V & V Construction Co. v. McGonagle

42 Mass. App. Dec. 121
CourtMassachusetts District Court, Appellate Division
DecidedDecember 27, 1968
DocketNos. 24205/66 & 24406
StatusPublished

This text of 42 Mass. App. Dec. 121 (V & V Construction Co. v. McGonagle) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
V & V Construction Co. v. McGonagle, 42 Mass. App. Dec. 121 (Mass. Ct. App. 1968).

Opinion

Cox, J.

These are two contract actions which were tried together.

In the first action the plaintiff seeks to recover a balance of $1,154.72 for completing a dwelling owned by the defendant in West Falmouth. The declaration is in three counts, all for the same cause of action. Count one is for [124]*124labor and materials. Count two is upon an account annexed. Count three is upon a quantum meruit for substantial performance. The answer is a general denial and payment. It also alleges that the plaintiff breached its agreement by failing to perform in a workmanlike manner, by performing carelessly and negligently and that the work was not completed by the plaintiff. There was a finding for the corporate plaintiff in the sum of $1,154.72 on all three counts. This case (No. 24205) is reported because the defendant claims to be aggrieved by the denial of his requested rulings numbers 3, 4, and 5 which, with the justice’s action thereon, are as follows:

“3. The evidence warrants a finding that the plaintiff failed to substantially perform its contract with the defendant and is barred in its claim for quantum meruit. Denied as 1 find that the Plaintiff did substantially perform his contract.
“4. The evidence warrants a finding that the plaintiff willfully departed from the terms of the contract without justification or excuse in matters other than those falling within the rule of de minimis so as to be barred in its claim for quantum meruit. Denied as I find that the plaintiff did, not wilfully depart from the terms of the contract as claimed in this request.
[125]*125“5. The' evidence warrants that the defendant was justified in his refusal to pay the Plaintiff’s claim of $1,154.72 as alleged in the Plaintiff’s declaration. Corbin on contracts, Vol. 3A, sec. 708, p. 322, 1960 West Publishing Edition. Denied. There is no legal justification for the defendant’s refusal to fay.

In the second case, No. 24406, the plaintiff McGonagle claims damages for breach of contract. In that case there was a finding for the defendant corporation. That case is also reported because the plaintiff, McGonagle, claims to be aggrieved by the denial of his requested rulings numbers 3, 4, 5, 6, 7, 8, 12 and 13. Numbers 5 and 6 are waived.

The trial justice made special findings in both cases which may be summarized as follows : On July 14, 1965 the parties entered into an agreement whereby Y & Y Construction Company, Inc. was to complete McGonagle’s unfinished house on Lot 16, Nemasket Road, West Falmouth, except masonry work, seeding and grading, for $12,800.00. The plaintiff did complete the house according to the contract and is entitled to the balance of $1,154.72. “I find (No. 24406) that the plaintiff (Mc-Gonagle) had certain trouble with the septic tank system which resulted in expense to him for repair and in loss of rentals. I find however that this trouble was not the fault of the [126]*126defendant or Ms agents but was due to the nature of the terrain and due in part to the negligence of the parties who were hired by the Plaintiff (McGonagle) to repair the same.

“I further find that certain defects to the premises which the plaintiff has listed are exaggerated and on all the evidence I find that the plaintiff’s claim for defective workmanship is without merit.

The requests numbers 3, 4, 5 by the defendant McGonagle in case No. 24205, were for rulings that the evidence warrants findings that the plaintiff corporation failed to substantially perform its contract wilfully, and without justification or excuse, departed from the contract in matters not trivial, and that the defendant was therefore warranted in his refusal to pay the balance.

If there was evidence which would support such findings “the defendant was entitled to the rulings requested or to a statement by the judge of findings of fact sufficient to show that it (they) had become irrelevant.” Hurley v. Ornsteen, 311 Mass. 477, 480. On that point the opinion cites Bresnick v. Heath, 292 Mass. 293, 298. Strong v. Haverhill Electric Co., 299 Mass. 455, 456. Marquis v. Messier, 303 Mass. 553, 555, 556.

The defendant McGonagle contends that there ;was evidence which would support as warranted the findings requested' and therefore denial.of. the requests was error. He .argues [127]*127particularly that it was error for the trial justice to excuse the plaintiff from performing the contract with reference to the septic tank because of “the nature of the terrain.”

