Canal Electric Co. v. Westinghouse Electric Co.

973 F.2d 988
CourtCourt of Appeals for the First Circuit
DecidedAugust 31, 1992
DocketNos. 91-1432, 91-1433 and 91-1504
StatusPublished
Cited by5 cases

This text of 973 F.2d 988 (Canal Electric Co. v. Westinghouse Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Canal Electric Co. v. Westinghouse Electric Co., 973 F.2d 988 (1st Cir. 1992).

Opinion

BREYER, Chief Judge.

The consolidated appeals in this diversity case arise out of the discovery, between 1983 and 1985, of tiny cracks (called “fretting”) in the turbine blades of a Canal Electric Company generator. Canal Electric Company sued the firm that had promised to service the generator, Westinghouse Electric Corporation, claiming that Westinghouse had breached both the generator’s service and equipment warranties. Several Canal customers (the third-party plaintiffs) also sued Westinghouse, claiming that the cracks harmed them, by disrupting Canal’s operations, and thereby bringing about higher electricity prices.

The two law suits met different fates. The district court ordered a directed verdict against the third-party plaintiffs. Although it also dismissed some of Canal’s claims, it permitted one of those claims — a claim for certain repair costs — to proceed to trial 756 F.Supp. 620. The jury awarded Canal $380,000 plus interest.

Westinghouse now appeals the judgment in Canal’s favor. Canal has filed a cross-appeal. And, the third-party plaintiffs appeal the directed verdict against them. We reverse the judgment in Canal’s favor, and we otherwise affirm the determinations of the district court.

I

Background

A

The Basic Facts

The basic facts in this case are not significantly disputed. They include the following:

1. In early 1983 Westinghouse promised Canal it would inspect and clean a generator, which Westinghouse had sold Canal fifteen years earlier.
2. The basic contract consisted of two purchase orders (dated February 24 and March 4, 1983), both of which cross-referenced (and thereby incorporated) a standard Westinghouse “selling policy” document. That document included an equipment and service warranty and various liability limitations.
3. In late February 1983 Canal found small cracks (the “fretting”), in some of the generator’s turbine blades. Westinghouse replaced the cracked blades in March 1983.
4. In July 1983, only a few months later, the blades broke; they “completely sheared off”. Westinghouse replaced the new blades. The replacement job took four months. In November 1983 the generator was “ready for service” and went back on-line.
5. In April 1985, seventeen months later, Canal took the generator off-line for a routine inspection. During the inspection, Westinghouse found fretting in the same blades it had installed between July and November 1983.
6. Working together with Canal, Westinghouse eventually found ways to overcome the problem that was causing fretting in the turbine blades. But, the necessary studies and repairs were costly. The two companies disagreed about how to split the costs. Canal wanted Westinghouse to pay; Westinghouse thought they should split the costs.

[990]*990B

Proceedings Below

We shall summarize, simplifying significantly, the lengthy proceedings of this case, while emphasizing matters relevant on this appeal. In their lawsuits, Canal and its customers basically claimed (1) that Westinghouse breached its equipment and service warranties through its failure to replace properly the blades that “sheared off” in July 1983, and (2) that Westinghouse breached its service warranty by failing properly to prevent the blade fretting that occurred between November 1983 and April 1985. The plaintiffs initially focused on the first of these failures, the one in July 1983, seeking to recover for losses suffered during the subsequent generator outage between July and November 1983.

The contract’s “selling policy” contained two provisions that posed serious obstacles to the plaintiffs' July 1983 warranty claim. First, the warranty provision itself, while warranting the promised work for “one year” against “any defects in workmanship and material,” also said simply that, “should any defect appear” during that time, Westinghouse “shall correct such nonconformity, by repairing or, at its option, replacing the defective work.” Second, a “limitation of liability” provision said that Westinghouse “shall not be liable” for any “special, indirect, incidental or consequential damages whatsoever,” that the “remedies ... set forth herein are exclusive,” and that “the total liability of Westinghouse ... shall not exceed the price set forth for the work in the purchase order....”

These provisions threatened claims based on the July 1983 blade failure because Westinghouse had already refunded to Canal the purchase price of the blades that had then “sheared off.” Westinghouse also had replaced the defective blades largely free of charge. It thus appeared to have satisfied its promise under the warranties to “repair or replace” defective parts, and seemed also to have reached the maximum liability ceiling set forth by the equipment warranty’s limitation clause. Further, the damages the plaintiffs suffered during the July-November 1983 outage were basically “consequential” damages, such as lost profits and overtime expenses. The “limitation of liability” provision strictly barred recovery for such damages.

Faced with these obstacles, Canal and its customers argued that the “limitation of liability” provision was unenforceable. They claimed that Westinghouse, after the July 1983 blade failure, did not “repair[ ] or replace[ ] ... the defective work” on time. Rather, it delayed too long in making proper repairs. It thereby failed to live up to the exclusive remedy in the warranty. And, that failure (for various legal reasons), they said, invalidated the “limitation of liability” provision elsewhere in the contract. The district court, uncertain of the legal validity of this argument, certified to the Massachusetts Supreme Judicial Court the following question:

Assuming that the Westinghouse exclusive remedy [in its warranty] failed [because Westinghouse failed to replace the sheared-off blades promptly] ... is the provision entitled Limitation of Liability enforceable under the circumstances alleged in this case?

The Supreme Judicial Court answered that the limitation clause was still enforceable. The district court consequently dismissed Canal’s equipment warranty claims. And, for other reasons (which we shall discuss in Part IV below), it dismissed all the claims of Canal’s customers, the third-party plaintiffs.

Following the ruling of the Supreme Judicial Court, Canal reformulated, and then proceeded with, its remaining, “service warranty” claim. It argued that the fretting that occurred between November 1983 and April 1985 (fretting that was discovered in 1985) violated the warranty against defects in workmanship. It sought as damages, not the “consequential” damages flowing from the July-November 1983 generator down-time, but, rather, those exceptional costs involved in the April 1985 outage, including those of diagnosing, and curing, the fretting problem.

As we have said, the district court submitted Canal’s service warranty claim to the jury. The jury awarded Canal $380,000 plus interest. Westinghouse appeals this award; Canal cross appeals; and the third-party plaintiffs appeal as well.

II

The Westinghouse Appeal

The Westinghouse appeal turns upon the meaning of a key word in the warranty [991]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
973 F.2d 988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/canal-electric-co-v-westinghouse-electric-co-ca1-1992.