Fargo Management, LLC v. City of Worcester

33 Mass. L. Rptr. 65
CourtMassachusetts Superior Court
DecidedNovember 21, 2014
DocketNo. SUCV201201028C
StatusPublished

This text of 33 Mass. L. Rptr. 65 (Fargo Management, LLC v. City of Worcester) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fargo Management, LLC v. City of Worcester, 33 Mass. L. Rptr. 65 (Mass. Ct. App. 2014).

Opinion

Gordon, Robert B., J.

The plaintiff, Fargo Management, LLC (“Fargo”), has brought suit against the defendant, City of Worcester, Massachusetts (“Worcester” or the “City”), alleging material breach of the Land Disposition and Development Agreement entered into by the parties on June 3, 2003 for the acquisition of certain land and the development thereof. It is undisputed that Worcester did not commence construction of a contractually required skywalk between the Worcester Center Boulevard Parking Garage and the Hilton Garden Inn Hotel, which is owned by Fargo. Fargo now moves for summary judgment as to liability on the sole count in its Complaint for material breach of contract, on the ground that Worcester has conceded its failure to construct the skywalk by October 13, 2006—the date that Fargo was issued a certificate of use and occupancy for its hotel. For its part, Worcester asserts that Fargo’s contract is void for lack of an appropriation certification under G.L.c. 44, §31C, and that in all events its non-construction of the subject skywalk was excused on grounds of frustration of purpose and commercial impracticability/impossibility. Worcester additionally defends Fargo’s contract action, and moves for summary judgment in its favor on the sole contract count of the Counterclaim, on the ground that Fargo materially breached the agreement by withholding payment (beginning in April 2007) for contractually reserved parking spaces for Fargo’s hotel and restaurant guests in the Worcester Center Boulevard Parking Garage.

BACKGROUND

The evidence, as revealed by the summary judgment record, establishes the following.1

On June 3, 2003, Worcester and Fargo entered into a Land Disposition and Development Agreement (the “LDDA” or the “Agreement”), whereby Worcester agreed to convey to Fargo a parcel of land located at 35 Worcester Center Boulevard for $1,000,000 as part of a planned development project. The Agreement required Fargo to construct a hotel on the conveyed property. In December 2004, the parties executed “Amendment Number One” to the LDDA (the “LDDA Amendment”), which called upon Worcester to construct an elevated pedestrian walkway (the “Skywalk”) connecting the forthcoming Hilton Garden Inn Hotel (the “Hotel”) with the adjacent Worcester Center Boulevard Parking Garage (the “Garage”) and Worcester Convention Center Facilily. Pursuant to the express terms of the LDDA Amendment, construction of the Skywalk was due for completion by the time the Hotel was complete and the project architect had applied for its first certificate of use and occupancy. The agreement to construct the Skywalk thus provides in pertinent part as follows:

(c) Slqjwalk Agreement Worcester shall construct an elevated pedestrian walkway (“Skywalk”) connecting the [hotel] to both the Worcester Center Boulevard Parking Garage and the Convention Center Facilily under the following terms and conditions:
(2) Fargo shall contribute $625,000 to Worcester for the construction of the Skywalk;
(3) Fargo shall cause the footing for the Skywalk to be constructed in the area shown on the Plan as the Skywalk Easement Area under the contract it issues for the construction of the Hotel;
(4) The amount expended by Fargo for the construction of said footing shall be credited against the $625,000 due Worcester under this subsection;
(5) Worcester shall include in the Skywalk construction plans a connection between the Skywalk and the building to be constructed by Fargo on the Property and that [sic] such work will be performed by the general contractor selected by Worcester to construct the Skywalk;
(6) Worcester shall complete construction of the Skywalk at or before the date upon which the project architect for the Hotel applies for the first certificate of use and occupancy.

(Ex. 3, at 2.)

A separate part of the LDDA Amendment, the “Parking Agreement,” provides that Worcester will guarantee a number of parking spaces in the Garage for guests and patrons of the Hotel and its restaurants. Under the Parking Agreement, Worcester reserves (and Fargo commits to pay for) 200 parking spaces at a rate of $65 per space per day commencing upon completion and opening of the Hotel. Additionally, Worcester keeps available for day-to-day reservation an additional 100 parking spaces at a rate of $6 per vehicle per overnight parking in these preferred spaces. (Id. at 3.)

