Cox v. McLaughlin

54 Cal. 605
CourtCalifornia Supreme Court
DecidedJuly 1, 1880
DocketNo. 5,057
StatusPublished
Cited by32 cases

This text of 54 Cal. 605 (Cox v. McLaughlin) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cox v. McLaughlin, 54 Cal. 605 (Cal. 1880).

Opinion

By the Court, McKinstry, J.:

The judgment appealed from is against defendant McLaughlin alone. The contract on which the plaintiffs must rely—being that set forth in the answer of defendant McLaughlin—was held to he an “ entire contract ” in Cox v. W. P. R. R. Co. 44 Cal. 18. Assuming that the failure to pay, as alleged, constituted a breach of the contract, the plaintiffs could have treated the specific contract as rescinded, and have brought suit on the [606]*606implied promise of defendant to pay the value of the work actually done.

That the present is not an action on the implied promise is apparent, not only from the omission of any averment of the actual value of the work done, but from the whole frame of the complaint.

Where an entire contract is terminated by the employer against the will of the contractor, the latter is not confined to the actual value of the work done, but may prosecute his action for the breach of the agreement, and may recover as damages the profits he would have made had he been allowed to complete the work. The contract is thus terminated where the employer prevents or prohibits the completion of the 'work—the contractor being ready and willing to complete the work. Such actions have been often sustained by the courts. (Smith’s Leading Cases, 7th Am. ed. p. 53; Dillon v. Anderson, 43 N. Y. 237.) But in such cases he must declare specially, and set forth the readiness or tender, and refusal or prevention'.

The language of the complaint before us indicates an intention on the part of the pleader to conform to the precedents in actions of the character last mentioned; it contains a distinct allegation that the defendant prevented the complete performance.

Had the evidence sustained the averment of the complaint, (supposing the pleading in other respects sufficient) the plaintiffs should have recovered not only the amount due when the work ceased, according to the terms of the specific contract, but also such profits as they would have made upon the remainder of the work, had they been permitted to complete the line they had contracted to construct.

The Court below found that the contract alleged by plaintiffs was not the contract between the parties in substance or effect; but we need not make the decision here depend upon that finding.

The District Court did not find that defendant had prevented the plaintiff from completing the work. The finding on that subject is as follows:

“ The defendant, Charles McLaughlin, retarded prosecution of the work under the contract very much, directing suspension [607]*607of the full force of men that could and would have been employed in prosecution thereof; and said McLaughlin, well knowing that the plaintiffs had to rely upon the moneys they received from him to pay for the materials furnished, and labor and services rendered in performing said contract, and that by refusing to let plaintiffs have their money as it became due, they could not carry on their work, he utterly refused to pay them their money as it became due, for the purpose and with the intent to prevent them from completing their work under said contract, and he did thus prevent them from completing the same.”

By the contract between plaintiffs and defendant McLaughlin, it was provided: “And it is further understood and agreed as aforesaid, that the said party of the second part shall have and enjoy the right to cause the said parties of the first part to increase or diminish the force of laborers, or other means necessary and proper to carry on the work, or to suspend the work entirely, on giving notice to that effect to said parties of the first part, as follows: to increase or diminish such force at least fifteen days, and to suspend the work entirely on thirty days’ notice •—but all delays of time caused by such notices to suspend work, or to diminish the force as aforesaid, shall be allowed to said parties of the first part, for the completion of said work, beyond the time and times herein stipulated for the completion thereof ; and that said parties of the first part shall do and perform such work, or portions thereof, at any and all times, and at such places on the said first section of twenty miles, within the time herein prescribed for the completion thereof, as the said party of the second part shall indicate and require ; or any other portion of said work—giving reasonable notice thereof.”

It appears that by the contract, defendant McLaughlin was authorized to direct “ suspension of the full force of men.” His direction that the force be reduced was, therefore, not a prevention.

