Robberson Steel, Inc. v. J. D. Abrams, Inc.

582 S.W.2d 558, 27 U.C.C. Rep. Serv. (West) 114, 1979 Tex. App. LEXIS 3639
CourtCourt of Appeals of Texas
DecidedMay 16, 1979
Docket6770
StatusPublished
Cited by13 cases

This text of 582 S.W.2d 558 (Robberson Steel, Inc. v. J. D. Abrams, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robberson Steel, Inc. v. J. D. Abrams, Inc., 582 S.W.2d 558, 27 U.C.C. Rep. Serv. (West) 114, 1979 Tex. App. LEXIS 3639 (Tex. Ct. App. 1979).

Opinion

OPINION

OSBORN, Justice.

This case arises out of a breach of contract between a steel fabricator and a construction company who had contracted to build four bridges for the State of Texas. The trial Court found for the steel fabricator as to the amount due for steel furnished but unpaid for and provided for recovery of attorney’s fees as found by the jury, but the Court allowed the construction company an offset for the amount of its damages as found by the jury to have resulted from the delay in delivery of the steel for the bridges. We affirm.

J. D. Abrams, Inc. (contractor) sued Rob-berson Steel, Inc. (fabricator) for damages resulting from a timely failure to furnish structural steel for four bridges being constructed for the Texas Highway Department in El Paso County, Texas. After Abrams became the successful bidder on this project it entered into a written contract with Robberson to furnish the necessary structural steel at various dates for a certain price per unit of steel. Overall the contract price was $1,347,214.33. The purchase order issued by Abrams to Robberson is dated 4-8-74 and it sets forth the shipping dates for the four different structures to be completed. Paragraph 8 of the General Conditions of the purchase order states “Delivery of materials will be in accordance with the construction schedule established by J. D. Abrams, Inc. Time is the essence of this Contract * * *.”

Robberson was unable to obtain steel from the steel mills and was approximately six months late in delivering some of the fabricated steel to Abrams. That delay resulted in this suit. Robberson claimed the delay was excused under Section 2.615, Tex. Bus. & Comm.Code. It also pled waiver as a defense. Robberson filed a cross-action against Abrams and Argonaut Insurance Company, the surety on its payment bond, for the balance due on the purchase price of steel delivered, plus interest and attorney’s fees. The trial Court found the amount owed by Abrams to Robberson to be $204,-990.58 and did not submit any issue to the *560 jury on that claim. There is no complaint about that finding.

In answer to Special Issue No. 1, the jury found Abrams’ damages from the delay in delivery of steel to be $127,250.00. The next four issues about which there is substantial dispute are as follows:

“SPECIAL ISSUE NO. 2
“Was the delay in the delivery of the fabricated steel by the defendant the result of the Steel Mills’ inability to furnish the steel to the Defendant?
“ANSWER ‘YES’ OR ‘NO’.
“ANSWER: YES
“If you have answered the following Special Issue ‘Yes’, then but not otherwise, answer the following Special Issue.”
“SPECIAL ISSUE NO. S
“Was such inability on the part of the Steel Mills to furnish the steel to the Defendant, if you have so found, a contingency the non-occurrence of which was a basic assumption of the parties on which the contract (Plaintiff’s Exhibit-22A, B, C) was made?
“ANSWER ‘YES’ OR ‘NO’
“ANSWER: YES
“If you have answered the foregoing Special Issue ‘Yes’, then but not otherwise, answer the following Special Issue.”
“SPECIAL ISSUE NO. 4
“Did the Defendant, Robberson Steel, Inc. seasonably notify the Plaintiff, J. D. Abrams, Inc. of the delay in delivery?
“ANSWER ‘YES’ OR ‘NO’
“ANSWER: YES
“If you have answered the foregoing Special Issue ‘Yes’, then but not otherwise, answer the following Special Issue.”
“SPECIAL ISSUE NO. 5
“Did the Defendant, Robberson Steel, Inc. allocate the steel it received from the Steel Mills among its customers in a fair and reasonable manner?
“ANSWER ‘YES’ OR ‘NO’
“ANSWER: YES”

In addition, the jury failed to find a waiver of timely delivery as required by the purchase order, found Robberson gave written notice by certified mail of nonpayment of its claim to Abrams and Argonaut, and found Robberson’s attorney’s fees for prosecuting its claim to be $7,200.00.

After the verdict was received .various motions for judgment were filed by the parties. The trial Court entered judgment based upon its finding that Abrams and Argonaut were indebted to Robberson for steel delivered and unpaid for in the amount of $204,990.58, plus the sum of $7,200.00 for attorney’s fees, and interest on such sums from the date of the verdict on July 6,1977, less the offset of $127,250.00 as damages for delay in delivery of steel. In entering such judgment the trial Court found “1. Robberson Steel, Inc., considered the availability of steel prior to entering into the contract; and 2. Robberson Steel, Inc., assumed the risk of non-availability of steel under the contract; and 3. By the contract terms, Robberson Steel, Inc., assumed the obligation to deliver steel in strict accordance with the schedule in the contract;” and granted Abrams’ motion for judgment non obstante veredicto and motions for judgment on the basis of the verdict and findings of the Court on unsubmit-ted issues. The net effect of the judgment was that the trial Court made findings on certain controlling issues as to the defense of delay in delivery of steel under Section 2.615, Tex.Bus. & Comm.Code, and set aside certain jury findings on those issues.

By the first four points of error Robber-son complains of the trial Court’s disregarding the jury’s answers to Special Issues Nos. 2 through 5 and entering judgment notwithstanding those findings. Points of Error Nos. 5, 6 and 7 complain about the trial Court making findings on unsubmitted issues which form the basis for the trial Court’s judgment.

The controlling provision in Section 2.615, Tex.Bus. & Comm.Code, provides that “Delay in delivery * * * by a seller * * is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made * * *.” In United *561 States v. Wegematic Corporation, 360 F.2d 674 (2d Cir. 1966) the Court said this “test seems a somewhat complicated way of putting Professor Corbin’s question of how much risk the promisor assumed. Recent Developments in the Law of Contracts, 50 Harv.L.Rev. 449, 465-66 (1937); 2 Corbin, Contracts § 1333, at 371.” In West Los Angeles Institute for Cancer Research v. Mayer, 366 F.2d 220 (9th Cir. 1966), the Court in considering the test to be applied with regard to impossibility in the performance of a contract said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
582 S.W.2d 558, 27 U.C.C. Rep. Serv. (West) 114, 1979 Tex. App. LEXIS 3639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robberson-steel-inc-v-j-d-abrams-inc-texapp-1979.