1. The Court erred in excluding the contract as evidence of the value of the work. It was competent to show the reasonable value.
2. The complaint counts upon a
special contract in writing
not performed by the plaintiffs, but which they allege they were prevented from performing by the defendants, and they seek to recover upon the prices set out in the first contract, without reference to the second. This they cannot do. (
Cutter
v.
Powell,
2 Smith’s S. C. 506;
Ford
v.
Smith,
25 Ga. 679.)
3. Prevention here could only be by an affirmative act; mere failure to pay did not constitute prevention.
(Palm
v.
The Ohio & Miss. R. R. Co.
18 Ill. 219;
County of Christram
v.
Overholt et al.
18 Ill. 227.) These cases cover this case exactly. In the first the plaintiff attempted to recover upon a contract unperformed. There, as here, the work was to be paid for in installments, and the defendant neglected to pay for an engine when it was delivered. The next case is even stronger in our favor; for the defendants not only failed, but also refused to pay.
To the same effect is
Wright
v.
Haskell,
45 Me. 492, where it is held that a refusal on the part of the defendant to pay does not constitute such a breach as authorizes the plaintiff to rescind. It must be an active prevention, not a passive one. In
Withers
v.
Reynolds,
2 Barn. & Adol. 882, Patterson, J., said that had the defaulting party merely refused to pay for a load of hay, that might not have excused the other party from
delivering more straw, but he expressly refused to pay as delivered. The Court thus draws a distinction between a repudiation of a contract and neglect or inability at the time to comply with it. (See, also,
Franklin
v.
Millen,
4 Ad. & E. 599;
Rankin
v. Darnell, 11 B. Mon. 31.)
John B.
Felton,
McAllisters & Bergin, Mosés Q.
Cobb, and
J. P. Doge,
for Respondents.
1. The exclusion of the contract was not error. It was not set out in the complaint; its supposed legal effect was alleged. There was no pretense of any variance, much less that the parties were misled to their prejudice. The evidence was fully gone into upon all the issues.
2. In the case at bar, whilst the plaintiffs were diligently engaged upon performance of the contract, the defendant not only refused to pay, but charged that the contract was a fraud on him, which he repudiated, and has ever since repudiated as such. Was not this prevention ?
We think it was, and in support of that proposition we will now call the attention of the Court to the following authorities directly on the point:
In the
Canal Company
v. Gordon, 6 Wall. 561, the work was to be paid for monthly as the work progressed, and if this money was not paid when due, it was
to bear
interest, thus showing
intended credit.
Under the contract, Gordon & Kenyon worked until June 7th, 18§8, at which time they were entitled to about $20,000 due for work done in the preceding month of May. The money not having been paid on that day, they notified the company that, owing to such non-payment, the contract was annulled and at an end. Subsequently suit was brought to enforce payment, and to have a lien declared on the work for the amount of work actually done. A decree was rendered in favor of the plaintiffs, and upon appeal, the Supreme Court, speaking upon this point, say:
“ This part of the case has been argued very fully by counsel
on both sides. We have looked carefully into the evidence. The result is, that we are entirely satisfied with the report, and in this respect with the decree. We think the fault of the rupture lies wholly with the company. Gordon & Kenyon adhered to the contract, and pursued the work longer than they were bound to do. When they retired they were fully justified, and had a clear equity to be paid for the work they had performed.”
In
Phillips, etc., Const. Co.
v.
Seymour,
91 U. S. Rep. 1 Otto, 647) which was the case of a contract
to
construct a railroad, which was to be paid for in monthly installments as the work progressed, upon estimates furnished, as in the case at bar, work was done under the contract, when for non-payment for work done the contractors stopped work, and brought suit to recover for what they had done. Upon this point the Court say:
“Plaintiffs here had already performed, and the defendant failed to do its corresponding duty under the contract; and defendant having defaulted on a payment due, plaintiffs are not required to go on at the hazard of a further loss.”
See, also,
Freeth
v.
Burr,
Law R. 9 Com. P. 208;
Cort
v.
