Mishara Construction Co. v. Transit-Mixed Concrete Corp.

310 N.E.2d 363, 365 Mass. 122, 70 A.L.R. 3d 1259, 14 U.C.C. Rep. Serv. (West) 556, 1974 Mass. LEXIS 635
CourtMassachusetts Supreme Judicial Court
DecidedApril 17, 1974
StatusPublished
Cited by56 cases

This text of 310 N.E.2d 363 (Mishara Construction Co. v. Transit-Mixed Concrete Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mishara Construction Co. v. Transit-Mixed Concrete Corp., 310 N.E.2d 363, 365 Mass. 122, 70 A.L.R. 3d 1259, 14 U.C.C. Rep. Serv. (West) 556, 1974 Mass. LEXIS 635 (Mass. 1974).

Opinion

Reardon, J.

In this action of contract a verdict was returned for the defendant. The case is here on the plaintiffs exceptions.

The plaintiff Mishara Construction Company, Inc. (Mis-hara) was the general contractor under contract with the Pittsfield Housing Authority for the construction of Rose Manor, a housing project for the elderly. In September, 1966, the plaintiff negotiated with the defendant Transit-Mixed Concrete Corp. (Transit) for the supplying of ready-mixed concrete to be used on the project. An agreement was reached that Transit would supply all the concrete needed on the project at a price of $13.25 a cubic yard, with deliveries to be made at the times and in the amounts as ordered by Mishara. This agreement was evidenced by a *124 purchase order signed by the parties on September 21, 1966. That purchase order identified the Rose Manor project and indicated that delivery was to be made “[a]s required by Mishara Construction Company.” Performance under this contract was satisfactory to both parties until April, 1967. In that month a labor dispute disrupted work on the job site. Although work resumed on June 15, 1967, a picket line was maintained on the site until the completion of the project in 1969. Throughout this period, with very few exceptions, no deliveries of concrete were made by Transit notwithstanding frequent requests by Mishara. After notifying Transit of its intention, Mishara purchased the balance of its concrete requirements elsewhere. Mishara sought in damages the additional cost of concrete incurred by virtue of the higher price of the replacement product, as well as the expenses of locating an alternate source.

The plaintiffs exceptions relate to the introduction of certain evidence and the failure of the trial judge to give certain requested instructions. Requests 2 and 3 sought instructions that the requirements that a definite quantity of goods and a definite duration of performance be specified in an enforceable contract are satisfied if the contract is one which calls for deliveries as required on a particular project. Since this is a contract for the sale of goods it is governed by the Uniform Commercial Code. G. L. c. 106. “Requirements contracts” of the kind the plaintiff contends was present here are explicitly recognized as valid by the Code in G. L. c. 106, § 2-306 (l). 1 The Official Comment No. 2 to that section makes clear the drafters’ intention that when quantity is phrased only in terms of output or requirements the contract “is not too indefinite since it is held to mean the actual good faith output or requirements” of the buyer *125 or seller. Such a view is consistent with the established law of Massachusetts. Royal Paper Box Co. v. E. R. Apt Shoe Co. 290 Mass. 207 (1935). Neofotistos v. Harvard Brewing Co. 341 Mass. 684 (1961). Nor is a supply contract tied to a particular project too indefinite with respect to duration. This is not a case in which no time for performance is set out in the contract, and in which the court by long established rule will imply a reasonable time. Cf. Cohen v. Wintman, 236 Mass. 471, 472 (1920); G. L. c. 106, § 2-309 (1). Although no specific date is named in the contract, the time is sufficiently determined by the occurrence of a specified event, i.e., the completion of the project. In Phelps v. Shawprint, Inc. 328 Mass. 352 (1952), in which payments were to continue so long as certain defendants were associated with the defendant corporation, it was said at pp. 354-355: “The contract was not silent on this aspect for it carried its own measure of time. .. . Such a contract is not too indefinite or uncertain to be enforceable at least for partial breaches even though it is impossible to predict precisely when the contingency will occur that will bring the contract to an end.” See Proctor v. Union Coal Co. 243 Mass. 428 (1923); G. L. c. 106, § 2-309, comment No. 1. Therefore both of Mishara’s requests were correct as matters of law. We believe, however, that these points were adequately covered in the judge’s charge albeit in less than perfect form. There was no error in the failure to give instructions in precisely the form requested. Palmer Russell Co. v. Rothenberg, 328 Mass. 477, 482-483 (1952). Campbell v. Shea, 332 Mass. 422, 425 (1955).