The installation of the septic tank system was the corporation’s obligation. The plaintiff corporation so" regarded it because it in fact made the installation. Having undertaken to install the septic tank system the plaintiff is not excused from adequate performance because of the nature of the terrain. It bound itself to do the work. “If it turns out that he (it) has agreed to do something which is impossible or impracticable, he (it) cannot for that reason alone refuse to go forward. Having made his (its) contract, he (it) must fulfill it or bear the consequences of a breach.” N. J. Magnan Co. v. Fuller, 222 Mass. 530, 533. See also Rowe v. Peabody, 207 Mass. 226, 234.

There must be complete performance to permit recovery on a contract. However, “One who in good faith substantially performs his contract may recover on a quantum meruit, Cutter v. Arlington Construction Co., 268 Mass. 88; Reynolds v. Cole, 272 Mass. 282, the sum recovered being the contract price, less ‘the amount by which the value of the house as left by the ... (builder) fell short of what that value would have been if the contract had been exactly performed.’ (cits.) What amounts to substantial performance of a building contract is to be determined in reference to the entire con[128]*128tract and what has been done and omitted to be done under it, Bowen v. Kimbell, 203 Mass. 364, and to recover under a quantum meruit the owner must obtain substantially what was called for by the contract. Lynch v. Culhane, 237 Mass. 172. But where the default is wilful there can be no recovery either on the contract or on a quantum meruit, (cits.)” The question is from Glazer v. Schwarts, 276 Mass. 54, 57. See also Albre Marble & Tile Company, Inc. v. Goverman, 353 Mass. 546, 550 and cases cited. Biggs v. Densmore, 323 Mass. 106, 108.

The proper installation of septic tank is an item of importance in connection with a dwelling. There was evidence that the tank leaked at the point where the pipe from the house was joined to it. There was evidence that the pipe leading from the tank to the filter field was improperly installed and consisted of inferior material; that the pipe was installed four inches under the surface of the driveway under which it passes and was broken; that the filter field seeped and blew out causing the septic material to drain back towards the back steps of the house; that the cost of repair was $866. and the loss of rentals.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlantic Building Corp. v. Whyte
168 N.E.2d 90 (Massachusetts Supreme Judicial Court, 1960)
ALBRE MARBLE & TILE CO. INC. v. Goverman
233 N.E.2d 533 (Massachusetts Supreme Judicial Court, 1968)
Mastercraft Wayside Furniture Co. v. Sightmaster Corp.
125 N.E.2d 233 (Massachusetts Supreme Judicial Court, 1955)
Concannon v. Galanti
202 N.E.2d 236 (Massachusetts Supreme Judicial Court, 1964)
Bowen v. Kimbell
203 Mass. 364 (Massachusetts Supreme Judicial Court, 1909)
Rowe v. Inhabitants of Peabody
93 N.E. 604 (Massachusetts Supreme Judicial Court, 1911)
N. J. Magnan Co. v. Fuller
222 Mass. 530 (Massachusetts Supreme Judicial Court, 1916)
Lynch v. Culhane
129 N.E. 717 (Massachusetts Supreme Judicial Court, 1921)
Cutter v. Arlington Construction Co.
167 N.E. 266 (Massachusetts Supreme Judicial Court, 1929)
Reynolds v. Cole
172 N.E. 91 (Massachusetts Supreme Judicial Court, 1930)
Glazer v. Schwartz
176 N.E. 613 (Massachusetts Supreme Judicial Court, 1931)
Bresnick v. Heath
198 N.E. 175 (Massachusetts Supreme Judicial Court, 1935)
Strong v. Haverhill Electric Co.
13 N.E.2d 39 (Massachusetts Supreme Judicial Court, 1938)
Marquis v. Messier
22 N.E.2d 473 (Massachusetts Supreme Judicial Court, 1939)
Hurley v. Ornsteen
42 N.E.2d 273 (Massachusetts Supreme Judicial Court, 1942)
Perry v. Hanover
50 N.E.2d 41 (Massachusetts Supreme Judicial Court, 1943)
Hoffman v. City of Chelsea
52 N.E.2d 7 (Massachusetts Supreme Judicial Court, 1943)
Brodeur v. Seymour
53 N.E.2d 566 (Massachusetts Supreme Judicial Court, 1944)
Liberatore v. Town of Framingham
53 N.E.2d 561 (Massachusetts Supreme Judicial Court, 1944)
Biggs v. Densmore
80 N.E.2d 38 (Massachusetts Supreme Judicial Court, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
42 Mass. App. Dec. 121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/v-v-construction-co-v-mcgonagle-massdistctapp-1968.