Dyer v. City of Boston

172 N.E. 235, 272 Mass. 265, 70 A.L.R. 979, 1930 Mass. LEXIS 1217
CourtMassachusetts Supreme Judicial Court
DecidedJuly 2, 1930
StatusPublished
Cited by24 cases

This text of 172 N.E. 235 (Dyer v. City of Boston) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dyer v. City of Boston, 172 N.E. 235, 272 Mass. 265, 70 A.L.R. 979, 1930 Mass. LEXIS 1217 (Mass. 1930).

Opinion

Sanderson, J.

This is an action of contract in two counts. In the first the plaintiffs allege a breach by the defendant of their written agreement for the construction of a boiler plant for the defendant. In the second they seek to recover upon an account annexed. The case was referred to an auditor, and upon the coming in of his report was heard by a judge of the Superior Court without further evidence. He found for the plaintiffs in the sum of $5,080.18. Their exceptions are confined to rulings given and refused.

On or about April 16,1928, the plaintiffs, who are partners, entered into a written agreement with the defendant whereby they were to furnish all materials and perform all the work necessary for and incident to the construction of the boiler plant for $85,872, subject to additions and deductions in accordance with the terms of the contract. The plaintiffs bound themselves to carry on the work with due diligence and despatch and tq bring it to entire completion according to the specifications within six months from the date of the contract. The plans and specifications required that the foundations should be of concrete piles set at such a depth as would give to each pile a bearing capacity of five tons per square foot. In case the piles were carried to a grade lower than indicated on the drawings (grade minus sixteen) the plaintiffs were to be paid for such increase at the rate of $60 per lineal foot, and in case the piles were not required to go to that depth the defendant was to deduct $60 per lineal foot from the contract price.

Parts of the contract and specifications are not in the record, but among the provisions there appearing are the following: payments are to be made monthly on certificates when and as authorized by the architects; all orders and certificates are to be approved by the duly authorized representatives of the city and are not to be binding on the city until so approved; the architects shall issue certificates for payment monthly based on the contractor’s monthly appli[268]*268cations, and provision is made that each certificate shall be for eighty-five per cent of the value of the work done since the date to which the preceding certificate was computed. A provision is also made for reimbursement for loss or injury suffered by the contractor by any act or neglect of the city, its agents or employees. It provides for termination of the employment if the contractor neglects in any respect to prosecute the work with promptness and diligence, or fails in the performance of any of the agreements therein contained, if the architect certifies that such neglect or failure is a sufficient ground for such termination, with the right on the part of the city to enter upon the premises and take possession, for the purpose of completing the work included under the contract, of all materials, tools and appliances, and to employ any other person or persons to finish the work and provide the material therefor; and in case of such termination the contractor is not entitled to any further payment under the contract until the work is wholly finished, at which time, if the unpaid balance of the amount to be paid under the contract shall exceed the expense incurred by the city in finishing the work, such excess shall be paid by the city to the contractor, but if such expense shall exceed the unpaid balance, the contractor shall pay the difference to the city.

The plaintiffs entered upon the performance of their contract the last of April, 1928, and proceeded with the work according to its terms until a controversy arose between the parties as to the payment for additional piling and the removal of certain iron slag. In May the plaintiffs discovered that it would be necessary to drive the piles to a depth greater than that indicated in the drawings in order that each should have the specified bearing capacity, and so notified the defendant’s' architects. They also gave notice of the necessity of removing certain iron slag from the site of a chimney to be built. They received written authorization from the proper city officials to drive the piles to the required depth and to remove the slag, and on May 26, 1928, an order for change in the contract with the following terms was duly executed by the [269]*269defendant and delivered: “Drive the piles to additional depth required for firm bearing as per order of City Inspector on job; the additional depth to be determined by the records of the above named City Inspector. Excavate at Northeast corner where chimney is to be located and remove iron slag deposit so that piles under chimney may be driven and remove the slag deposit wherever necessary for driving of piles.” About ten days before this order for change was executed the defendant’s architects, in a letter to the plaintiffs purporting to authorize the driving of piles deeper than the grade indicated in the drawings and also the removal of slag, stated that the plaintiffs would receive additional compensation according to the terms of their contract for driving piles deeper than was originally intended.

