McConnell v. Corona City Water Co.

85 P. 929, 149 Cal. 60, 1906 Cal. LEXIS 215
CourtCalifornia Supreme Court
DecidedMarch 27, 1906
DocketL.A. Nos. 1495, 1496.
StatusPublished
Cited by72 cases

This text of 85 P. 929 (McConnell v. Corona City Water Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McConnell v. Corona City Water Co., 85 P. 929, 149 Cal. 60, 1906 Cal. LEXIS 215 (Cal. 1906).

Opinion

HENSHAW, J.

Plaintiff engaged himself to build for defendant a tunnel “in a good, substantial, and workmanlike manner to completion,” as far as the defendant might direct; “it being the intention to construct the said tunnel for the distance, of about 1,200 feet to the artesian wells, unless water in sufficient quantities is encountered before reaching that point.” It was stipulated “that said tunnel shall be constructed on the grades and according to the specifications of the engineers of the party of the second part in charge of the work. The tunnel will be timbered in a thoroughly workmanlike and practical manner so as to protect against outward and also inward pressure.” The defendant agreed to furnish all the lumber needed and required by the plaintiff for the tunnel, the lumber to be delivered on the ground at the shafts where it was to be used. The defendant also agreed to make progress payments during the performance of the work, on the first of each and every month, of seventy-five per cent of the work completed during the previous month at the agreed rate. Work was prosecuted under this contract until some 764 feet of tunnel had been driven, the progress payments being made upon the report of defendant’s engineers. At this point of the work the tunnel caved, and repair work upon it became necessary. This work was done by the plaintiff. The case L. A. No. 1,496 is to recover from defendant *62 the value of such work done up to March 20, 1902. The other action (L. A. No. 1,495) is for similar work done after that date, and also for damages for loss of estimated profits occasioned by defendant’s failure and refusal to allow plaintiff to proceed and complete the tunnel.

The action L. A. No. 1,496, for convenience, may first be considered. Plaintiff recovered judgment in the sum of two thousand dollars as the value of such extra work, and the defendant appeals. Its principal contention is that the contract for the construction of the tunnel was entire and indivisible; that under it, notwithstanding the provision for partial payments, as the work progressed, it became the duty of plaintiff to turn over to defendant a completed tunnel, driven and supported in a thoroughly workmanlike manner ; in particular, that plaintiff had agreed to timber the tunnel in a thoroughly workmanlike and practical manner so as to protect against outward and inward pressure; that the caving of the tunnel afforded evidence that it was not properly timbered; that it became the duty, therefore, of the plaintiff, at his own cost, to do this repair work; that it was repair work within the terms of the contract for which, treating the contract as indivisible, plaintiff had no cause of action, and the cost of which he himself should have borne. In support of this position, appellant cites many cases, such as Cox v. Western Pacific R. R. Co., 44 Cal. 18; Boyle v. Agawan Canal Co., 22 Pick. 381, [33 Am. Dec. 749] ; Seguin v. Debon, 3 Mart. (La.) 6, [5 Am. Dec. 735], to the effect that where a contractor agrees to do certain work, as the grading of a certain section of railroad, in the first case, or the construction of a certain part of a canal, as in the second case, even though the contracts may provide for progress payments, such contracts are entire and the provision for progress payments does not make them divisible. The soundness of these cases and of the proposition of law which they enunciate are not to be doubted, and in the case at bar if the question were whether the contract for the construction of this tunnel was entire and indivisible, there would be no hesitation in saying that it was. But this conclusion does not advance us in the determination of the real question in dispute between the parties. That question may be thus stated: Treating the contract as entire, was the extra work necessitated *63 by the caving of the tunnel, work within the contemplation of the contract, for which, therefore, the contractor was entitled to no remuneration, or was it work without the contemplation of the contract, for the doing of which he is entitled to compensation ? To answer this question, in addition to the provisions of the contract, resort must be had to the evidence. First, as to the terms of the contract, it will be noted that while the contractor agrees to timber in a thoroughly workmanlike and practical manner, so as to protect against outward and also inward pressure, he is controlled in this by the further provisions that the tunnel is to be constructed according to the specifications of the engineers of the company in charge of the work, and that the material for timbering is to be furnished him by defendant. The evidence shows that the plaintiff did drive the tunnel and timber it under the directions and specifications of the supervising engineers of defendant; that progress payments were made upon the certificate of the engineers of the completion according to the terms of the contract of certain portions of the tunnel; that" the contractor complained of the inferior quality of the timber which defendant persisted in delivering to him, and of the inadequacy of the timber work which the engineers directed should be done, all without avail; that he'was obliged to use the inferior lumber which was furnished; and that the timbering was done under the directions of and to the satisfaction of defendant’s engineers. Under such circumstances, notwithstanding that the contract is indivisible, there can be no hesitation in saying that the contractor’s responsibility for any completed portion of the work, so done under the direction and to the satisfaction of the engineers, relieves him from responsibility for such an accident as that which befell, that the responsibility for such accident must rest on the defendant, and that, notwithstanding that the contract was entire and indivisible, plaintiff was under no more compulsion to perform the extra work of repairing the cave in the tunnel so occurring than he would have been if it had been occasioned by a willful act of destruction upon the part of the defendant. The work became necessary to enable the contractor to proceed under his contract. It was occasioned by the failure of the defendant to furnish suitable timbers and by the mistake-of their engineers as to the strength of *64 the timbering required. As the contractor was doing his work under the directions and specifications o£ those engineers he cannot be held responsible for their errors or miscalculations.