Request 9 was an instruction that the contract was not terminable until Mishara had received all the concrete it required for the project. Again, although this was a correct statement of the law, we believe it was not error for the judge to refuse it. As has been shown, the specification of deliveries as needed on the project was a sufficiently definite statement of the time for performance. Therefore this was not a contract which contemplated ongoing and open-ended performance which would be terminable on reasonable notice. G. L. c. 106, § 2-309, and comment *126 No. 1. Simons v. American Dry Ginger Ale Co. Inc. 335 Mass. 521 (1957). Since, however, there was no indication from the evidence or the judge’s charge that this was such a contract, there was no need to charge that it was not. A request correct in law but not appropriate to the conditions of a case is properly refused. Altavilla v. Old Colony St. Ry. 222 Mass. 322 (1916). McNeil v. Middlesex & Boston St. Ry. 233 Mass. 254, 256 (1919). Since it is unlikely that the jury would on their own initiative come to the conclusion that this was a contract which could properly be terminated prior to completion of performance by either party, it would have been misleading for the judge to charge that it was not terminable by the defendant. See Dixon v. New England R. R. 179 Mass. 242, 247 (1901).

Nor was there error in the refusal to give request 13, that on the evidence the jury “must find that [the] defendant breached its contract with [the] plaintiff by failing to deliver” Mishara’s concrete requirements. The principal issue in the case was the defendant’s claimed excuse of impossibility of performance. The determination of that issue depended on facts and circumstances which were for the jury to decide. While we suppose one could develop a nice technical argument that impossibility does not nullify a breach but rather provides an excuse for it, to give the instruction requested would surely have misled the jury on the ultimate question of liability. Moreover, the failure to give it was of no detriment to the plaintiff of which it can complain. See Howes v. Grush, 131 Mass. 207 (1881). Dixon v. New England R. R., supra.

The remainder of the plaintiffs exceptions relate to the proffered defence of the impossibility of performance. Objection was made to the introduction of all evidence regarding the existence of a picket line at the job site and the difficulty which Transit did encounter or might have encountered in attempting to make deliveries through that picket line.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ALAN FILZER & Others v. PITSICK LLC & Others.
Massachusetts Appeals Court, 2025
Private Jet Servs. Grp. v. Tauck, Inc.
2024 N.H. 20 (Supreme Court of New Hampshire, 2024)
Honey Dew Associates, Inc. v. John F. Kennedy.
Massachusetts Appeals Court, 2024
Becker v. Phelps
111 N.E.3d 1114 (Massachusetts Appeals Court, 2018)
Karaa v. Kuk Yim
20 N.E.3d 943 (Massachusetts Appeals Court, 2014)
Fargo Management, LLC v. City of Worcester
33 Mass. L. Rptr. 65 (Massachusetts Superior Court, 2014)
Whitcomb v. Smith
33 Mass. L. Rptr. 172 (Massachusetts Superior Court, 2014)
Protégé Software Services, Inc. v. Colameta
30 Mass. L. Rptr. 127 (Massachusetts Superior Court, 2012)
Global Investors Agent Corp. v. National Fire Insurance
927 N.E.2d 480 (Massachusetts Appeals Court, 2010)
Commonwealth v. B & M Fitzgerald Builders, Inc.
883 N.E.2d 328 (Massachusetts Appeals Court, 2008)
Wagner & Wagner Auto Sales, Inc. v. Land Rover North America, Inc.
539 F. Supp. 2d 461 (D. Massachusetts, 2008)
Gurwitz v. Mercantile/Image Press, Inc.
21 Mass. L. Rptr. 84 (Massachusetts Superior Court, 2006)
RGJ Associates, Inc. v. Stainsafe, Inc.
338 F. Supp. 2d 215 (D. Massachusetts, 2004)
Waste Stream Environmental, Inc. v. Lynn Water & Sewer Commission
15 Mass. L. Rptr. 723 (Massachusetts Superior Court, 2003)
Bilingual Master Parents Advisory Counsel v. Boston School Committee
14 Mass. L. Rptr. 612 (Massachusetts Superior Court, 2002)
Reale v. Donato
12 Mass. L. Rptr. 478 (Massachusetts Superior Court, 2000)
Saab v. Norton Family, Inc.
2000 Mass. App. Div. 200 (Mass. Dist. Ct., App. Div., 2000)

Cite This Page — Counsel Stack

Bluebook (online)
310 N.E.2d 363, 365 Mass. 122, 70 A.L.R. 3d 1259, 14 U.C.C. Rep. Serv. (West) 556, 1974 Mass. LEXIS 635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mishara-construction-co-v-transit-mixed-concrete-corp-mass-1974.