Carlson v. Sheehan

109 P. 29, 157 Cal. 692, 1910 Cal. LEXIS 314
CourtCalifornia Supreme Court
DecidedMay 11, 1910
DocketS.F. No. 5124.
StatusPublished
Cited by21 cases

This text of 109 P. 29 (Carlson v. Sheehan) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlson v. Sheehan, 109 P. 29, 157 Cal. 692, 1910 Cal. LEXIS 314 (Cal. 1910).

Opinion

SHAW, J.

Plaintiff brought this action to recover the ■sum of $1715.00, alleged to be the balance due and unpaid for work done and materials furnished by plaintiff for defendant in constructing a building at defendant’s special instance and request. After the plaintiff had introduced his evidence upon the trial the court, on motion of the defendant, ordered a nonsuit. The plaintiff appeals from the judgment thereupon rendéred. .

The plaintiff and defendant entered into a contract whereby the plaintiff agreed to erect a building upon a lot belonging to the defendant for the sum of $3680. The plaintiff completed the building in part only and the defendant paid him twenty-one hundred dollars upon the contract. The remainder was to be paid on and after completion. The cost of finishing the uncompleted part of the building would have been about five hundred dollars. The claim of the plaintiff is that he was prevented or excused from completing the building according to the agreement by the conduct of the defendant. The object of the suit is to recover the difference between the value of the work done at the contract rate and the amount paid by the defendant.

*695 We do not think there is any merit in the contention of the respondent that a recovery cannot be had upon the common •count for the value of the work and material, and that the plaintiff should have averred the special contract, the sum agreed to be paid, the performance by himself, and non-payment by defendant. Such a rule may apply where a contract has been -performed by the plaintiff, but where complete performance has been prevented by the fault of the defendant; the plaintiff may sue for the value of that which he has done under it.

The lot on which the building was erected was twenty-five feet in width fronting on Market Street and one hundred and' twenty-five feet in depth. The building was a two-story frame structure covering the entire width of the lot and running back seventy feet. The defendant did not own the adjoining lot on either side. At the time the work was begun on the contract the lot had been graded down lower than the natural surface of the adjoining lots, leaving high vertical banks of earth on each side. These banks were unprotected by retaining walls or otherwise, and were liable to slide down upon the lot and against any building erected thereon, in case of heavy rains. The contract was made on September 2, 1906, and plaintiff began the work about the first of October. At the time of making the contract the defendant was grading the lot to prepare it for the building. Plaintiff saw the condition •of the banks on each side and knew the character of the soil. He did not believe the banks would stand without support, and there was some negotiation between him and defendant about putting in a concrete retaining wall four feet high to protect them from caving or sliding in upon the building, but there was no agreement regarding it. It was agreed that plaintiff should put in a wooden bulkhead in the rear five feet in height. The defendant told plaintiff that he had contracted with the graders to slope off the banks on each side, but that the contract was not in writing and they had refused to do it. Counsel for plaintiff earnestly insist that this was said at the time of executing the contract and that it constituted an inducement or consideration therefor from which an agreement by the defendant to slope off the banks would be implied. Giving to the evidence the full force which is to be attributed to it on a motion for nonsuit, we cannot so construe it. The *696 conversation referred to, in which this was said, occurred after the contract was signed and before the work was begun. The statement itself indicates that it was made after the lot was-graded and the context confirms this conclusion. There is nothing to show that Carlson signed the contract in reliance upon, or in consideration of, any agreement of Sheehan to-slope off the banks.

The work was begun by Carlson with full knowledge of the-conditions and without any protest or objection by him on account of any danger of a landslide from the adjoining banks. When the building was nearly finished there were heavy rains-which caused the said banks to slide in on the building, crushing in the sides thereof and damaging it to such an extent that it would require an expense of four hundred dollars to restore-it to its former condition. The defendant thereupon undertook to clear away the earth so that plaintiff could complete-the building and directed the plaintiff to stop further work until the earth was removed. This occupied several months. When it was done the defendant requested that plaintiff proceed with the work to completion. Plaintiff demanded that defendant pay the expense necessary to restore the building to-the condition it was in before the slide occurred. The defendant refused to -do this and thereupon the plaintiff refused to complete the building. The decision of the case depends on the question whether or not the plaintiff was justified, in his refusal to go on with the work, under the facts stated.

