Barrett v. Austin

31 P. 3, 3 Cal. Unrep. 551, 1892 Cal. LEXIS 1048
CourtCalifornia Supreme Court
DecidedSeptember 1, 1892
DocketNo. 14,753
StatusPublished

This text of 31 P. 3 (Barrett v. Austin) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barrett v. Austin, 31 P. 3, 3 Cal. Unrep. 551, 1892 Cal. LEXIS 1048 (Cal. 1892).

Opinion

BELCHER, C.

This is an action to recover damages for breach of contract. It is alleged in the complaint that on the fourth day of February, 1890, plaintiff and defendant entered into a written contract, a copy of which is set out, for the boring of a well on plaintiff’s land; that plaintiff complied with all the conditions of the contract to be performed on his part, and in pursuance thereof furnished the materials and supplies provided for of the value of $1,000; and the defendant failed and refused to comply with any of the conditions to be performed on his part, and that, by reason of such failure and refusal, plaintiff had been damaged in the sum of $1,000, for which he asked judgment. By the contract the plaintiff bound himself “to furnish all the tubing and casing at his own expense; also all necessary fuel for the use of the engine, and all the casing clay needed in the boring of a certain well, now commenced and sunk about one hundred and forty feet, on the following described land,” etc.; “also to board and furnish house room for the men— three in number—employed in boring said well”;'“also to pay to the party of the second part (defendant) seventy cents per foot in depth, commencing from the top of the ground, for each and every foot in depth of said well, and to make said payment in full, as aforesaid, at the completion and cessation of the boring of said well.” And the defendant bound himself “-to continue the boring of said well, commencing on the eleventh day of February instant, barring bad weather or other unavoidable hindrances, until the depth of one thousand feet shall have been secured,” provided that if a satisfactory flow of water should be secured, or impenetrable rock be encountered, before the depth of one thousand feet should be reached, then the boring was to cease, and the defendant was to be paid for the work done, as before provided. By his answer, the defendant admitted the execution of the contract, but denied that plaintiff had complied with all the [553]*553conditions thereof as alleged; and also denied that he had sustained damages in the sum of $1,000, or in any sum, by reason of any failure, neglect, or refusal on the part of defendant to perform the conditions of the contract to be by him performed; and alleged that plaintiff was the party in default, and by his own acts had prevented the completion of the work. Defendant also filed a cross-complaint, in which he set up the contract, and alleged that under and in pursuance of its terms he commenced boring the well on the eleventh day of February, 1890; that he had at the place of performance all necessary machinery and assistance for the full execution and completion thereof; that he steadily and industriously continued the work until the ninth day of April, 1890, when the plaintiff failed and refused to furnish any more fuel for the engine or board for the men; and that by reason of such failure and refusal he was then, and ever since had been, prevented from proceeding and fully completing the work required of him by the terms of the contract, although he was, and at all times since had been, ready, willing and able to perform all the conditions required to be kept and performed by him; that, in accordance with the terms of the contract, he bored the well to a depth of five hundred and sixty-three feet, and at the request of plaintiff furnished and used therein thirty-four feet of casing of the value of $15.30, and loaned to the plaintiff $2.50; that there was due to defendant from plaintiff, for the boring done, the easing furnished, and the money loaned, the sum of $411.90, for which he prayed judgment. At the trial it was proved, without contradiction, that the defendant commenced boring the well on the 11th of February, and continued the work a little more than a month, when his boring pipe and auger broke near the lower end thereof. He then tried to remove the broken pieces, and to that end worked diligently until the 9th of April. Up to that time the plaintiff furnished fuel for the engine and board for the men, but he then refused to furnish them any longer. The plaintiff testified: “The boring was stopped by reason of his boring pipe breaking off and leaving the auger at the bottom of the well. Defendant worked about two or three weeks trying to get the auger out, .... but he never succeeded in getting it out, and finally I quit, because I never agreed to dig his tools out, if [554]*554he got them fast. I quit furnishing him provisions after he got the auger stuck in the well, I think about two or three weeks.....I saw no way to get the auger and boring pipe out of the well. Elr. Austin says he can get it out. He always contended that he would get it out. Said he could bore the well.....I didn’t propose to keep furnishing him with fuel and provisions to dig out his tools. I didn’t consider that I had agreed to do that. After he got them down there he could not get them out, and I quit. He told me that he could get the tools out and complete the well. ’ ’

When the plaintiff refused to furnish any more fuel or provisions, defendant notified him that, unless they were furnished, he would be compelled to stop all further work. He testified: “I remained there and worked all the time steadily at the work until the time he quit furnishing me and refused to furnish me the supplies that is required of him by the contract. I was compelled to quit for want of these supplies.” When the work was stopped defendant had bored the well to a depth of five hundred and sixty-three feet, and had used four hundred and thirty-eight feet of the casing furnished by plaintiff, the cost price of which was seventy-five cents a foot. The court found that the plaintiff had complied with all the conditions of the contract to be performed on his part, and that he caused to be delivered at the proper place casing of the value of $400, and furnished board and lodging to the defendant of the value of $30, and wood of the value of $150; that defendant failed, neglected, and refused to comply with the conditions of the contract to be performed on his part, and abandoned the contract before the commencement of the action; and, as a conclusion of law, that the plaintiff was entitled to judgment against the defendant for the sum of $580, damages for breach of the contract and costs. Judgment was accordingly so entered, from which, and from an order denying a new trial, defendant appeals.

1. It is apparent that the judgment as entered was erroneous. It allowed the plaintiff $400 for the casing delivered, when, at most, he was entitled only to recover for so much as was used, the cost of which was $328.50. Besides, the easing is still in his land, and belongs to him, and it may perhaps be taken out, and then have some value over the cost of .its recovery. The judgment also ignores the defendant’s [555]*555claim for the casing furnished and the money paid out by him.

2. If the judgment might be modified so as to correct the errors above noted, still we are unable to see how, under the facts shown, the plaintiff was entitled to any relief. By the contract he obligated himself to furnish the casing, fuel, and board “at his own expense,” and the defendant obligated himself to commence and continue the boring, “barring bad weather or other unavoidable hindrances.” There was no provision that the plaintiff should be released from furnishing the supplies during the continuance of bad weather or other hindrances, and that he did not understand that he was so released is shown by the fact that he continued to furnish them for about three weeks after the auger was broken.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cox v. McLaughlin
52 Cal. 590 (California Supreme Court, 1878)
Cox v. McLaughlin
54 Cal. 605 (California Supreme Court, 1880)

Cite This Page — Counsel Stack

Bluebook (online)
31 P. 3, 3 Cal. Unrep. 551, 1892 Cal. LEXIS 1048, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barrett-v-austin-cal-1892.