserved was incorrect, judgment is to be entered for the defendant.

The evidence in its aspect most favorable to the plaintiff tends to show the following facts: Under the terms of the contract the plaintiff agreed to render services, as an architect, in connection with the proposed construction of a high school building for girls in the “Martin District” in Boston, in the performance of which he was to make preliminary studies, to submit them to the defendant, to provide working drawings, specifications and blue prints, and to assume the active supervision of all construction work on the building and also of “landscape and domestic engineering.”

The contract contained, among others, the following pertinent provisions: ‘ ‘ Section 1. The Board. — (a). Is to furnish the Architect with the requirements and information for the design and construction of the said building and to give the maximum cubical contents and the cost for said building, which shall not be in excess of one million eight hundred thousand (1,800,000) dollars. . . . Section 3. (a). The City ... is ... to pay the Architect 22/5 per cent, upon the cost of the landscape and domestic engineering, exclusive of plumbing, and 6 per cent, upon the cost of all other work. The Board at any time may discontinue the services of the Architect, and if . . . [so] discontinued prior to the completion of the work to be done by the Architect under this contract, the value of the Architect’s services shall be reckoned to the date of the discontinuance, and payment shall be made pro rata in accordance with the terms of this contract, and when made shall relieve the City from any further liability under this contract, (b). Payments to be made as follows: 1. When preliminary studies are completed, an amount not to exceed one-sixth of the estimated total commission, which total commission is to be based upon the estimated cost of the building, which estimated [73]*73cost is not to exceed the amount mentioned in Section 1 (a) of this contract. 2. When working drawings and specifications are ready for contract, Architect’s services to that date shall be reckoned as 3 3/5 per cent, of the actual cost, but in no event in excess of 3 3/5 per cent, of the cost as designated in Section 1 (a) ... . There shall be deducted from said 3 3/5 per cent, any sums previously paid for work done under this contract ... 3. After the contract is let to do the work . . . additional payments are to be made to the Architect estimated at 2 2/5 per cent, of the amounts approved for payment to the contractor or contractors. All of said payments ... to be on account of the total commission. 4. Final payment is not to be made . . . until the work is fully completed and the building finally accepted . . . .” The total appropriation ultimately made for the construction of the building was $1,119,995.71 and that made for “plans” was $110,000.1

The plaintiff completed the preliminary studies in accordance with the terms of the contract on or before December 28, 1929. On that date he submitted a bill to the city as follows:

“To professional services in the preparation of studies for the Girls High School, Worthington Street, Roxbury, in accordance with contract dated November 18, 1929,
Estimated cost of building, $1800000.00
Estimated cost of Heating & Ventilating, $144000.00
Estimated cost of Electrical work, 90000.00
Estimated cost of Landscape engineering, 20000.00
$254000.00 254000.00
$1546000.00
6% of $1546000.00 $92760.00
2 2/5% of $254000.00 6096.00
Total estimated commission $98856.00
1/6 of $98856.00............................ $16476.00”

This bill was paid by the defendant on May 21, 1930.

On February 4, 1931, the plaintiff delivered to the defendant the “working drawings and specifications ready for [74]*74contract.” On March 27, 1931, he presented a bill to the city in the following form:

“To professional services in the preparation of studies, working drawings and specification for the Girls High School, Worthington Street, Martin District, Roxbury, in accordance with contract dated November 18, 1929.
Estimated cost of building, $1300000.00
Estimated cost of Heating & Ventilating, $104000.00
Estimated Cost of Electric work 65000.00
Estimated cost of Landscape engineering, 5000.00
$174000.00 174000.00
$1126000.00
3.6% of $1126000.00 $40536.00
Previous payment, 16476.00
Due at this time, $24060.00”

Accompanying this bill was a letter from the plaintiff . to the defendant's superintendent of construction, which reads in part as follows: “At current prices I feel confident that this building could be placed under contract for a price not in excess of $1300000.00 and for that reason I am revising the figures to agree with the above in submitting a bill for services to date, a payment of three and three fifths per cent, on the above amount of $1300000.00 as the cost of the work, deducting the estimated cost of the electrical, heating and ventilating, and, landscape work; less the amount of the previous payment.” The defendant paid this bill on April 21, 1931. The plaintiff had fully performed all the duties required of him under the contract up to that date. He never performed any services under the contract thereafter, and on June 16, 1933, the defendant notified him, in writing, that his contract was terminated because “the school will not be built” and that he had been paid in full for his services. The defendant never constructed the school building or any part thereof, and so far as appears no construction contracts were ever let in connection with the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citizens Bank v. Milligan
20 Mass. L. Rptr. 559 (Massachusetts Superior Court, 2006)
McAdams v. Massachusetts Mutual Life Insurance
391 F.3d 287 (First Circuit, 2004)
Nadherny v. Roseland Property Co.
390 F.3d 44 (First Circuit, 2004)
Fishman v. LaSalle National Bank
247 F.3d 300 (First Circuit, 2001)
Kelley v. Dolben
12 Mass. L. Rptr. 509 (Massachusetts Superior Court, 2000)
O'Hagan v. Taveras
12 Mass. L. Rptr. 11 (Massachusetts Superior Court, 2000)
In Re Simon
179 B.R. 1 (D. Massachusetts, 1995)
Raphael v. Nagog Realty Corp.
1994 Mass. App. Div. 224 (Mass. Dist. Ct., App. Div., 1994)
Urban Investment & Development Co. v. Turner Construction Co.
616 N.E.2d 829 (Massachusetts Appeals Court, 1993)
Canal Electric Co. v. Westinghouse Electric Co.
973 F.2d 988 (First Circuit, 1992)
Henry v. Black & Decker Inc.
779 F. Supp. 778 (D. New Jersey, 1991)
Boston Helicopter Charter, Inc. v. Agusta Aviation Corp.
767 F. Supp. 363 (D. Massachusetts, 1991)
Hawes Office System Inc. v. Wang Laboratories, Inc.
537 F. Supp. 939 (E.D. New York, 1982)
Bulpett v. Dodge Associates, Inc.
365 N.E.2d 1248 (Massachusetts Appeals Court, 1977)
Day v. a & G Construction Co., Inc.
528 P.2d 440 (Alaska Supreme Court, 1974)
Werner Construction Co. v. Dorchester Savings Bank
45 Mass. App. Dec. 115 (Mass. Dist. Ct., App. Div., 1970)
Limbach Co. v. George B. H. Macomber Co.
258 N.E.2d 548 (Massachusetts Supreme Judicial Court, 1970)
Union Hospital v. Donatelli
35 Mass. App. Dec. 187 (Mass. Dist. Ct., App. Div., 1968)
Kelleher v. Rosenberg
214 N.E.2d 880 (Massachusetts Supreme Judicial Court, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
37 N.E.2d 131, 310 Mass. 70, 1941 Mass. LEXIS 838, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atwood-v-city-of-boston-mass-1941.