Fargo MacHine & Tool Co. v. Kearney & Trecker Corp.

428 F. Supp. 364, 21 U.C.C. Rep. Serv. (West) 80, 1977 U.S. Dist. LEXIS 17484
CourtDistrict Court, E.D. Michigan
DecidedFebruary 7, 1977
DocketCiv. 39836 and 4-70185
StatusPublished
Cited by71 cases

This text of 428 F. Supp. 364 (Fargo MacHine & Tool Co. v. Kearney & Trecker Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fargo MacHine & Tool Co. v. Kearney & Trecker Corp., 428 F. Supp. 364, 21 U.C.C. Rep. Serv. (West) 80, 1977 U.S. Dist. LEXIS 17484 (E.D. Mich. 1977).

Opinion

OPINION

GUY, District Judge.

These consolidated contract cases arise from a dispute over payment of the remaining balance due on a sophisticated piece of automated industrial equipment used for machining metal. Fargo Machine & Tool Company, the purchaser, is a machine shop in Michigan and Kearney & Trecker Corporation, the seller, is a Wisconsin corporation which manufactures industrial machines. Allen-Bradley, also a Wisconsin corporation, and third-party defendant in this suit, manufactured and supplied to Kearney & Trecker a major portion of the electronic system which controls the machine in question.

The president of Fargo, Mr. Fortunski, contacted a local Gorton (a Kearney & Trecker subsidiary which has since been absorbed) sales representative early in 1970 after noticing a two-page advertisement in a prominent trade journal for the “Series H-60 Milwaukee Matic Machining Center.” In May of 1970, after reviewing Gorton’s promotional literature and specifications with the salesmen, Fortunski and his chief engineer, McCaffrey, went to Gorton’s Wisconsin headquarters for a demonstration. They were quoted an added cost figure to equip the machine with a larger table (designating the machine H-100) and on June 1, 1970, accordingly submitted a purchase order in a total amount of $153,725.00 detailing specifications and the desired options. Fargo attached to its order a copy of “terms and conditions governing quotations” which had earlier been provided by Gorton, and on July 1, 1970, Gorton acknowledged and accepted.

Delivery was made in August of 1971, and installation was completed late in September of 1971. The machine was not operating to the full satisfaction of Fargo and a lengthy series of service calls commenced. Gorton’s service calls were made, in 1971, from September 30 through October 1; October 26, in 1972, March 1, March 13 through 16, June 5, June 29 through June 30, July 13 through July 14, July 17 through July 21, August 23 through August 25, September 28 through September 29, October 2 through October 6, October 11, October 30 through November 1, and November 8 through November 9; in 1973, January 22, January 24 through January 26, January 29 through February 3, February 12, March 8 and March 21.

Fargo had paid $75,000.00 on the machine on September 1, 1971, leaving approximately the same amount due. As of January, 1972, the balance had not been paid and a Kearney & Trecker vice-president, Christopherson, called on Fargo to try and arrange payment. The substance of the complaints aired by Fargo in that meeting is reflected in the confirming correspondence Fortunski *369 and Christopherson exchanged in February of 1972. Fortunski, although dissatisfied with still unresolved technical problems, agreed to pay $28,868.00, reducing the balance due to $50,000.00 in return for Kearney & Trecker’s promise to make good on the machine notwithstanding the warranty expiration and to correct specified deficiencies. See also Kearney & Trecker affidavit from Wisconsin pleadings, Exhibit No. 55 re warranty extension of six months.

Kearney & Trecker advised Fargo by letter dated June 16,1972, that the particular problems they had discussed had been remedied and that prompt payment of the balance due was in order. Although Fargo did not respond to this letter, Fortunski and McCaffrey testified that all the problems had not been eliminated and, further, that new problems were still developing. By letter of September 7, 1972, Fortunski expressed further misgivings about paying the balance due since Kearney & Trecker had not been able to remedy the machine’s problems even while that incentive was outstanding. Another meeting was held in October of 1972 at which Fargo submitted a further list McCaffrey had prepared noting uncured defects Fargo considered incompatible with satisfactory operation of the H-100. ,

Service calls continued until March 21, 1973, the parties having again met on March 1st. On April 6, about two weeks after its last call, Kearney & Trecker filed suit in state court in Wisconsin to recover the balance due. Fargo counter-claimed in breach of warranty and removed to the United States District Court for the Eastern District of Wisconsin. Thereafter, Fargo filed its own action against Kearney & Trecker in the United States District Court for the Eastern District of Michigan alleging breach of warranty and attempted “recission.” Venue in the Wisconsin action was transferred to Michigan and both cases were consolidated before this court. Kearney & Trecker thereafter impleaded Allen-Bradley as third-party defendant on an indemnity theory.

