McCulloch v. Liguori

199 P.2d 25, 88 Cal. App. 2d 366, 1948 Cal. App. LEXIS 1476
CourtCalifornia Court of Appeal
DecidedNovember 8, 1948
DocketCiv. No. 13644
StatusPublished
Cited by20 cases

This text of 199 P.2d 25 (McCulloch v. Liguori) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCulloch v. Liguori, 199 P.2d 25, 88 Cal. App. 2d 366, 1948 Cal. App. LEXIS 1476 (Cal. Ct. App. 1948).

Opinion

BRAY, J.

Plaintiff sued for damages for breach of contract. The court allowed no damages but gave judgment in [368]*368favor of plaintiff for the return of a $750 deposit. Plaintiff appealed from this judgment.

The action involves the failure of defendants to build and deliver possession to plaintiff of a building as provided in an agreement between the parties dated February 2, 1946. The portions of the agreement important here are as follows:

“Ageeement
“We, Alphonsus Liguori and Vera S. Liguori, his wife, hereby agree to lease to R. H. McCulloch ... that building to be constructed on . . . [certain premises in] Redwood' City . . . for a period of sixty (60) months at a total rental of $7500.00 payable as follows:
“$750.00 tobe deposited upon signing this agreement.
“ 125.00 to be paid upon taking possession of building.
11 125.00 to be paid each 30 days thereafter, for 54 months. “Lessors agree to use diligence in constructing the improvements to be placed on said lots and to deliver said premises at the earliest possible date; but same shall be done on or before May 1st, 1946. Said building shall be constructed according to plans and specifications to be furnished by lessors.”

With the execution of the agreement, or shortly thereafter, defendants furnished plans and specifications for the building which were then and there approved and accepted by plaintiff. Defendants retained the only copy. Plaintiff paid the $750 down payment. Thereafter defendants entered into a contract with one Philip Hastings for the construction of the building. Defendants in their answer admit their failure to build the building as required by the agreement, but deny that they refused to build it. As defenses, defendants allege:

(1) that any failure of completion of the building was through no fault of defendants but was due to the failure of Hastings, their building contractor, to complete the building in time;
(2) that the delay in construction was caused by “governmental controls and federal regulations.”

The building was not completed by May 1st, as agreed. On May 24th, plaintiff’s attorney wrote defendants, complaining that the building was not ready as agreed, and also that plaintiff had been unable to learn defendants’ plans as to compliance in the future. He offered to waive any claim for damages if defendants would assure him that the building would be ready within a reasonably short time. On May 27th, defendants answered that completion had been prevented by government restrictions and circumstances beyond [369]*369their control, and offered to return the deposit and release plaintiff from the agreement. They further stated that the building would be completed as soon as possible, and enclosed a check for $750, offering to release plaintiff from any further obligation on the contract. On May 31st, plaintiff answered, stating he did not accept the offer of release, returned the check, and demanded a statement as to whether defendants intended to perform their agreement, and if so, when.

No answer to this letter having been received, plaintiff on June 6th wrote defendants to the effect that plaintiff would hold defendants responsible in damages unless plaintiff received an assurance that the building would be ready for occupancy within a reasonable time.

On June 11th, defendants, through their attorney, replied to the effect that they were advised by their contractor that “he expected the work to proceed from this point on in the customary manner.”

On July 5th, plaintiff notified defendants that because of defendants’ failure to deliver possession of the premises as agreed and their further failure to advise plaintiff when, if at all, they intended to deliver the same, plaintiff elected to treat such failure as a material breach of the contract, and that that day he had entered into a five-year lease of comparable premises at a rental of $225 per month, a difference of $6,000 more than the total rental provided in the agreement between the parties. Demand was made for this and other claimed damages, as well as the return of the first payment.

The court found that defendants had failed to deliver the building as agreed but that such failure was excused because (1) it was the failure of the contractor and without any fault of defendants, and (2) it was caused by government controls and federal regulations, again through no fault of defendants, and because of matters beyond their control. The court further found that plaintiff was not damaged by any act or omission of the defendants, but was entitled to a return of the $750.

Failure of the Contractor

Plaintiff moved to strike this defense from the answer. The motion was denied. It should have been granted. It is obvious that any fault of the builder with whom defendants had entered into a contract, to which the plaintiff was in no wise a party, could not excuse defendants from performing their agreement with plaintiff. Defendants have cited no authority to support their contention that a principal may [370]*370escape an obligation to a third party merely because of the default of his agent. There are none. “Impossibility of performing a promise that is not due to the nature of the performance, but wholly to the inability of the individual promisor, neither prevents the formation of a contract nor discharges a duty created by a contract.” (Restatement of the Law, Contracts, p. 845.)

In Hoag v. Jenan, 86 Cal.App.2d 556 [195 P.2d 451], the court refused to support a defense to an agreement by an owner to enlarge a building for his tenant, based upon the inability of the owner’s contractor to obtain the necessary building materials.

Govebnment Regulations

Defendants have shifted their position since the trial of the case in respect to this defense. They alleged that the delay in construction of the building was caused by government controls and federal regulations. At the trial they attempted to prove that it was difficult to obtain materials because of these regulations. Now, on appeal, they claim that they established the doctrine of commercial frustration. It is doubtful if their answer sets up the defense of commercial frustration. However, assuming that it does, before considering the applicable law, let us examine the facts adduced at the trial.

One Welbanks, a general contractor, called by defendants, testified that prior to and at the time of the execution of the agreement, it was known to him and to all industry that labor and materials were scarce; that in February, March and April, 1946, the prevailing market conditions were such that the only way building materials could be bought was either on the black market or by breaking the law; that after the government conversion order went into effect materials could not be bought even with priorities; that commercial buildings could not get priorities. When asked as to when the conversion order went into effect, he said he thought it was about March. On cross-examination he stated that during that period Hastings completed other buildings of comparable nature, and he himself completed one, although the buildings were started the previous year.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robberson Steel, Inc. v. J. D. Abrams, Inc.
582 S.W.2d 558 (Court of Appeals of Texas, 1979)
Call v. Feher
93 Cal. App. 3d 434 (California Court of Appeal, 1979)
Foreman & Clark Corp. v. Fallon
479 P.2d 362 (California Supreme Court, 1971)
Abrams v. Motter
3 Cal. App. 3d 828 (California Court of Appeal, 1970)
DREDGE CORPPRATION v. Wells Cargo, Inc.
410 P.2d 751 (Nevada Supreme Court, 1966)
Kennedy v. Reece
225 Cal. App. 2d 717 (California Court of Appeal, 1964)
Gold v. Salem Lutheran Home Assn.
347 P.2d 687 (California Supreme Court, 1959)
Haggerty v. City of Oakland
326 P.2d 957 (California Court of Appeal, 1958)
Oosten v. Hay Haulers Dairy Employees & Helpers Union
291 P.2d 17 (California Supreme Court, 1955)
City of Vernon v. City of Los Angeles
290 P.2d 841 (California Supreme Court, 1955)
Lewis v. James
285 P.2d 86 (California Court of Appeal, 1955)
Gillespie v. Ormsby
272 P.2d 949 (California Court of Appeal, 1954)
Walpole v. Prefab Manufacturing Co.
230 P.2d 36 (California Court of Appeal, 1951)
Glens Falls Indemnity Co. v. Perscallo
216 P.2d 567 (California Court of Appeal, 1950)
McCulloch v. Superior Court
205 P.2d 689 (California Court of Appeal, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
199 P.2d 25, 88 Cal. App. 2d 366, 1948 Cal. App. LEXIS 1476, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcculloch-v-liguori-calctapp-1948.