Webb Granite & Construction Co. v. City of Worcester

73 N.E. 639, 187 Mass. 385, 1905 Mass. LEXIS 1006
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 28, 1905
StatusPublished
Cited by17 cases

This text of 73 N.E. 639 (Webb Granite & Construction Co. v. City of Worcester) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Webb Granite & Construction Co. v. City of Worcester, 73 N.E. 639, 187 Mass. 385, 1905 Mass. LEXIS 1006 (Mass. 1905).

Opinion

Braley, J.

The contract between the parties rests on an order of the city council passed May 24, 1897, that required the street commissioner, under the direction of the mayor, to construct “ a three arch masonry bridge ” at the causeway crossing Lake Quinsigamond, “ the cost of construction to be charged to street construction account.”

In the litigation which took place over this order, two suits were brought to test its validity. It was decided in one, that as the order was for specific repairs of a public way, which the city council had authority to make, a petition for a writ of certiorari to quash the record should be denied ; and in the other, that a bill in equity brought by ten taxable inhabitants of the defendant under Pub. Sts. c. 27, § 129, after the contract had been signed, to restrain the expenditure of money thereunder, and in which the plaintiff was joined as a party defendant, should be dismissed. Bigelow v. City Council of Worcester, 169 Mass. 390. See also St. 1893, c. 444, § 20, which is the revised charter of the defendant, and Worcester v. County Commissioners, 167 Mass. 565.

Although the order must be treated as valid, the defendant now contends that on July 30, 1897, when the contract was [387]*387executed, there was no sufficient appropriation available from which the cost of the bridge could properly be paid. If this is proved, then the city was-prohibited from incurring this liability, as the revised charter provides that “ No sum appropriated for a specific purpose shall be expended for any other purpose, and no expenditure shall be made and no liability incurred by or on behalf of the city until the city council has duly voted an appropriation sufficient to meet such expenditure or liability, together with all prior unpaid liabilities which are payable therefrom.” St. 1893, c. 444, § 29.

That the plaintiff was required to take notice of this statutory limitation may be conceded, yet the defendant’s authority to bind itself was limited only by conditions that depended upon previous lawful municipal action.

The specific appropriation provided by the order of June 1, 1897, “ for the construction of streets and bridges ” was more than sufficient to pay for the bridge and construction of streets previously ordered, unless damages awarded for lands taken in the laying out of these streets are to be deducted.

All the decrees taking the land, awarding damages therefor and establishing the lay out, were in the usual form, and it was within the power of the city council to have made an appropriation from which damages should be paid when the lands were entered upon and possession taken for purposes of construction. Pub. Sts. c. 49, §§ 14, 69, 91. St. 1892, c. 415, § 4. St. 1893, c. 444, § 20. See Harding v. Medway, 10 Met. 465.

No money, however, was appropriated by any separate order.

Assuming without deciding .that if damages are to be paid from this account it must be' for the reason that the general words “ construction of streets ” include payment for land acquired by right of eminent domain over which they are laid out, this defence is not sufficient to enable the defendant to avoid the contract. In order to sustain this position it is not enough to prove that the total “ estimated expense ” shown by the orders for streets thus reduced the appropriation, even if these estimates are held to combine damages and costs of construction ; for the liability of the city to pay therefor must have been actually incurred. The restriction of the right to contract which is invoked covers only all prior liabilities which were [388]*388“ payable therefrom.” Its liability to pay damages did not accrue until the city had entered upon and taken possession of the land for the purpose of constructing the streets. Pub. Sts. c. 49, §§ 14, 69, 91. Corey v. Wrentham, 164 Mass. 18, 22, and cases cited. Pegler v. Hyde Park, 176 Mass. 101, 103. Wheeler v. Fitchburg, 150 Mass. 350, 352.

Bartlett Place and Carlton Street were among the new streets. Both were ordered constructed May 10, 1897, and under the lay out of each substantial land damages had been awarded, which, not being accepted, were afterwards increased as the result of trials in the Superior Court. The defendant admits that if these damages are not to be deducted it was free to' make the contract. The decrees of the city council laying out each street might have contained a provision prescribing the time in which buildings should be removed and directing the delimitation of each way by the setting of bounds, and that notice be given to the owners of buildings to remove them. White v. Foxborough, 151 Mass. 28, 36, 37. Taber v. New Bedford, 135 Mass. 162. This was not done, but the orders for construction in each case authorized and directed the street commissioner, under the direction of the mayor, to construct the streets in accordance with the decree. The street commissioner was thus charged with the duty and, under the revised charter, clothed with authority to do whatever was required to carry out these orders unless otherwise directed by the mayor, who does not appear to have interposed. See St. 1893, c. 444, § 40.

