USM Corp. v. Arthur D. Little Systems, Inc.

546 N.E.2d 888, 28 Mass. App. Ct. 108, 10 U.C.C. Rep. Serv. 2d (West) 327, 1989 Mass. App. LEXIS 666
CourtMassachusetts Appeals Court
DecidedNovember 27, 1989
Docket88-P-650
StatusPublished
Cited by163 cases

This text of 546 N.E.2d 888 (USM Corp. v. Arthur D. Little Systems, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
USM Corp. v. Arthur D. Little Systems, Inc., 546 N.E.2d 888, 28 Mass. App. Ct. 108, 10 U.C.C. Rep. Serv. 2d (West) 327, 1989 Mass. App. LEXIS 666 (Mass. Ct. App. 1989).

Opinion

Fine, J.

This dispute concerns an attempt by the plaintiff, USM Corp. (USM), to acquire a computer system for use in its business of manufacturing and selling shoe-making equipment. The defendant Arthur D. Little Systems, Inc. (ADLS), was organized in 1971 as a wholly owned subsidiary of the defendant Arthur D. Little, Inc. (ADL), for the purpose of developing, marketing, and installing “turnkey” computer systems. USM and ADLS entered into a contract for such a system, but the result of considerable effort over the course of several years was a system which failed to meet the needs of USM. USM sued both ADLS and its parent, ADL. Against ADLS, USM alleged breach of contract and deceit. Against ADL, USM claimed liability vicariously for ADLS’s breach of contract, tortious behavior, and violation of G. L. c. 93A, and, on the basis of ADL’s own conduct, for violation of G. L. c. 93A. ADLS filed a counterclaim for payments from USM due on the contract.

Summary judgment was ordered in favor of ADL on the allegations of vicarious liability for ADLS’s tortious conduct and breách of contract, and no argument has been made on appeal that that order was erroneous. After a lengthy jury-waived trial in the Superior Court, the judge ruled in favor of the defendants on all of the plaintiff’s claims and on the counterclaim, and he assessed costs against USM. Of the *110 issues raised on appeal, we find it necessary to discuss at length only the contract and c. 93A claims. 2 We agree with the judge that ADL is not liable to USM under G. L. c. 93A. We disagree with his determination that ADLS is not liable to USM for breach of contract. We therefore reverse the decision in favor of ADLS on USM’s claim and on the counterclaim, vacate the assessment of costs, and remand the case for a determination of damages.

1. Breach of contract. We take the facts from the judge’s findings. Sometime prior to February 12, 1975, USM began to look into replacing its existing computer system with a more powerful one. The primary purpose of the new system, which USM called MATCON, would be to provide accounts receivable, billing data, inventory control, and other record-keeping functions. USM requested proposals for a “turnkey” systems development approach from a number of vendors, and ADLS, among others, submitted a proposal. ADLS described the services it would supply as follows: “Turnkey Systems Development: in which the complete responsibility for system development — from project definition to complete system delivery — rests with ADL Systems.” In its definitive proposal, dated August 7, 1975, ADLS described its proposal as being “for the implementation of a ‘turnkey’ mini-computer based material control system at USM’s Beverly plant.” It went on to state that “[t]he proposed system is ‘turnkey’ in the sense that ADLS will develop and implement *111 a completely operable system, according to the specifications in our proposal, on a fixed price basis. ADLS will acquire the proposed computer hardware, develop the proposed applications software, integrate the two and demonstrate the proposed system in operation for acceptance by USM.” The proposal was to use a minicomputer and software manufactured by Data General. Proposals from other prospective vendors would have utilized the products of other manufacturers. In weighing the various proposals, USM engaged in a detailed study of the alternatives, hired an outside consultant for advice, and discussed products directly with the manufacturers, including Data General. As a result of its studies, USM was aware that there were risks involved with ADLS’s proposal, but USM favored that proposal over the others.

In the fall of 1976, ADLS personnel began to meet with USM personnel in order to define USM’s use requirements so that ADLS could create specific application functions and design a suitable software program. By this time, changes had been made in the proposal with respect to both the hardware and the software to be used for the system. 3 In December of 1976, USM approved the MATCON project and authorized ADLS to proceed to implement the new system. On or about December 15, 1976, the first design phase of the project was completed with ADLS’s delivery to USM of the two-volume Functional Design document and the Systems Architecture and Performance Analysis document.

