G. M. Bryne Co. v. Town of Barnstable

191 N.E. 45, 286 Mass. 544, 1934 Mass. LEXIS 1099
CourtMassachusetts Supreme Judicial Court
DecidedMay 29, 1934
StatusPublished
Cited by12 cases

This text of 191 N.E. 45 (G. M. Bryne Co. v. Town of Barnstable) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. M. Bryne Co. v. Town of Barnstable, 191 N.E. 45, 286 Mass. 544, 1934 Mass. LEXIS 1099 (Mass. 1934).

Opinion

Field, J.

This is an action of contract to recover from the defendant town compensation for building a bridge. The declaration as amended is in five counts — the first on a written contract dated May 15, 1911, the second, third and fourth each on an account annexed, and the fifth on an express contract alleging that on or about May 15, 1911, the plaintiff entered into a written contract with the defendant; “that immediately thereafter it commenced the construction of the bridge in accordance with the terms of said contract and with specifications and the plans accompanying the same; that thereafter by agreement of the parties said contract was modified in certain respects so as to provide among other things that the plaintiff should proceed with changes in and additions to said work [547]*547without waiting for written orders in accordance with the terms of said written contract, and that any increased cost incurred by the plaintiff by reason thereof should be paid by the defendant plus fifteen per cent.” The case was heard by an auditor, who filed a report. Thereafter it was tried before a judge and a jury on the auditor’s report and other evidence. The plaintiff waived the third and fourth counts of its declaration and the judge directed a verdict for the defendant on the second count. The defendant admitted that the plaintiff was entitled to recover the sum of $2,976.61 under the original contract, but did not admit that the plaintiff was entitled to recover any amount on the fifth count. The judge, subject to the plaintiff’s exception, required the plaintiff to elect on which count it would go to the jury and it elected to go to the jury on the fifth count. The defendant’s motion for a directed verdict was denied and the defendant excepted. The defendant also excepted to the refusal of the judge to make certain requested rulings and to portions of the charge. And the plaintiff excepted to the exclusion of certain evidence, to the refusal of the judge to make certain requested rulings, to certain rulings made at the request of the defendant and to portions of the charge. There was a verdict for the plaintiff on the fifth count which, after a part of the amount thereof was remitted, stood for the sum of $14,549.36.

The written contract of May 15, 1911; including plans, specifications and “proposal sheet” which were a part of it, was in evidence. It provided that the work should be completed on or before October 15, 1911. The contract price fixed thereby was $12,750 with a further provision for payment for “extra work or materials, if any, performed or furnished” in accordance with art. 5 of the contract, “the reasonable cost of the work or materials as determined by the Engineer plus fifteen percentum (15%) of such cost.” Said art. 5 is as follows: “The Engineer may at any time make such changes in the amount of any of the descriptions of work to be done, or in the quality of the material to be used, as the interests of the work or of the Town may in his opinion require. If any such [548]*548changes should diminish the quantity of work to be done, they shall not constitute a claim for damages or for anticipated profits on the work that may be so dispensed with. If the amount of work shall be increased by the enlargement of any part of the same or by any contingent work which the Engineer may deem necessary to facilitate its execution or render it in any particular conformable to local circumstances, or which may be deemed by the Engineer necessary for perfecting the work beyond what is provided for in this agreement, or if such work is not similar to work herein contracted for, it shall be paid for as extra work at the rate named in the proposal sheet attached hereto and made a part of this contract. But it is distinctly understood and agreed that no such changes shall be made except upon the written order of the Engineer. And the Contractor hereby expressly covenants and agrees that he will not, under any circumstances, or for any reason whatsoever, make any such changes unless and until so specified and set forth in writing. And the Contractor further hereby expressly covenants and agrees that he will not, under any circumstances or for any reason whatsoever, make any claim or demand for any extra compensation in excess of the prices named in this agreement, excepting such compensation as may be specified for extra work performed as provided for in this paragraph. And the Contractor is hereby absolutely prohibited from doing any work or furnishing any material, for which he will demand extra compensation in excess of that provided for in this contract, or in any other way departing or varying from the provisions hereof, or from said plans and specifications, upon any order or request, whether verbal or in writing, given by any Assistant Engineer, Inspector, or any other Employee or Agent of the Town.”

