Chase Precast v. JOHN J. PAONESSA CO., COMMONWEALTH

566 N.E.2d 603, 409 Mass. 371, 1991 Mass. LEXIS 87
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 20, 1991
StatusPublished
Cited by57 cases

This text of 566 N.E.2d 603 (Chase Precast v. JOHN J. PAONESSA CO., COMMONWEALTH) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chase Precast v. JOHN J. PAONESSA CO., COMMONWEALTH, 566 N.E.2d 603, 409 Mass. 371, 1991 Mass. LEXIS 87 (Mass. 1991).

Opinion

Lynch, J.

This appeal raises the question whether the doctrine of frustration of purpose may be a defense in a breach *372 of contract action in Massachusetts, and, if so, whether it excuses the defendant John J. Paonessa Company, Inc. (Paonessa), from performance.

The claim of the plaintiff, Chase Precast Corporation (Chase), arises from the cancellation of its contracts with Paonessa to supply median barriers in a highway reconstruction project of the Commonwealth. Chase brought an action to recover its anticipated profit on the amount of median barriers called for by its supply contracts with Paonessa but not produced. Paonessa brought a cross action against the Commonwealth for indemnification in the event it should be held liable to Chase. After a jury-waived trial, a Superior Court judge ruled for Paonessa on the basis of impossibility of performance. 2 Chase and Paonessa cross appealed. The Appeals Court affirmed, noting that the doctrine of frustration of purpose more accurately described the basis of the trial judge’s decision than the doctrine of impossibility. Chase Precast Corp. v. John J. Paonessa Co., 28 Mass. App. Ct. 639 (1990). We agree. We allowed Chase’s application for further appellate review, and we now affirm.

The pertinent facts are as follows. In 1982, the Commonwealth, through the Department of Public Works (department), entered into two contracts with Paonessa for resurfacing and improvements to two stretches of Route 128. Part of each contract called for replacing a grass median strip between the north and southbound lanes with concrete surfacing and precast concrete median barriers. Paonessa entered into two contracts with Chase under which Chase was to supply, in the aggregate, 25,800 linear feet of concrete median barriers according to the specifications of the department for highway construction. The quantity and type of barriers to be supplied were specified in two purchase orders prepared by Chase.

*373 The highway reconstruction began in the spring of 1983. By late May, the department was receiving protests from angry residents who objected to use of the concrete median barriers and removal of the grass median strip. Paonessa and Chase became aware of the protest around June 1. On June 6, a group of about 100 citizens filed an action in the Superior Court to stop installation of the concrete median barriers and other aspects of the work. On June 7, anticipating modification by the department, Paonessa notified Chase by letter to stop producing concrete barriers for the projects. Chase did so upon receipt of the letter the following day. On June 17, the department and the citizens’ group entered into a settlement which provided, in part, that no additional concrete median barriers would be installed. On June 23, the department deleted the permanent concrete median barriers item from its contracts with Paonessa.

Before stopping production on June 8, Chase had produced approximately one-half of the concrete median barriers called for by its contracts with Paonessa, and had delivered most of them to the construction sites. Paonessa paid Chase for all that it had produced, at the contract price. Chase suffered no out-of-pocket expense as a result of cancellation of the remaining portion of barriers.

This court has long recognized and applied the doctrine of impossibility as a defense to an action for breach of contract. See, e.g., Boston Plate & Window Glass Co. v. John Bowen Co., 335 Mass. 697 (1957); Baetjer v. New England Alcohol Co., 319 Mass. 592 (1946); Butterfield v. Byron, 153 Mass. 517 (1891). Under that doctrine, “where from the nature of the contract it appears that the parties must from the beginning have contemplated the continued existence of some particular specified thing as the foundation of what was to be done, then, in the absence of any warranty that the thing shall exist ... the parties shall be excused . . . [when] performance becomes impossible from the accidental perishing of the thing without the fault of either party.” Boston Plate & Window Glass Co., supra at 700, quoting Hawkes v. Kehoe, 193 Mass. 419, 423 (1907).

*374 On the other hand, although we have referred to the doctrine of frustration of purpose in a few decisions, we have never clearly defined it. See Mishara Constr. Co. v. Transit-Mixed Concrete Corp., 365 Mass. 122, 128-129 (1974); Essex-Lincoln Garage, Inc. v. Boston, 342 Mass. 719, 721-722 (1961); Baetjer v. New England Alcohol Co., supra at 602. Other jurisdictions have explained the doctrine as follows: when an event neither anticipated nor caused by either party, the risk of which was not allocated by the contract, destroys the object or purpose of the contract, thus destroying the value of performance, the parties are excused from further performance. See Howard v. Nicholson, 556 S.W.2d 477, 482 (Mo. Ct. App. 1977); Perry v. Champlain Oil Co., 101 N.H. 97 (1957); Lloyd v. Murphy, 25 Cal. 2d 48 (1944).

In Mishara Constr. Co., supra at 129, we called frustration of purpose a “companion rule” to the doctrine of impossibility. Both doctrines concern the effect of supervening circumstances upon the rights and duties of the parties. The difference lies in the effect of the supervening event. Under frustration, “[performance remains possible but the expected value of performance to the party seeking to be excused has been destroyed by [the] fortuitous event . . . .” 3 Lloyd v. Murphy, supra at 53. The principal question in both kinds of cases remains “whether an unanticipated circumstance, the risk of which should not fairly be thrown on the promisor, has made performance vitally different from what was reasonably to be expected.” See Lloyd, supra at 54 (frustration); Mishara Constr. Co., supra at 12;9 (impossibility).

Since the two doctrines differ only in the effect of the fortuitous supervening event, it is appropriate to look to our *375 cases dealing with impossibility for guidance in treating the issues that are the same in a frustration of purpose case. 4 The trial judge’s findings with regard to those issues are no less pertinent to application of the frustration defense because they were considered relevant to the defense of impossibility.

Another definition of frustration of purpose is found in the Restatement (Second) of Contracts § 265 (1981):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ALAN FILZER & Others v. PITSICK LLC & Others.
Massachusetts Appeals Court, 2025
Doe v. Brandeis University
D. Massachusetts, 2022
JACOB SLATER & another v. TRAYNOR MANAGEMENT, INC., & another.
101 Mass. App. Ct. 705 (Massachusetts Appeals Court, 2022)
Stern Taylor v. Sawyer
D. Massachusetts, 2022
DON PERRY v. ZONING BOARD OF APPEALS OF HULL & others.
100 Mass. App. Ct. 19 (Massachusetts Appeals Court, 2021)
McCullough v. Chase Great Marsh LLC
Massachusetts Land Court, 2021
Becker v. Phelps
111 N.E.3d 1114 (Massachusetts Appeals Court, 2018)
Bairos Construction, Inc. v. Anjos
2015 Mass. App. Div. 163 (Mass. Dist. Ct., App. Div., 2015)
Karaa v. Kuk Yim
20 N.E.3d 943 (Massachusetts Appeals Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
566 N.E.2d 603, 409 Mass. 371, 1991 Mass. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chase-precast-v-john-j-paonessa-co-commonwealth-mass-1991.