Appellant further contends that while the court awarded a judgment in the sum of two thousand dollars for the value of the work and labor so done up to the 20th of March, 1902, the undisputed evidence offered by plaintiff himself shows that only $1,024.60 was actually so expended. To this contention respondent makes no answer, and the record seems to bear out appellant’s position in this regard. It is not necessary, however, that a new trial should be ordered. It is sufficient to order, and it is ordered, that the judgment be modified in this regard, with an allowance to plaintiff of the sum of $1,024.60, instead of two thousand dollars, and that, as so modified, it stands affirmed. The appellant will recover his costs upon this appeal.

L. A. No. 1,495. The complaint in this action charged in two counts: The first for the value of the extra labor performed as in L. A. No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Onyx Pharmaceuticals, Inc. v. Bayer Corp.
863 F. Supp. 2d 894 (N.D. California, 2011)
Robinson v. Powers
777 S.W.2d 675 (Missouri Court of Appeals, 1989)
Phillips v. Playboy Music, Inc.
424 F. Supp. 1148 (N.D. Mississippi, 1976)
Fracasse v. Brent
494 P.2d 9 (California Supreme Court, 1972)
Curzon v. Wells Cargo, Inc.
382 P.2d 906 (Idaho Supreme Court, 1963)
M & R Contractors & Builders, Inc. v. Michael
138 A.2d 350 (Court of Appeals of Maryland, 1958)
Stark v. Shaw
317 P.2d 182 (California Court of Appeal, 1957)
Boomer v. Abbett
315 P.2d 924 (California Court of Appeal, 1957)
Bowman v. Santa Clara County
315 P.2d 67 (California Court of Appeal, 1957)
Gagne v. Bertran
275 P.2d 15 (California Supreme Court, 1954)
Morello v. Growers Grape Products Assn.
186 P.2d 463 (California Court of Appeal, 1947)
Alphonzo E. Bell Corp. v. Listle
169 P.2d 462 (California Court of Appeal, 1946)
Grupe v. Glick
160 P.2d 832 (California Supreme Court, 1945)
Rehart v. Klossner
119 P.2d 148 (California Court of Appeal, 1941)
Big Boy D. Corp., Ltd. v. Etheridge
111 P.2d 953 (California Court of Appeal, 1941)
Brunvold v. Johnson
97 P.2d 489 (California Court of Appeal, 1939)
Hartman Ranch Co. v. Associated Oil Co.
73 P.2d 1163 (California Supreme Court, 1937)
United Bank & Trust Co. v. Hunt
18 Cal. App. 2d 112 (California Court of Appeal, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
85 P. 929, 149 Cal. 60, 1906 Cal. LEXIS 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcconnell-v-corona-city-water-co-cal-1906.