Ambergate,
6 Eng. L. & Eq. 230;
Bernardy
v.
Haring,
8 Ex. 822;
Planche
v.
Colburn,
8 Bing. 14;
Thompson
v.
Laing,
8 Bosw. 485;
Lamoroux
v.
Rolfe,
36 N. H. 36;
Shaw
v.
Grandy,
5 Jones, (N. C.) 57;
Grandy
v.
Small,
Ibid. 51;
Hochester
v.
De Latour,
20 Eng. L. 160.
By the Court :
If, after this cause shall have been remitted to the District Court, the plaintiff shall ask and the Court shall permit an amendment of the complaint by the insertion of an averment of the actual value of the work done, it will remain for plaintiffs to
prove
the actual value.
Where a variance has occurred in the performance of a specific contract, under such circumstances as still enable a plaintiff to maintain an action on the implied promise to pay the reasonable value of the work actually done, and the contract,
so far as it has been performed
in accordance with the specifications
therein contained, the contract may ordinarily be introduced as evidence of value.
But whether, when the contract provides for an arbitrary and merely conventional standard of determining what work has been done, an appeal to which does not show what work has in fact been done, the contract is admissible as evidence of the actual value, is not a question an answer to which is necessary to the determination of this appeal.
When the cause was here on the first appeal, this Court held the contract between McLaughlin and Cox, Myers & Co. to be an
entire
contract, and said: “ It is not alleged in the complaint that the work contracted to be performed has been completed, nor that its performance has been
prevented
by McLaughlin, or that the contract has been rescinded.” (44 Cal. 27.)
Free access — add to your briefcase to read the full text and ask questions with AI
1. The Court erred in excluding the contract as evidence of the value of the work. It was competent to show the reasonable value.
2. The complaint counts upon a
special contract in writing
not performed by the plaintiffs, but which they allege they were prevented from performing by the defendants, and they seek to recover upon the prices set out in the first contract, without reference to the second. This they cannot do. (
Cutter
v.
Powell,
2 Smith’s S. C. 506;
Ford
v.
Smith,
25 Ga. 679.)
3. Prevention here could only be by an affirmative act; mere failure to pay did not constitute prevention.
(Palm
v.
The Ohio & Miss. R. R. Co.
18 Ill. 219;
County of Christram
v.
Overholt et al.
18 Ill. 227.) These cases cover this case exactly. In the first the plaintiff attempted to recover upon a contract unperformed. There, as here, the work was to be paid for in installments, and the defendant neglected to pay for an engine when it was delivered. The next case is even stronger in our favor; for the defendants not only failed, but also refused to pay.
To the same effect is
Wright
v.
Haskell,
45 Me. 492, where it is held that a refusal on the part of the defendant to pay does not constitute such a breach as authorizes the plaintiff to rescind. It must be an active prevention, not a passive one. In
Withers
v.
Reynolds,
2 Barn. & Adol. 882, Patterson, J., said that had the defaulting party merely refused to pay for a load of hay, that might not have excused the other party from
delivering more straw, but he expressly refused to pay as delivered. The Court thus draws a distinction between a repudiation of a contract and neglect or inability at the time to comply with it. (See, also,
Franklin
v.
Millen,
4 Ad. & E. 599;
Rankin
v. Darnell, 11 B. Mon. 31.)
John B.
Felton,
McAllisters & Bergin, Mosés Q.
Cobb, and
J. P. Doge,
for Respondents.
1. The exclusion of the contract was not error. It was not set out in the complaint; its supposed legal effect was alleged. There was no pretense of any variance, much less that the parties were misled to their prejudice. The evidence was fully gone into upon all the issues.
2. In the case at bar, whilst the plaintiffs were diligently engaged upon performance of the contract, the defendant not only refused to pay, but charged that the contract was a fraud on him, which he repudiated, and has ever since repudiated as such. Was not this prevention ?
