Hart Engineering Co. v. FMC Corp.

593 F. Supp. 1471, 39 U.C.C. Rep. Serv. (West) 1313, 1984 U.S. Dist. LEXIS 23681
CourtDistrict Court, D. Rhode Island
DecidedSeptember 12, 1984
DocketCiv. A. 83-0219 S
StatusPublished
Cited by36 cases

This text of 593 F. Supp. 1471 (Hart Engineering Co. v. FMC Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hart Engineering Co. v. FMC Corp., 593 F. Supp. 1471, 39 U.C.C. Rep. Serv. (West) 1313, 1984 U.S. Dist. LEXIS 23681 (D.R.I. 1984).

Opinion

OPINION and ORDER

SELYA, District Judge.

In this diversity action, 28 U.S.C. § 1332, plaintiff Hart Engineering Company (Hart) seeks to recover damages for costs incurred in the removal, shipment and reinstallation of six drive bases taken from clarifiers supplied by the defendant FMC Corporation (FMC) for use at the municipal waste water treatment facility in Holyoke, Massachusetts. Count one of plaintiff’s complaint alleges a breach of express and implied warranties made in connection with the sale of the clarifiers. Count two alleges that FMC ignored its contractual obligations to Hart in the premises. The remaining two statements of claim seek damages under principles of tort law, count three being grounded in negligence and count four in strict product liability. 1

*1474 The ease was docketed in this court on March 25, 1983. In January of 1984, the parties crossmoved for summary judgment. Those motions were each denied without prejudice on April 20, 1984. The plaintiff and defendant then agreed to submit the case to the court for decision on the merits essentially on their respective summary judgment initiatives, as fleshed out by an agreed statement of facts and certain other supplemental materials. Pursuant to the court’s order of May 24, 1984, the parties submitted a joint bench book containing and/or referencing the desiderata to be considered by the court. 2 In addition, the matter has been amplificatively briefed. Oral argument has been waived. This opinion, therefore, constitutes the court’s findings of fact and conclusions of law as required by Fed.R.Civ.P. 52(a).

I.

Hart is a Rhode Island corporation with its principal place of business in East Providence, Rhode Island. FMC is incorporated under the laws of the Commonwealth of Pennsylvania and has its principal place of business in that state. Jurisdiction is premised on diversity of citizenship and the existence of a controversy in an appropriate amount. 28 U.S.C. § 1332.

The present dispute arose out of a purchase agreement entered into by Hart and FMC in early February of 1979. At that time, FMC agreed to supply a half dozen clarifiers and various other kinds of machinery for Hart’s use at the municipal sewage treatment plant then under construction in Holyoke, Massachusetts (Hart having theretofore been awarded the general contract by the city). The agreement as finally executed by the parties was the product of a hard-driven (albeit not impolitic) battle of proposals and counterproposals between individuals savvy in the trade. Under the terms of that agreement, the plaintiff committed to purchase two main clarifiers, four secondary clarifiers, two gravity thickeners, and additional overload devices to be used in conjunction with already existing clarifiers. The total cost of the items to be bought aggregated $320,-000.

The contract contained some twelve general terms and conditions governing the relationship between the buyer and the seller. One of those conditions provided in material part:

4. WARRANTY. New equipment manufactured by Seller is warranted to be free from defects in material and workmanship under normal use and service for a period of one year from date of shipment; Seller’s obligation under this warranty being limited to repairing or replacing at its option any part found to its satisfaction to be so defective provided that such part is, upon request, returned to Seller’s factory from which it was shipped, transportation prepaid____ THIS WARRANTY IS EXPRESSLY IN LIEU OF ANY OTHER WARRANTIES, EXPRESS OR IMPLIED AND SELLER SPECIFICALLY DISCLAIMS ANY IMPLIED WARRANTY OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE.

The last of those conditions provided:

12. DISCLAIMER OF CONSEQUENTIAL DAMAGES, LIQUIDATED DAMAGES OR PENALTIES. SELLER SHALL NOT BE LIABLE FOR CONSEQUENTIAL DAMAGES. CONSEQUENTIAL DAMAGES FOR THE PURPOSES OF THIS AGREEMENT SHALL INCLUDE BUT NOT BE LIMITED TO LOSS OF USE, INCOME, OR PROFIT, *1475 OR LOSS OF OR DAMAGE TO PROPERTY INCLUDING, BUT WITHOUT LIMITATION, PRODUCTS MANUFACTURED, PROCESSED OR TRANSPORTED BY THE USE OF THE EQUIPMENT, OCCASIONED BY OR ARISING OUT OF THE OPERATION, USE, INSTALLATION, REPAIR OR REPLACEMENT OF THE EQUIPMENT OR OTHERWISE....