The stated purpose of the Performance Analysis portion of the Systems Architecture and Performance Analysis document was “[t]o publish the results of an analysis of expected performance of the system.” Among the results published was a calculation of the response time expected for the MATCON system. 4 That calculation yielded the following results: “92% of the time, response time will not exceed 2 *112 seconds/field[;] 98% of the time, response time will not exceed 3 seconds/field.” The results were described as “estimates” based on “available data,” and they were “to be reviewed at the completion of the detailed design phase in order to verify the results.” However, the Performance Analysis also refers to its estimates as being conservative and describes a response time of eight or nine seconds as being the “worst case.”

As the process moved forward, both USM and ADLS were aware that response time might be a problem. 5 A consultant, hired by ADLS to review the Performance Analysis, prepared a detailed report on the problem, 6 ****6 but he, along with others at ADLS, believed it could be solved by adding a second disk controller to the system. Some computer systems will support access to two disk controllers simultaneously through a process known as “overlapping” or “multiple seeks.” As a result of “multiple seeks,” the number of disk accesses available to the system would be doubled, thereby cutting the disk-utilization factor in half and improving response time accordingly. Throughout the spring of 1977, Data General assured ADLS that the MATCON system, using the specified products (the C-330 minicomputer and IN- *113 FOS and IDEA), would support “multiple seeks.” The judge found that ADLS reasonably relied on Data General’s assurances, although they would later turn out to be false. USM was never provided a copy of the ADLS consultant’s detailed report on the response time problem. The judge found, however, that USM personnel were aware of the issues raised in the report as well as the proposed solution.

On March 4, 1977, USM and ADLS memorialized their agreement in a writing entitled “Turnkey Systems Agreement.” The basic agreement between the parties was that:

“ADLS shall furnish, and Customer shall accept, a computer system (the ‘System’), sometimes called a ‘turnkey system’ in the vernacular, that comprises the Equipment and Software Programs and satisfies the Specifications, all as set forth in the following schedule, as it might be amended, on the terms and subject to the conditions set forth below and on the following pages of this Agreement[.]”

Under the heading “Specifications,” the contract provided:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PAMELA CYR & Another v. KATHERINE L. SMITH.
Massachusetts Appeals Court, 2025
EILEEN S. HOFFNER v. STEVEN S. SIEGEL & Another.
Massachusetts Appeals Court, 2025
Patrick Furnari v. John S. Holden, Third.
Massachusetts Appeals Court, 2024
Alan Smith v. Decisionone Corporation.
Massachusetts Appeals Court, 2024
K.W. v. LAZ PARKING LIMITED, LLC, & Others.
Massachusetts Appeals Court, 2023
Paisner v. Mairs
119 N.E.3d 355 (Massachusetts Appeals Court, 2018)
Sea Breeze Estates, LLC v. Jarema
113 N.E.3d 355 (Massachusetts Appeals Court, 2018)
Columbia Plaza Assocs. v. Ne. Univ.
104 N.E.3d 682 (Massachusetts Appeals Court, 2018)
Willard P. Wagner v. Eric Martin Novelli
Court of Appeals of Tennessee, 2018
Bailey v. Astra Tech, Inc.
84 Mass. App. Ct. 590 (Massachusetts Appeals Court, 2013)
Massachusetts Highway Department v. Perini Corp.
981 N.E.2d 721 (Massachusetts Appeals Court, 2013)
NSTAR Electric Co. v. Department of Public Utilities
968 N.E.2d 895 (Massachusetts Supreme Judicial Court, 2012)
Indus Partners, LLC v. Intelligroup, Inc.
934 N.E.2d 264 (Massachusetts Appeals Court, 2010)
Sheriff of Suffolk County v. AFSCME Council 93, Local 419
914 N.E.2d 124 (Massachusetts Appeals Court, 2009)
Colorio v. Marx
892 N.E.2d 356 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
546 N.E.2d 888, 28 Mass. App. Ct. 108, 10 U.C.C. Rep. Serv. 2d (West) 327, 1989 Mass. App. LEXIS 666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/usm-corp-v-arthur-d-little-systems-inc-massappct-1989.