The work of removing the slag was completed on May 31, 1928, and the plaintiffs’ charge for the same.was referred to as extra in their communication asking that this sum be added to their requisition for work completed in May. The price was found by the auditor to be fair and reasonable for the work done. The plaintiffs also completed in May the work of driving all concrete piles, and their charge for additional length of all piles driven to a lower grade than indicated in the drawings was $37,740, computed on the basis of six hundred and twenty-nine extra feet at $60 per foot. They requested the defendant to add this sum as an extra to their requisition for work done in May. The auditor found that the piles were in fact driven the number of extra feet specified and that the charge was proper under the contract unless ruled to be unconscionable. Neither of these items sought to be collected as extras has been paid. The plaintiffs’ charges for other work done in April, May and June were approved by the architects and paid. Their charge for work in July was allowed by the architects but no certificate for payment was issued by them and the amount has not been paid. On June 22 they notified the architects and the proper city official that it was imperative that certificates for the payment of the full amount of their charges for driving piles and removing slag issue at once; [270]*270otherwise that they would not be able to continue with the work until such payment was received. On July 9 they again gave notice that to carry on the contract they must receive these payments at once, that they could not proceed further with any work until they had received them, and that they were so notifying the defendant and their bonding company, but that when the amounts were received they would proceed with the completion of their contract. On July 14, 1928, the plaintiffs filed a claim for damages in the sum of $75 a day for each working day from July 9 until such time as the requisitions for slag removal and additional pilings should be paid. On August 17, 1928, the plaintiffs wrote the architects that the failure to pay for the July work was a breach of contract and that the charges for extras had nothing to do with this payment. They did not for this reason, however, undertake to rescind the contract nor did they completely abandon the work, but continued to keep the superintendent and some workmen on the place and left there the materials and equipment, prepared to resume full operations when their demand of payment for slag removal and additional piling should be paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boston Edison Co. v. City of Boston
459 N.E.2d 1231 (Massachusetts Supreme Judicial Court, 1984)
Thomas O'Connor & Co. v. City of Medford
448 N.E.2d 1276 (Massachusetts Appeals Court, 1983)
County of Suffolk v. Labor Relations Commission
444 N.E.2d 953 (Massachusetts Appeals Court, 1983)
Boston Teachers Union v. School Committee
434 N.E.2d 1258 (Massachusetts Supreme Judicial Court, 1982)
Boston Gas Co. v. City of Boston
433 N.E.2d 483 (Massachusetts Appeals Court, 1982)
Glynn v. City of Gloucester
401 N.E.2d 886 (Massachusetts Appeals Court, 1980)
Urban Transport, Inc. v. Mayor of Boston
369 N.E.2d 1135 (Massachusetts Supreme Judicial Court, 1977)
Boston Teachers Union v. School Committee of Boston
350 N.E.2d 707 (Massachusetts Supreme Judicial Court, 1976)
City of Marlborough v. Cybulski, Ohnemus & Associates, Inc.
346 N.E.2d 716 (Massachusetts Supreme Judicial Court, 1976)
Arthur R. Murphy, AIA, & Associates, Inc. v. City of Brockton
305 N.E.2d 103 (Massachusetts Supreme Judicial Court, 1973)
Old Colony Trust Co. v. City of Quincy
24 Mass. App. Dec. 98 (Mass. Dist. Ct., App. Div., 1962)
Duff v. Town of Southbridge
90 N.E.2d 12 (Massachusetts Supreme Judicial Court, 1950)
Adalian Bros. v. City of Boston
84 N.E.2d 35 (Massachusetts Supreme Judicial Court, 1949)
Commissioners of Woburn Cemetery v. Treasurer of Woburn
64 N.E.2d 627 (Massachusetts Supreme Judicial Court, 1946)
Metcalfe v. Town of Franklin
9 Mass. App. Div. 37 (Mass. Dist. Ct., App. Div., 1943)
Baker v. Commonwealth
45 N.E.2d 470 (Massachusetts Supreme Judicial Court, 1942)
Atwood v. City of Boston
37 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1941)
Cook v. Overseers of Public Welfare
22 N.E.2d 189 (Massachusetts Supreme Judicial Court, 1939)
Collins v. City of Lawrence
3 Mass. App. Div. 9 (Mass. Dist. Ct., App. Div., 1937)
Continental Construction Co. v. City of Lawrence
9 N.E.2d 550 (Massachusetts Supreme Judicial Court, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
172 N.E. 235, 272 Mass. 265, 70 A.L.R. 979, 1930 Mass. LEXIS 1217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dyer-v-city-of-boston-mass-1930.