In accordance with its obligations under the contract, the defendant manufactured the six clarifiers and shipped them to Holyoke in May of 1980. They were subsequently installed. For nearly two years after the goods were forwarded, there was no communication of any significance between Hart and FMC. That state of equipoise began to dissolve, however, in February of 1982. The wellspring of the instant dispute was unearthed at that time, when Tighe & Bond (T & B), the consulting engineers who had supervised erection of the plant for the city of Holyoke, discovered a malfunction in one of the new clarifiers supplied by FMC. This trickle of dissatisfaction dampened few spirits. Hart routinely notified the defendant of the problem, and at least one FMC employee sojourned to Holyoke to investigate the matter. With representatives of FMC and Hart in attendance, T & B thereafter diagnosed the malady to be the absence of major portions of weld from the clarifier’s drive base. That discovery, however, revealed only the tip of what was soon found to be a ubiquitous iceberg; subsequent perscrutation by the consulting engineers dredged up the unhappy finding that substantial segments of weld were missing from the drive base components of all six of the clarifiers manufactured by the defendant.

The effluent stream of contentiousness thereafter began to run downhill. A flurry of communications between the plaintiff, the defendant, and T & B ensued. In an apparent effort to ameliorate an increasingly tense situation, the defendant offered to perform field repairs on the defective drive base components. In a letter to the plaintiff dated March 24, 1982, T & B, with obvious reluctance, agreed to allow the field repairs to go forward on a “trial basis.” This acquiescence was to be conditioned, however, on FMC’s and/or Hart’s acceptance of financial responsibility (i) for costs to be expended in cleaning out each tank as the work progressed, and (ii) for expenses to be incurred in monitoring and evaluating the “failure and repair” of the units. As a further stipulation, T & B also insisted that the defendant furnish “an extended five year warranty from date of acceptance of the equipment repairs.” A copy of that letter was sent to FMC by Hart. Not surprisingly, the proposition failed to evoke a chorus of assents.

In a letter from the defendant to the plaintiff dated March 26, 1982, A. Joseph Antunes, FMC’s manager of water treatment, stated in pertinent part,

We have been surprised at the entire reaction to the situation since we consider the problem to be a warranty problem.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alan Brown v. Louisiana-Pacific Corporation
820 F.3d 339 (Eighth Circuit, 2016)
Baptist Memorial Hospital v. Argo Construction Corp.
308 S.W.3d 337 (Court of Appeals of Tennessee, 2009)
In Re Access Cardiosystems, Inc.
361 B.R. 626 (D. Massachusetts, 2007)
Robertson Stephens, Inc. v. Chubb Corp.
473 F. Supp. 2d 265 (D. Rhode Island, 2007)
Kennedy v. Acura, 01-4063 (2002)
Superior Court of Rhode Island, 2002
Gail Frances, Inc. v. Alaska Diesel Electric, Inc.
62 F. Supp. 2d 511 (D. Rhode Island, 1999)
Besicorp Group, Inc. v. Thermo Electron Corp.
981 F. Supp. 86 (N.D. New York, 1997)
Swift River . . . v. Zurich Ins.
D. New Hampshire, 1996
Ritter v. Custom Chemicides, Inc.
912 S.W.2d 128 (Tennessee Supreme Court, 1995)
Doyle v. Hoyle
D. New Hampshire, 1995
Boston Investment Property 1 State v. E.W. Burman, Inc.
658 A.2d 515 (Supreme Court of Rhode Island, 1995)
In Re: v. Beach Shellfish
First Circuit, 1994
Purina Mills, Inc. v. Askins
875 S.W.2d 843 (Supreme Court of Arkansas, 1994)
Portland General Electric Co. v. Westinghouse Electric Corp.
842 F. Supp. 161 (W.D. Pennsylvania, 1993)
Providence & Worcester Railroad v. Sargent & Greenleaf, Inc.
802 F. Supp. 680 (D. Rhode Island, 1992)
Canal Electric Co. v. Westinghouse Electric Co.
973 F.2d 988 (First Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
593 F. Supp. 1471, 39 U.C.C. Rep. Serv. (West) 1313, 1984 U.S. Dist. LEXIS 23681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hart-engineering-co-v-fmc-corp-rid-1984.