Big Boy D. Corp., Ltd. v. Etheridge

111 P.2d 953, 44 Cal. App. 2d 114, 1941 Cal. App. LEXIS 960
CourtCalifornia Court of Appeal
DecidedApril 9, 1941
DocketCiv. 12349
StatusPublished
Cited by9 cases

This text of 111 P.2d 953 (Big Boy D. Corp., Ltd. v. Etheridge) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Big Boy D. Corp., Ltd. v. Etheridge, 111 P.2d 953, 44 Cal. App. 2d 114, 1941 Cal. App. LEXIS 960 (Cal. Ct. App. 1941).

Opinion

DORAN, J.

This is an appeal by plaintiff, taken by means of a bill of exceptions, from separate judgments of nonsuit in favor of each of the defendants, rendered by the trial court sitting without a jury in an action brought to recover damages for the breach of an oil well drilling contract. The judgments were rendered following the sustaining of objections to the introduction of certain evidence offered by the plaintiff (appellant).

Appellant was the drilling contractor under the agreement in question. The contract called for the drilling of an oil well to a specified maximum depth for a specified total sum, payable partly in cash and partly in certificates of beneficial interest in a certain common law trust. Payments of cash were to be made in installments at specified intervals during the progress of the work and until the full sum of $120,000 in cash had been paid. The provision of the contract most pertinent to the instant action reads as follows: “It is expressly understood and agreed by and between the parties hereto, that in event of failure of Owner to make the cash payments and deliver the certificates of beneficial interest provided to be paid and delivered in Paragraph V of this contract, contractor may, at his option, suspend drilling operations until such time as the failure of owner is remedied, and such suspension of operations shall not be deemed to be a breach by contractor of this contract. It is further under *116 stood and agreed that if by reason of such default contractor shall suspend drilling operations, owner agrees to pay contractor upon the termination of such suspension period, the sum of $288.00 per day as liquidated damages for the period of such suspension. In the event that owner fails to remedy his default within a period of 90 days, then in that event, any time after such period of 90 days contractor may, at his option, and without further notice to owner, deem the same to be a permanent and definite default and breach of contract and treat the same in accordance therewith, without further or any notice whatsoever to said owner. It is further agreed that the contractor at all times shall be the sole owner of the said machinery and drilling equipment, and nothing herein shall be construed to be a transfer of any portion of the interest and ownership of said contractor in and to said equipment and machinery, and said machinery and equipment shall be subject to removal by said contractor upon completion of said well or before as hereinbefore provided.” Payments under the contract were not made and appellant availed itself of the above quoted terms and instituted the present action to recover damages sustained by reason of the alleged breach of the contract and for loss of profits as a result thereof.

At the trial appellant, in addition to the contract, set forth as an exhibit attached to the complaint, proposed to introduce evidence with reference to the knowledge by respondents of appellant’s financial condition, and with reference to an alleged agreement that the provision above quoted would constitute a condition precedent to further performance by the contractor, which evidence consisted of oral conversations and agreements by and between the appellant and respondents not reduced to writing. Objection to appellant’s offer of proof thereon was sustained, and an objection to appellant’s offer to prove all the allegations of its complaint was likewise sustained. Appellant thereupon rested and the court subsequentty granted respondents’ separate motions for nonsuit. Appellant here takes exception to the rulings of the trial court upon its offers of proof.

The questions here raised by appellant which require consideration are: (a) Were the payments under the contract conditions precedent to further performance on the part of the contractor; and (b) may the contractor sue upon the contract or is he confined to a suit in quantum meruit for the *117 reasonable value of the work actually done by him ? As may be seen hereinafter, the answer to the second question depends upon the answer to the first.

It is respondents’ contention that under a contract of the nature of the one in question a contractor is limited to a suit for the reasonable value of the work actually done. Respondents base their contention upon the series of cases concerned with a suit for damages for breach of the contract for the construction of the Western Pacific Railroad from San Jose to Sacramento, which eases may for convenience be denominated the Cox cases (Cox v. Western Pac. R. R. Co., 44 Cal. 18; 47 Cal. 87; Cox v. McLaughlin, 52 Cal. 590; 54 Cal. 605; 63 Cal. 196; 76 Cal. 60 [18 Pac. 100, 9 Am. St. Rep. 164]; 10 Pac. C. L. J. 263). It is true that these eases hold generally that mere failure to make installment payments under a construction contract does not prevent the contractor from continuing with the work and does not authorize him to abandon the contract and sue for all benefits he would have received upon full performance (Cox v. McLaughlin, 52 Cal. 590; 54 Cal. 605); but that he may recover in quantum meruit for the reasonable" value of the work actually done. (Cox v. McLaughlin, 76 Cal. 60, supra.) However, it should be pointed out that certain situations are excepted from the rule laid down by the Cox cases, namely, those in which the contractor is prevented by the breach from further performance, or where the condition breached is expressly made precedent to further performance. In Cox v. McLaughlin, 54 Cal. 605, it is stated at page 606: “Where an entire contract is terminated by the employer against the will of the contractor, the latter is not confined to the actual value of the work done, but may prosecute his action for the breach of the agreement, and may recover as damages the profits he would have made had he been allowed to complete the work. The contract is thus terminated where the employer prevents or prohibits the completion of the work—the contractor being ready and willing to complete the work.” (Italics included.) And in the same case, at page 609, it is said (quoting with approval from Palm et al. v. Ohio & Mississippi Railroad Co., 18 Ill. 217): " `A contract, no doubt, may be so drawn as to make the payment of a part of the consideration, by installments as the work progresses, or at stated times independently of the progress of the work, a condition precedent to the fur *118 ther prosecution of the work, and make its non-payment such a substantial violation of the contract as to authorize the other party to abandon the work and sue upon it, as for having been prevented from completing it by the act of the party who had thus failed to perform such condition precedent. But the law cannot infer such a consequence from the ordinary obligation to pay money at a particular time, or upon a completion of a specified part of the work. ’ ”

Respondents, of course, contend that the instant contract provides for no more than the ordinary obligation to pay money in installments at a particular time and that the rule of the Cox cases applies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Integrated, Inc. v. Alec Fergusson Electrical Contractor
250 Cal. App. 2d 287 (California Court of Appeal, 1967)
Kenworthy v. State of California
236 Cal. App. 2d 378 (California Court of Appeal, 1965)
Guerrieri v. Severini
330 P.2d 635 (California Supreme Court, 1958)
United Artists Corp. v. Strand Productions, Inc.
216 F.2d 305 (Ninth Circuit, 1954)
Abraham Lehr, Inc. v. Cortez
135 P.2d 684 (California Court of Appeal, 1943)
Burr v. Pacific Indemnity Co.
133 P.2d 24 (California Court of Appeal, 1942)
Paratore v. Scharetg
128 P.2d 560 (California Court of Appeal, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
111 P.2d 953, 44 Cal. App. 2d 114, 1941 Cal. App. LEXIS 960, Counsel Stack Legal Research, https://law.counselstack.com/opinion/big-boy-d-corp-ltd-v-etheridge-calctapp-1941.