The LDDA and LDDA Amendment did not fix the cost of construction for the Skywalk or expressly provide for a source of funding. Rather, as evidenced by deposition testimony from Worcester City Manager Michael O’Brien, a number of financial sources for the development project were identified, most notably, a loan guarantee of $5,125,000 appropriated by the Worcester City Council from the “DCU Special District Improvements” account, which was created “for the purpose of making improvements to the DCU Arena and Convention Center.” Other sources of revenue identified to fund the Skywalk’s construction included a $1,875,000 loan guarantee supported by bonds based on anticipated parking garage revenues; $1,260,000 from the DCU Naming Rights Fund; and [67]*67a contractually required $625,000 cash contribution for the Skywalk from Fargo.

Construction for the Skywalk was first put out to bid in 2005, following a professional estimate that totaled $4,065,202. In 2005, two companies bid on this piece of the project; and their bids came in at $6,507,000 and $7,488,277, respectively. The parties do not dispute that the primaiy cause of the delta between the original estimate and the bids received was an intervening increase in the cost of steel. On October 10, 2006, construction of the Hotel was completed on Worcester Center Boulevard, and a certificate of use and occupancy issued to it on October 13, 2006. The Hotel opened for operation beginning on October 17, 2006. Construction on the Skywalk, however, had not even begun. As agreed, Fargo had included in its construction of the Hotel the footing required for the Skywalk. Worcester’s project consultant assessed the cost to construct the footing at $200,0002 which was to be credited against Fargo’s contractually required contribution to the Skywalk of $625,000.

In 2007, the Skywalk project was redesigned (to reduce construction costs) and rebid, with the two lowest bids returning at $7,975,000 and $8,251,000, respectively. Once again, the received bids were substantially higher than the estimated construction costs for the Skywalk, which after re-design were estimated at $6,400,000. The failure to begin construction on the Skywalk prompted Fargo, in April 2007, to cease further payment for the guaranteed and preferred parking spaces in the adjacent Garage. Thereafter, in May 2007, Worcester City Manager Michael O’Brien wrote to the Worcester City Council, informing the Council of his decision to discontinue the Skywalk’s construction due to its high costs, and suggesting that Worcester reallocate the appropriated funds to other uses.

DISCUSSION

I. Standard of Review

Summaiy judgment is appropriate when, viewing the evidence in the light most favorable to the non-moving party, there is no genuine dispute of material fact and the moving parly is entitled to judgment as a matter of law. Mass.R.Civ.P. 56(c); Cassesso v. Commissioner of Corr., 390 Mass. 419, 422 (1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Godbout v. Cousens
485 N.E.2d 940 (Massachusetts Supreme Judicial Court, 1985)
Mishara Construction Co. v. Transit-Mixed Concrete Corp.
310 N.E.2d 363 (Massachusetts Supreme Judicial Court, 1974)
City of Lawrence v. Falzarano
402 N.E.2d 1017 (Massachusetts Supreme Judicial Court, 1980)
Charles, Henry & Crowley Co. Inc. v. Home Ins. Co.
212 N.E.2d 240 (Massachusetts Supreme Judicial Court, 1965)
Chase Precast v. JOHN J. PAONESSA CO., COMMONWEALTH
566 N.E.2d 603 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Ryan v. City of Somerville
103 N.E.2d 707 (Massachusetts Supreme Judicial Court, 1952)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
City of Marlborough v. Cybulski, Ohnemus & Associates, Inc.
346 N.E.2d 716 (Massachusetts Supreme Judicial Court, 1976)
The Pitt News v. Fisher
215 F.3d 354 (Third Circuit, 2000)
Canton v. Thomas
162 N.E. 769 (Massachusetts Supreme Judicial Court, 1928)
Massachusetts Municipal Wholesale Electric Co. v. Town of Danvers
411 Mass. 39 (Massachusetts Supreme Judicial Court, 1991)
Reynolds Bros. v. Town of Norwood
414 Mass. 295 (Massachusetts Supreme Judicial Court, 1993)
Twin Fires Investment, LLC v. Morgan Stanley Dean Witter & Co.
445 Mass. 411 (Massachusetts Supreme Judicial Court, 2005)
Bradston Associates, LLC v. Suffolk County Sheriff's Department
892 N.E.2d 732 (Massachusetts Supreme Judicial Court, 2008)
Kitras v. Zoning Administrator
453 Mass. 245 (Massachusetts Supreme Judicial Court, 2009)
Prozinski v. Northeast Real Estate Services, LLC
797 N.E.2d 415 (Massachusetts Appeals Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
33 Mass. L. Rptr. 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fargo-management-llc-v-city-of-worcester-masssuperct-2014.