Before proceeding to the principal claims of the parties, it is expedient to consider the third-party claim against Allen-Bradley. The court is disposed to dismiss Kearney & Treeker’s third-party claim in indemnity against Allen-Bradley on the grounds that no case for recovery against Allen-Bradley was presented separately or as part of a case in chief, defendant Kearney & Trecker having rested at the close of Fargo’s case.

The status of Allen-Bradley here may be described as that of a component supplier. The Allen-Bradley component is comprised of a rack into which approximately fifty integrated circuit boards or modules of complex miniaturized circuitry are inserted which control, in part, the functions the machine performs. Were indemnity to lie against Allen-Bradley, it must initially be predicated on a showing that the component part that Allen-Bradley supplied, the Allen-Bradley control unit, had a causative link with the machine’s malfunctions. Indemnity Insurance Co. v. Otis Elevator, 315 Mich. 393, 24 N.W.2d 104 (1946). Proving this hypothesis, however, posed a very basic difficulty. Fargo had no claim directly against Allen-Bradley and no problems that it traced directly to a defect in the Allen-Bradley portion of the H-100. Fargo’s allegation, in essence, was that the machine did not work automatically and that the cause could not be pinpointed or would have been fixed. Fargo, thus, was of no assistance in attributing problems to specific defects in the Allen-Bradley control. Kearney & Trecker, on the other hand, concentrated on attempting to show that the faults were either de- minimis, had been substantially remedied, resulted from Fargo’s fault, or were not communicated to Kearney & Trecker. The end result, of course, was that, at the close of plaintiff’s case, the’ evidence provided no indication that any existent malfunctions were specifically attributable to defects in the Allen-Bradley control. Indeed, to the contrary, the testimony of Mr. Martin, an Allen-Bradley field service manager, was that those portions of the Allen-Bradley control which showed visible irregularity or modification had been altered after it had undergone *370 extensive Allen-Bradley testing and after the unit had left Allen-Bradley hands and been shipped to Gorton. It is beyond argument that a component supplier cannot be liable in indemnity where the part has been altered or modified after it has left his control. Grummons v. Zollinger, 189 F.Supp. 64 (N.D.Ind.1960); Frank R. Jellef, Inc. to use of Liberty Mutual Insurance Co. v. Poliak Bros., Inc., 171 F.Supp. 467 (N.D. lnd. 1957).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keahole Point Fish LLC v. Skretting Canada Inc.
971 F. Supp. 2d 1017 (D. Hawaii, 2013)
Contech Casting, LLC v. ZF Steering Systems, LLC
931 F. Supp. 2d 809 (E.D. Michigan, 2013)
In Re Scba Liquidation, Inc.
451 B.R. 747 (W.D. Michigan, 2011)
Kraft v. DR. LEONARD'S HEALTHCARE CORP.
646 F. Supp. 2d 882 (E.D. Michigan, 2009)
Kolarik v. Cory International Corp.
721 N.W.2d 159 (Supreme Court of Iowa, 2006)
Computer Network, Inc. v. AM General Corp.
696 N.W.2d 49 (Michigan Court of Appeals, 2005)
In Re Meridia Products Liability Litigation
328 F. Supp. 2d 791 (N.D. Ohio, 2004)
Ducharme v. a & S RV CENTER, INC.
321 F. Supp. 2d 843 (E.D. Michigan, 2004)
Heidtman Steel Products, Inc. v. Compuware Corp.
178 F. Supp. 2d 869 (N.D. Ohio, 2001)
Lumber Mutual Insurance v. Clarklift of Detroit, Inc.
569 N.W.2d 681 (Michigan Court of Appeals, 1997)
Bishop Logging Co. v. John Deere Industrial Equipment Co.
455 S.E.2d 183 (Court of Appeals of South Carolina, 1995)
Aluminum Line Products Co. v. Rolls-Royce Motors, Inc.
649 N.E.2d 887 (Ohio Court of Appeals, 1994)
Adams v. American Cyanamid Co.
498 N.W.2d 577 (Nebraska Court of Appeals, 1992)
Henderson v. Chrysler Corp.
477 N.W.2d 505 (Michigan Court of Appeals, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
428 F. Supp. 364, 21 U.C.C. Rep. Serv. (West) 80, 1977 U.S. Dist. LEXIS 17484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fargo-machine-tool-co-v-kearney-trecker-corp-mied-1977.