Dobbins v. Redden

759 S.W.2d 477, 1988 Tex. App. LEXIS 2811, 1988 WL 120273
CourtCourt of Appeals of Texas
DecidedSeptember 14, 1988
Docket04-88-00027-CV
StatusPublished
Cited by7 cases

This text of 759 S.W.2d 477 (Dobbins v. Redden) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dobbins v. Redden, 759 S.W.2d 477, 1988 Tex. App. LEXIS 2811, 1988 WL 120273 (Tex. Ct. App. 1988).

Opinion

OPINION

BUTTS, Justice.

This is an appeal from a judgment against Robert Dobbins, appellant. The central issue on appeal is whether the trial court properly disregarded certain jury findings.

In July 1985, the parties entered into an agreement wherein Roy Redden, appellee, agreed to construct a tank and dam on Dobbins’ property in Uvalde County. Redden initially sued Dobbins on a sworn account, alleging that $14,905.00 was still owed for his services on the project. He also sought foreclosure on a builders’ and mechanics’ lien. In addition he asked for attorney fees. (The foreclosure matter is not part of the appeal.) Dobbins filed a sworn denial alleging affirmative defenses of failure of consideration, payment, set-off, accord and satisfaction. He further counterclaimed for breach of contract and violations of the Deceptive Trade Practices-Consumer Protection Act (DTPA). TEX.BUS. & COM.CODE ANN. § 17.41 et seq. (Vernon 1973).

The jury found that Redden had constructed the tank in a good and workmanlike manner, that Dobbins had agreed to pay for Redden’s services, and that Dobbins presently owed $14,905.00 as the balance due for services. However, the jury also found that Redden had failed to perform all of his obligations under the agreement to construct the tank and dam and that the reasonable cost to repair or complete the tank and dam would be $10,-000.00. The trial court apparently disregarded these last two findings and entered judgment in favor of Redden for $14,-905.00 and attorney fees.

In his first two points of error, Dobbins argues that the trial court erred by denying his motion to reform the judgment because of the finding that Redden had breached the contract. He also argues that Redden failed to plead, prove, or submit issues on quantum meruit and therefore the court could not properly award damages on this theory, and, further, that the trial court lacked jurisdiction to disregard, on its own motion, the jury’s findings on appellant’s counterclaim. He requests reversal or alternatively that the judgment be reformed by setting off of the $10,000.00 found by the jury against the sum awarded to Redden.

The chief complaint is that the trial court improperly disregarded the jury’s findings that Redden had breached the contract and that appellant had been damaged in the amount of $10,000.00. The jury answered, along with other questions, the following two:

SPECIAL ISSUE NO. 7B

Do you find that Redden failed to perform all of his obligations to Dobbins under the agreement to construct the tank and dam?
ANSWER: “Yes.”

*479 SPECIAL ISSUE NO. 26

What sum of money, if any, do you find would reasonably compensate Dobbins for the following damages?
B. The reasonable and necessary cost to repair or complete the tank and dam. ANSWER: “$10,000.00.”

A trial court may disregard the jury’s finding on immaterial issues and render judgment based upon the remaining findings. C. & R. Transport, Inc. v. Campbell, 406 S.W.2d 191, 194 (Tex.1966); Brown v. Armstrong, 713 S.W.2d 725 (Tex.App.—Houston [14th Dist.] 1986, writ ref’d n.r.e.); J.R. Neatherlin Corp. v. Baughman, 580 S.W.2d 129, 130 (Tex.Civ.App.— Houston [14th Dist.] 1979, writ ref’d n.r.e.). Moreover a trial court on its own motion may disregard the jury’s answer to immaterial issues. However, when the issue is material the judgment must conform to the finding. Southern Pacific Transportation Co. v. Allen, 525 S.W.2d 300, 304 (Tex.Civ.App.—Houston [14th Dist.] 1975, no writ); Ridout v. Mobile Housing, Inc., 497 S.W.2d 66, 67 (Tex.Civ.App.—Austin 1973, writ ref'd n.r.e.). An issue is immaterial when it should not have been presented to the jury and such finding is inapplicable to the case. Robberson Steel, Inc. v. J.D. Abrams, Inc., 582 S.W.2d 558, 564 (Tex.Civ.App.—El Paso 1979, no writ); Ridout v. Mobile Housing, Inc., 497 S.W.2d at 67-68.

Here, there is evidence of an oral agreement (contract) between the parties providing for construction of the tank and dam. A special issue may be disregarded, even though properly submitted, where it has been rendered immaterial by other findings. Blue Bell, Inc. v. Isbell, 545 S.W.2d 563, 566 (Tex.Civ.App.—El Paso 1976, no writ); Saper v. Rodgers, 418 S.W.2d 874, 877 (Tex.Civ.App.—Houston [1st Dist.] 1967, writ ref’d n.r.e.). The jury in the instant case found that the services performed by Redden were done in a good workmanlike manner, that Dobbins agreed to pay him $85.00 per hour, that the amount presently due for services rendered was $14,905.00. The jury found in favor of Redden on all DTPA issues, including a finding that the construction was in fact performed in a skillful and workmanlike manner. The jury also specifically found that no misrepresentation or breach of warranty was committed by Redden.

Although these findings were in favor of Redden, the jury also found that Redden failed to perform all of his obligations under the agreement to construct the tank and dam, and that the reasonable and necessary costs to repair or complete the tank and dam was $10,000.00.

Rule 301 of the Texas Rules of Civil Procedure provides, in part, that the judgment of the court shall conform to the pleadings, the nature of the case proved and the verdict, if any, and shall be so framed as to give the party all the relief to which he may be entitled either in law or equity. “Provided, that upon motion and reasonable notice the court may ... disregard any Special Issue Jury Finding 1 that has no support in the evidence....” TEX.R.CIV.P. 301 (Vernon 1977).

In this case there was no motion by Redden that the court disregard the two jury findings. The judgment does not mention disregarding the findings, although that clearly was done.

The evidence was that both parties thought the stock tank and dam could be built for the sum of $10,000.00. That is the sum that Dobbins paid Redden. The evidence further showed that Redden confronted “core” problems on the construction. He was unable to establish a bottom. He testified that Dobbins told him to continue the work even though it would cost more than $10,000.00, while Dobbins testified that his stated and final cost would be only that amount. There was conflicting evidence whether Redden was told to leave the work unfinished or whether he abandoned the project. In any event, the evidence established that the tank and dam were not completed and were not functioning.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beltran v. Brookshire Grocery Co.
358 S.W.3d 263 (Court of Appeals of Texas, 2012)
Susie Aguilera v. Santiago Nava
Court of Appeals of Texas, 2010
Selma Clyde Gober v. Darlene Lester Davis
Court of Appeals of Texas, 2007
Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.
930 S.W.2d 877 (Court of Appeals of Texas, 1996)
Boy Scouts of America v. Responsive Terminal Systems, Inc.
790 S.W.2d 738 (Court of Appeals of Texas, 1990)
Dobbins v. Redden
785 S.W.2d 377 (Texas Supreme Court, 1990)
Harris v. Harris
765 S.W.2d 798 (Court of Appeals of Texas, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
759 S.W.2d 477, 1988 Tex. App. LEXIS 2811, 1988 WL 120273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dobbins-v-redden-texapp-1988.