We think it was, and in support of that proposition we will now call the attention of the Court to the following authorities directly on the point:
In the
Canal Company
v. Gordon, 6 Wall. 561, the work was to be paid for monthly as the work progressed, and if this money was not paid when due, it was
to bear
interest, thus showing
intended credit.
Under the contract, Gordon & Kenyon worked until June 7th, 18§8, at which time they were entitled to about $20,000 due for work done in the preceding month of May. The money not having been paid on that day, they notified the company that, owing to such non-payment, the contract was annulled and at an end. Subsequently suit was brought to enforce payment, and to have a lien declared on the work for the amount of work actually done. A decree was rendered in favor of the plaintiffs, and upon appeal, the Supreme Court, speaking upon this point, say:
“ This part of the case has been argued very fully by counsel
on both sides. We have looked carefully into the evidence. The result is, that we are entirely satisfied with the report, and in this respect with the decree. We think the fault of the rupture lies wholly with the company. Gordon & Kenyon adhered to the contract, and pursued the work longer than they were bound to do. When they retired they were fully justified, and had a clear equity to be paid for the work they had performed.”
In
Phillips, etc., Const. Co.
v.
Seymour,
91 U. S. Rep. 1 Otto, 647) which was the case of a contract
to
construct a railroad, which was to be paid for in monthly installments as the work progressed, upon estimates furnished, as in the case at bar, work was done under the contract, when for non-payment for work done the contractors stopped work, and brought suit to recover for what they had done. Upon this point the Court say:
“Plaintiffs here had already performed, and the defendant failed to do its corresponding duty under the contract; and defendant having defaulted on a payment due, plaintiffs are not required to go on at the hazard of a further loss.”
See, also,
Freeth
v.
Burr,
Law R. 9 Com. P. 208;
Cort
v.
Ambergate,
6 Eng. L. & Eq. 230;
Bernardy
v.
Haring,
8 Ex. 822;
Planche
v.
Colburn,
8 Bing. 14;
Thompson
v.
Laing,
8 Bosw. 485;
Lamoroux
v.
Rolfe,
36 N. H. 36;
Shaw
v.
Grandy,
5 Jones, (N. C.) 57;
Grandy
v.
Small,
Ibid. 51;
Hochester
v.
De Latour,
20 Eng. L. 160.
By the Court :
If, after this cause shall have been remitted to the District Court, the plaintiff shall ask and the Court shall permit an amendment of the complaint by the insertion of an averment of the actual value of the work done, it will remain for plaintiffs to
prove
the actual value.
Where a variance has occurred in the performance of a specific contract, under such circumstances as still enable a plaintiff to maintain an action on the implied promise to pay the reasonable value of the work actually done, and the contract,
so far as it has been performed
in accordance with the specifications
therein contained, the contract may ordinarily be introduced as evidence of value.
But whether, when the contract provides for an arbitrary and merely conventional standard of determining what work has been done, an appeal to which does not show what work has in fact been done, the contract is admissible as evidence of the actual value, is not a question an answer to which is necessary to the determination of this appeal.
When the cause was here on the first appeal, this Court held the contract between McLaughlin and Cox, Myers & Co. to be an
entire
contract, and said: “ It is not alleged in the complaint that the work contracted to be performed has been completed, nor that its performance has been
prevented
by McLaughlin, or that the contract has been rescinded.” (44 Cal. 27.)
After the cause was returned to the District Court, the plaintiffs, adopting the suggestion of this Court, amended their complaint by inserting the averment that defendants had “ prevented ” the completion of the work. There can be no doubt, as we intimated at the former hearing of this appeal, that the complaint, as amended, is an attempt to declare specially upon the contract part—performance and prevention.
The fact that it does not allege damages by reason of loss and profits on the whole job does not change the character of the pleading, nor of the proofs necessary to sustain it. Unless prevention was proved and found, the plaintiffs were not entitled to recover anything on the.
contract.