There was evidence that the payments by the defendant to the plaintiff aggregated $14,578.75. It was agreed “that the bridge was completed and accepted by the town about August 10, 1912,” and “that the final estimate and certificate of the engineer [for which provision was made in the contract] showed there was a balance of [549]*549$2,976.61 due from the defendant to the plaintiff and unpaid consisting of $1,413.13 admittedly due on the original contract of $12,750 and $1,563.48 admittedly due for extras.” The votes of the town in regard to building the bridge were as follows: At a town meeting on March 7, 1911, the town voted “unanimously to issue notes, bonds or script of the Town for $14,000, for the purpose of building a concrete bridge in the Village of Osterville, known as the Grand Island Bridge, and that a committee of three be appointed to act with the surveyors of highways in building said bridge. The following are appointed as a committee to act with the surveyors of highways: E. S. Crocker, James Bearse and John Bursley.” At a town meeting on March 5, 1912, a report was made by the bridge committee, and accepted by the town, containing the following statements: “It was finally decided by the Board of Harbor and Land Commissioners that they would not authorize a bridge having less than a 10-feet clearance under the drawway. Plans for the bridge with this clearance were then prepared by the engineer, and bids were first opened April 29, 1911. Two bids only were submitted in this instance, the lower being $16,000, which was $2,000 more than the amount appropriated for the work. The plans were then somewhat modified and new bids were called for, which were opened on May 13, 1911. The lowest bid submitted at this opening was that of George M. Bryne Company of Boston, who offered to build the bridge complete for $12,750. The bids ranged from this figure up to $23,000. The contract was awarded to the lowest bidder and actual work on the new bridge was started in June, 1911. The work progressed slowly from that date, and on August 29, 1911, the contractor discontinued active work on the bridge, and your committee has been unable to find any satisfactory reason for such discontinuance. Your committee had hoped that the contractor would resume operation within a reasonable length of time in order that the structure might be completed at the date named in the contract, namely, October 15, 1911. Work, however, has not been resumed up to the present [550]*550time, and the bridge is now about one-third completed, the substructure being practically complete. Your committee has availed itself of the advice of the Town counsel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Old Colony Trust Co. v. City of Quincy
24 Mass. App. Dec. 98 (Mass. Dist. Ct., App. Div., 1962)
The Salisbury Water Supply Co. v. Town of Salisbury
167 N.E.2d 320 (Massachusetts Supreme Judicial Court, 1960)
Duff v. Town of Southbridge
90 N.E.2d 12 (Massachusetts Supreme Judicial Court, 1950)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
Cerwonka v. Inhabitants of the Saugus
9 Mass. App. Div. 1 (Mass. Dist. Ct., App. Div., 1944)
George A. Fuller Co. v. Commonwealth
21 N.E.2d 529 (Massachusetts Supreme Judicial Court, 1939)
McCarthy v. City of Salem
4 Mass. App. Div. 116 (Mass. Dist. Ct., App. Div., 1939)
Daddario v. City of Pittsfield
17 N.E.2d 894 (Massachusetts Supreme Judicial Court, 1938)
Continental Construction Co. v. City of Lawrence
2 Mass. App. Div. 27 (Mass. Dist. Ct., App. Div., 1937)
McHenry v. City of Lawrence
3 N.E.2d 262 (Massachusetts Supreme Judicial Court, 1936)
Daddario v. Town of Medfield
2 N.E.2d 193 (Massachusetts Supreme Judicial Court, 1936)
Blair v. National Reserve Insurance
199 N.E. 337 (Massachusetts Supreme Judicial Court, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
191 N.E. 45, 286 Mass. 544, 1934 Mass. LEXIS 1099, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-m-bryne-co-v-town-of-barnstable-mass-1934.