The act of the city engineer in setting bounds showing the lines of these streets was not done under any order, ordinance or statute that imposed upon him the duty to take such action independently of the street commissioner.

Indeed the inference is that the work was done for "his own convenience, as the agreed facts state that the street commissioner, who, on June 17, 1897, had notified the landowners to remove their buildings, did not direct the setting of bounds, neither did he know that they had been set.

There is a further uncontroverted statement by the street commissioner, which is incorporated in and made a part of the agreed facts, that “ the first work done under my direction and with my knowledge as street commissioner for the purpose of [389]*389the construction of these streets was on September 13,” 1897; and this must be considered as fixing the date when possession was actually taken for this purpose.

A notice previously given to remove buildings, even if followed by their removal, from the proposed locations, though a significant act that might indicate an ultimate design to work the streets, does not constitute an entry upon or taking possession of the land, and is not sufficient to give the landowner a claim for damages for land taken. Pub. Sts. c. 49, §§ 14, 88. Parker v. Norfolk, 150 Mass. 489. Corey v. Wrentham, ubi supra. Wilcox v. New Bedford, 140 Mass. 570.

If no further steps are taken any expense to which he may be put by such preliminary measures is provided for by the express language of the statute, which gives to him full indemnity.

At the date of the contract, therefore, the liability to pay the awards had not arisen or become fixed, and the estimates made for this purpose were not “ unpaid liabilities.”

The defendant further contends that even if the order was valid, and the contract not prohibited, the street commissioner was not authorized to execute the agreement.

That the city council legally could authorize the building of the bridge must be taken as settled, and the authority of the street commissioner to act for the defendant may be found in the terms of the order itself. The language rrsed is broad.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chase Precast Corp. v. John J. Paonessa Co.
554 N.E.2d 868 (Massachusetts Appeals Court, 1990)
Fauci v. Denehy
127 N.E.2d 477 (Massachusetts Supreme Judicial Court, 1955)
Scannell v. State Ballot Law Commission
87 N.E.2d 16 (Massachusetts Supreme Judicial Court, 1949)
Sanford v. Boston Edison Co.
64 N.E.2d 631 (Massachusetts Supreme Judicial Court, 1946)
Daddario v. City of Pittsfield
17 N.E.2d 894 (Massachusetts Supreme Judicial Court, 1938)
Collins v. City of Lawrence
3 Mass. App. Div. 9 (Mass. Dist. Ct., App. Div., 1937)
Continental Construction Co. v. City of Lawrence
2 Mass. App. Div. 27 (Mass. Dist. Ct., App. Div., 1937)
G. M. Bryne Co. v. Town of Barnstable
191 N.E. 45 (Massachusetts Supreme Judicial Court, 1934)
Dyer v. City of Boston
172 N.E. 235 (Massachusetts Supreme Judicial Court, 1930)
Boston Penny Savings Bank v. Boston & Maine Railroad
138 N.E. 907 (Massachusetts Supreme Judicial Court, 1923)
Peckham v. Industrial Securities Co.
113 A. 799 (Superior Court of Delaware, 1921)
Merrill v. City of Lowell
236 Mass. 463 (Massachusetts Supreme Judicial Court, 1920)
Goldman v. City of Worcester
236 Mass. 319 (Massachusetts Supreme Judicial Court, 1920)
Fiske v. City of Worcester
219 Mass. 428 (Massachusetts Supreme Judicial Court, 1914)
Moshenz v. Independent Order Ahawas Israel
102 N.E. 324 (Massachusetts Supreme Judicial Court, 1913)
Kansas City v. Woerishoeffer
155 S.W. 779 (Supreme Court of Missouri, 1913)
Adams v. County of Essex
91 N.E. 557 (Massachusetts Supreme Judicial Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
73 N.E. 639, 187 Mass. 385, 1905 Mass. LEXIS 1006, Counsel Stack Legal Research, https://law.counselstack.com/opinion/webb-granite-construction-co-v-city-of-worcester-mass-1905.