Stark v. Shaw

317 P.2d 182, 155 Cal. App. 2d 171, 1957 Cal. App. LEXIS 1262
CourtCalifornia Court of Appeal
DecidedNovember 12, 1957
DocketCiv. 22456
StatusPublished
Cited by13 cases

This text of 317 P.2d 182 (Stark v. Shaw) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stark v. Shaw, 317 P.2d 182, 155 Cal. App. 2d 171, 1957 Cal. App. LEXIS 1262 (Cal. Ct. App. 1957).

Opinion

FOX, Acting P. J.

This is an action for damages for breach of contract. From a judgment in favor of plaintiffs, defendant Shaw Construction Company has appealed.

In 1952 the Shaw Construction Company began the development of certain tracts in a subdivision in the eastern portion of Los Angeles County known as La Mirada. The program contemplated building 10,000 homes over a four-year period. One of the first units developed by the company consisted of *175 312 homes. A contract for roofing these houses was let in June, 1953 to La Mirada Roofing Company, which was a family corporation organized in February, 1953 by Morgan S. Stark for this specific purpose. An appropriate license was granted the roofing company. Mr. Stark had been engaged in the roofing business for some 25 years and had a license therefor. He had been roofing houses for the Shaw Company for several years. More recently, he had been engaged in the business in partnership with his wife under the firm name of Morgan S. Stark Company. Neither the partnership nor Mrs. Stark had a roofing contractor’s license.

Early in March, 1954, before the roofing of the 312 homes had been fully completed, Mr. Shaw, president of defendant corporation, requested Stark to submit a bid for roofing 936 houses he planned to build immediately on four other tracts in La Mirada. Pursuant to this request, Stark, on March 12, submitted a bid which totaled approximately $355,000. It was accepted by Mr. Shaw on behalf of the corporation that same day. It was out of this contract 1 that this lawsuit arises. The contract did not specify a date on which defendant would start building the houses or on which the roofing would begin. *176 Shaw, however, represented that construction would begin in less than three weeks (approximately April 1st) and proceed at approximately 10 houses per day. It required about three weeks from the time a house was started until it was ready for roofing. At the time this contract was entered into Shaw advised Stark that the financing for his building venture had been arranged with a large and well-known financial institution operating in Southern California. At that time Tracts 18976 and 19041 had been graded both as to streets and as to lots. In Tract 15930 the streets and some of the lots were graded and temporary water was available. Water was also available in Tract 18976, on which were located more than half of the building sites here involved. No foundations, however, had been dug or poured.

Nothing having been done toward starting construction, Stark contacted Shaw during the last week in March and made specific inquiry as to a starting date. Shaw stated construction would begin in “approximately 15 days, not later than the 15th of April.” Early in April Shaw told Stark he had been delayed but he expected to start in two or three weeks. In the latter part of April Stark had another conversation with Shaw respecting a starting date. The latter stated he would be starting “very shortly.”

Early in May Stark and Shaw had a lengthy discussion concerning the entire situation. Stark told him that he was “getting pretty tired of this situation”; that he “had been living on promises since January of 1953, and something was going to have to be done about it”; that he “had been put to tremendous expenses—that it was on his [Shaw’s] say-so, that he said he was going to build the houses, and the work had not proceeded”; that he (Stark) was “in serious financial difficulty”; and he wanted to know what Shaw was going to do. Shaw then reiterated that construction would start soon, and he promised to have some money for Stark on May 17 for the latter to apply on the expenses which had been incurred. On that date no money was forthcoming and no construction had been started. Hence, on May 24, plaintiffs, as assignees of the roofing company, commenced this lawsuit on the theory that defendant’s continued failure to commence construction of the houses constituted a breach of contract.

Defendant’s first contention is that there is insufficient evidence to support the court’s finding that “a reasonable time for performance of the agreement had expired on May 17, 1954.” “If no time is specified for the performance of an act *177 required to be performed, a reasonable time is allowed.” (Civ. Code, § 1657.) Since the contract between the roofing company and defendant specified no time for commencing performance of the latter’s promises, a reasonable time is implied. In order for the roofing company to perform its part of the contract, it was necessary for defendant to construct the houses; the very nature of the contract gives rise to an implied promise on defendant’s part so to do. Defendant’s unexcused failure to commence construction within the required time would constitute a breach of contract, which excuses the other party and permits him to recover for any loss occasioned by the breach. (Sobelman v. Maier, 203 Cal. 1, 9 [262 P. 1087] ; Fountain v. Semi-Tropic Land & Water Co., 99 Cal. 677, 680-681 [34 P. 497] ; Eubanks v. Milton G. Cooper & Son, Inc., 68 Cal.App.2d 366, 372 [156 P.2d 775].)

The question of what constitutes a reasonable time is always a fact question. (Lyon v. Goss, 19 Cal.2d 659, 673 [123 P.2d 11] ; Leiter v. Handelsman, 125 Cal.App.2d 243, 251 [270 P.2d 563].) In determining what period of time would be reasonable, the situation of the parties, the nature of the transaction, and the facts of the particular case should all be considered. (Lyon v. Goss, supra, p. 673; Kersch v. Taber, 67 Cal.App.2d 499, 506 [154 P.2d 934].)

Shaw’s representation at the time the contract was entered into that construction would start on approximately April 1st; the statement that the financing for the project had been arranged; the fact that the streets had been graded, water provided, and the sites for more than half of the houses had been graded; the vastness of the entire project and the time schedule for its completion; the investment that was already necessarily involved; the desirability of putting the houses on the market so that they could be sold expeditiously at a profitable figure while there was a public demand for housing: all these circumstances reasonably support an inference that the parties contemplated that construction would start promptly. With this factual setting the arbiter of the facts could properly conclude that a reasonable time for starting construction expired on May 17 th which was more than two months after the contract was made. 2

*178

Free access — add to your briefcase to read the full text and ask questions with AI

Related

California Retail Portfolio Fund Gmbh & Co. Kg v. Hopkins Real Estate Group
193 Cal. App. 4th 849 (California Court of Appeal, 2011)
J. Iapaluccio, Inc. v. City of Torrington, No. 31 81 43 (Dec. 2, 1996)
1996 Conn. Super. Ct. 7469 (Connecticut Superior Court, 1996)
Atlas Assurance Co. v. McCombs Corp.
146 Cal. App. 3d 135 (California Court of Appeal, 1983)
Cohen v. Karubian
276 Cal. App. 2d 44 (California Court of Appeal, 1969)
Guinand v. Walton
450 P.2d 467 (Utah Supreme Court, 1969)
Sawday v. Vista Irrigation District
415 P.2d 816 (California Supreme Court, 1966)
Marshall & Co. v. Weisel
242 Cal. App. 2d 191 (California Court of Appeal, 1966)
Chapin v. Superior Court
234 Cal. App. 2d 571 (California Court of Appeal, 1965)
World Savings & Loan Ass'n v. Kurtz Co.
183 Cal. App. 2d 319 (California Court of Appeal, 1960)
De Flavio v. Estell
343 P.2d 150 (California Court of Appeal, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
317 P.2d 182, 155 Cal. App. 2d 171, 1957 Cal. App. LEXIS 1262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stark-v-shaw-calctapp-1957.