The inquiry which remains is: Was defendant’s neglect to pay money, as it became due, such prevention ?

The contract contains no express stipulation which can be so construed as that the payment of any sum, agreed to be paid during the progress of the work, can be held to be a condition [608]*608precedent to the completion of the work by the plaintiffs. In Palm et al. v. The Ohio and Mississippi Railroad Company, 18 Ill. R., the opinion of the Supreme Court of Illinois was delivered by Justice Caton, who said, (p. 219): “ I have examined all the authorities referred to by counsel, and have made diligent search myself, but have found no case where the plaintiff has been allowed to recover the losses sustained by not being permitted to complete the contract, unless he has been prevented from going on with his work by the positive affirmative act of the other party, or where the other party has neglected to do some act, without which the plaintiff could not, in the nature of things, go on with his contract: as where he refused to furnish a place whereon to erect a building, or to furnish material which, by the contract, was to be put in the works, and which was to be provided by him. In such a case, the act to be done is clearly a condition precedent and indispensable to enable the other party.to go on. Where the act, which the defendant was bound to do, is, by the terms of the contract, made a condition precedent to the performance by the plaintiff, either in the nature of things, or evidently in the contemplation of the parties at the time the contract was entered into, then the failure to do the act does of itself prevent the other party from performing, as much as if ho were forbidden to perform it. But nowhere have I found a case, where, the failure to pay the consideration for the work as it progresses according to the terms of the agreement, has been held such an act of omission on the part of the defendant as to prevent the other party from completing the contract. It is undoubtedly true that the failure to make such payments may, in point of fact, leave the other party without the means or,credit to go on and complete the job; but such is not the necessary result of such a failure, and we cannot safely adopt it as a conclusion of law, that it does prevent the party from going on. The prompt payment of such installments might be indispensable to enable a party of some means and credit to go on, while another of larger means and more extended credit might be able to complete the contract, without embarrassment or sacrifice. Can we inquire into the actual fact, and see whether the non-payment did really stop the plaint[609]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Integrated, Inc. v. Alec Fergusson Electrical Contractor
250 Cal. App. 2d 287 (California Court of Appeal, 1967)
Kenworthy v. State of California
236 Cal. App. 2d 378 (California Court of Appeal, 1965)
Smoll v. Webb
130 P.2d 773 (California Court of Appeal, 1942)
Big Boy D. Corp., Ltd. v. Etheridge
111 P.2d 953 (California Court of Appeal, 1941)
Woodruff v. Adams
25 P.2d 529 (California Court of Appeal, 1933)
Barris v. Atlas Rock Co.
5 P.2d 670 (California Court of Appeal, 1931)
Monson v. Fischer
5 P.2d 628 (California Court of Appeal, 1931)
Crawford v. Pioneer Box & Lumber Co.
288 P. 694 (California Court of Appeal, 1930)
Dyer Bros. G.W.I. Wks. v. Central I. Wks.
237 P. 386 (California Court of Appeal, 1925)
Dyer Bros. Golden West Iron Works v. Central Iron Works
72 Cal. App. 202 (California Court of Appeal, 1925)
Laiblin v. San Joaquin Agricultural Corp.
213 P. 529 (California Court of Appeal, 1923)
MacRae v. Heath
212 P. 228 (California Court of Appeal, 1922)
McCready v. Bullis
210 P. 638 (California Court of Appeal, 1922)
United Canneries Co. v. Seelye
292 P. 341 (California Court of Appeal, 1920)
Ackerman v. Santa Rosa-Vallejo Tanning Co.
257 F. 369 (Ninth Circuit, 1919)
Robinson v. Rispin
165 P.2d 979 (California Court of Appeal, 1917)
Leutheuser v. Silent
163 P. 225 (California Court of Appeal, 1916)
Greenlee County v. Cotey
155 P. 302 (Arizona Supreme Court, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
54 Cal. 605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cox-v-mclaughlin-cal-1880.