The
ninth
is simply a finding that defendant did not pay plaintiffs their money as it became due. We have nothing to add to what we have' already said in respect to this finding, except that the language that the defendant neglected and refused to pay, “ well knowing that plaintiffs had to rely on the moneys received from him,” adds nothing to its effect. Even if, under any circumstances, the failure to pay would authorize the plaintiffs to cease work and bring suit on the contract, (the parties having omitted to insert a provision in the written contract that such failure should constitute prevention) there is no finding
that defendant knew
at the time the contract was entered
into, that plaintiffs relied entirely on his payments to them, or that such reliance was an inducement to the contract on their part. It is manifest that the
motive
which induced him to refuse or neglect payment cannot affect the rights of the parties under the contract.
There is no finding, in general terms, that defendant “ prevented ” plaintiffs from performing their contract fully. Nor is there any finding, or evidence tending to prove, that he failed entirely, or prevented, by notifying plaintiffs that he would pay none of the installments as they should become due.
We are, therefore, brought again to the question—in cases like the present, will the
mere
failure or refusal to pay an installment as it becomes due, authorize the other party to abandon the work, and yet to bring suit for recovery of all the benefit he would have received had he fully performed—that is to say, the contract price up to the time the work ceased, and such profits as he would have made had he performed his contract in all respects ?
An examination of the cases cited ■ by plaintiffs’ counsel has not satisfied us that such mere failure to pay has ever been held to be prevention.
In
Withers
v. Reynolds, 2 Barn. & Ad. 882, Patterson, J., said: “ If the plaintiff had merely failed to pay for any particular load, that of itself might not have been an excuse to defendant for delivering no more straw; but the plaintiff here expressly refused to pay for the loads as delivered.” The case was' commented on in
Franklin
v. Miller, 4 Ad. & Ell. 599. Coleridge, J., there said: “ In
Withers
v. Reynolds, each load of straw was to be paid on delivery.”
When the plaintiff said that he would not pay for his loads on delivery, that was a
total
failure, and defendant was no longer bound to deliver.” (See note to
Cutter
v. Powell, 2 Smith’s Leading Cases.)
In
Masterton
v.
Mayor of Brooklyn,
(7 Hill, 64, 65) the plaintiff having continued to furnish marble, as required by his contract, up to a certain date, the defendants suspended oper
ations upon the building,
and refused to receive any more materials of the plaintiffs, though the latter were ready and offered to perform.
Canal Company
v.
Gordon,
(6 Wall. 561) construes a statute of California in respect to mechanics’ liens, and holds that where a contract is to complete a structure, with agreements for installment payments, a failure to make a payment at the time specified justifies an abandonment of the work, and entitles the contractor to receive
a reasonable compensation
for the work actually done.
In
Hale
v.
Trout,
(35 Cal. 242,) there was prevention, or total refusal. Sawyer, J., said: “ There was not merely a neglect of payment, but plaintiffs were notified by the defendants that
they should treat the contract as at an end, and would receive no more lumber under it.”
Cort
v.
Ambergate Railway Company.
This case is reported in Langdell’s Select Cases on Contracts, 970. Lord Campbell said: “On the whole, we think we are justified on principle, and without trenching on any former decision, in holding that when there is an executory contract for the manufacturing and supply of goods from time to time, to be paid for after delivery, if the purchaser, having accepted and paid for a portion of the goods,
gives notice to the vendor not to manufacture any more, as he has no occasion for them, and will not accept or pay for them,
the vendor having been
desirous and able
to complete the contract, he may, without manufacturing and tendering the rest of the goods, maintain an action against the purchaser for breach of the contract.”
Jones
v.
Barkley,
(2 Douglass, 684) and
Ripley
v.
McClure,
(4 Exch. 344) simply hold that where an act is covenanted to be performed by each of two parties at the same time, he who is ready and willing to perform may be
discharged
of performance by the other, and, if so discharged, may maintain his action on the contract.
None of the cases above referred to declare the proposition that failure to pay an installment on a contract of the kind here sued on will authorize an action like the present.
Por the reasons mentioned in the former and present opinion, the judgment and order denying new trial are reversed, and the cause remanded for a new trial.
Wallace, C. J., and Crockett, J., did not participate in this decision.