' Where a person agrees to do a thing for another for a-, specified sum of money to be paid on full performance, he is not entitled to any part of the sum until he has himself done-the thing he agreed to do, unless full performance has been excused, prevented, or delayed by the act of the other party, or by operation of law, or by the act of God or the public enemy, as specified in section 1511 of the Civil Code. If performance-is prevented by the party who is to make such payment, the-person doing the things is entitled to payment as for full performance. (Civ. Code, sec. 1512.) And if one party breaks an intermediate covenant of an executory agreement, the other party may treat the entire contract as rescinded and recover in quantum meruit for the value of the work he has done under it. (Cox v. McLaughlin, 76 Cal. 60, [9 Am. St. Rep. 164, 18 Pac. 100].)

*697 There was nothing done by Sheehan in the present case which had the effect of preventing Carlson from completing the building, or which justified a rescission by him. At the time the contract was signed the grading was in progress. There is no evidence that Sheehan then agreed that he would have the banks of the adjoining lots, which he did not own, sloped off so as to prevent the earth from falling on Sis own lot, or from sliding against the building to be erected thereon. He would have no right to do that; and his only lawful means of protecting his lot, without the consent of the adjoining owners, was to erect a retaining wall or bulkhead upon his own side of the boundary line. Carlson saw the situation in which the lot would be left when the grading was done, and he knew the character of the soil. With this knowledge he executed the contract without exacting any stipulation for his protection from the consequences of any caving of the banks which might occur during the erection of the building. Before he began the work he saw that the banks were vertical and Sheehan explained the reason, but did not agree to do anything to avoid or prevent the danger. Carlson must be presumed to have undertaken the performance of the contract at his own risk of interference by landslides from the adjoining lots.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schmeltzer v. Gregory
266 Cal. App. 2d 420 (California Court of Appeal, 1968)
Kennedy v. Reece
225 Cal. App. 2d 717 (California Court of Appeal, 1964)
United States ex rel. T. M. Page Corp. v. Hensler
125 F. Supp. 887 (S.D. California, 1954)
Magee v. Breckenridge
244 P.2d 103 (California Court of Appeal, 1952)
McCulloch v. Liguori
199 P.2d 25 (California Court of Appeal, 1948)
Kresse v. Ryerson
169 P.2d 850 (Arizona Supreme Court, 1946)
Big Boy D. Corp., Ltd. v. Etheridge
111 P.2d 953 (California Court of Appeal, 1941)
Orr v. Forde
282 P. 429 (California Court of Appeal, 1929)
Sun Oil Co. of California v. Union Drilling & Petroleum Co.
280 P. 535 (California Supreme Court, 1929)
Golden State Orchards v. Harter
269 P. 735 (California Court of Appeal, 1928)
Snow Mountain Water & Power Co. v. Kraner
216 P. 589 (California Supreme Court, 1923)
White v. Mitchell
213 P. 10 (Washington Supreme Court, 1923)
Gray v. Bekins
199 P. 767 (California Supreme Court, 1921)
Thomas Haverty Co. v. Jones
197 P. 105 (California Supreme Court, 1921)
Baranov v. Scudder
170 P. 1122 (California Supreme Court, 1918)
Suhr v. Metcalfe
164 P.2d 407 (California Court of Appeal, 1917)
Haub v. Coustette
160 P. 836 (California Court of Appeal, 1916)
Lapp-Gifford Co. v. Muscoy Water Co.
134 P. 989 (California Supreme Court, 1913)
American-Hawaiian Engineering & Construction Co. v. Butler
133 P. 280 (California Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
109 P. 29, 157 Cal. 692, 1910 Cal. LEXIS 314, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlson-v-sheehan-cal-1910.