Lapp-Gifford Co. v. Muscoy Water Co.

134 P. 989, 166 Cal. 25, 1913 Cal. LEXIS 279
CourtCalifornia Supreme Court
DecidedAugust 20, 1913
DocketL.A. No. 3416.
StatusPublished
Cited by31 cases

This text of 134 P. 989 (Lapp-Gifford Co. v. Muscoy Water Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lapp-Gifford Co. v. Muscoy Water Co., 134 P. 989, 166 Cal. 25, 1913 Cal. LEXIS 279 (Cal. 1913).

Opinion

THE COURT.

This cause comes here on an order of transfer following a judgment of affirmance in the district court of appeal ior the second appellate district. The facts are fully and correctly stated in the opinion of that court, and we were, at the time of ordering the transfer, and are now, of the view that there had been a correct disposition of all points presented except that relating to the plea of accord and satisfaction. We entertained some doubt on this point, but our further examination has convinced us that it, too, was rightly disposed of by the district court of appeal.

*27 The great weight of authority in American courts undoubtedly supports the rule that where the amount due is in dispute, and a check for an amount less than that claimed is sent to the creditor with a statement that it is sent in full satisfaction of the claim, and the tender is accompanied by such acts or declarations as amount to a condition that if the check is accepted at all it is accepted in full satisfaction of the disputed claim, and the creditor so understands, its acceptance by the creditor constitutes an accord and satisfaction, even though the creditor states at the time that the amount tendered is not accepted in full satisfaction. (Wald’s Pollock on Contracts, 3d ed., p. 839.) Whether there was a dispute concerning the amount due and whether the tender was on condition that acceptance would be in full satisfaction, are primarily questions of fact for the trial court. In the case at bar we think, notwithstanding an expression to the contrary by the district court of appeal, that it appears clearly enough that the amount due was in dispute at the .time of the acceptance and retention of the check.' But the evidence was such as to justify the finding (impliedly if not expressly made) that the tender was not subject to the condition that an acceptance of the check would be a satisfaction in full. This is an essential element of an accord and satisfaction by tender of a check. In the absence of such condition, the retention of the check, at least where the creditor promptly notifies the debtor that he still insists upon payment of the balance claimed, does not establish his assent to the acceptance of the sum tendered as a full settlement. (Hillestad v. Lee, 91 Minn. 335, [97 N. W. 1055] ; Fremont Foundry Co. v. Norton, 3 Neb. (Unof.) 804, [92 N. W. 1058]; Amer v. Folk, 28 Misc. Rep. 508, [59 N. Y. Supp. 532]; Eames Vac. Brake Co. v. Prosser, 157 N. Y. 289, [51 N. E. 986]; McKay v. Myers, 168 Mass. 312, [47 N. E. 98]; Boston Rubber Co. v. Peerless Wringer Co., 58 Vt. 551, [5 Atl. 407]; Van Dyke v. Wilder, 66 Vt. 579, [29 Atl. 1016].) The defendant’s letter inclosing its check for $816.26, stated that it was the amount due “as final payment for work on pipe-line, . . . less a deduction of $970.20 for 47 days time of our engineer and crew. This deduction was made on account of delay in completing the pipe-line. ’ ’ The letter did not state, in clear and unequivocal terms, that the sum tendered was offered as a *28 full settlement. The term “final payment” may reasonably be construed to refer to the, twenty-five per cent, which, under the contract, was to be paid thirty-six days after “the acceptance and final completion of this contract.” Indeed, this is the more natural interpretation of the letter, in view of the fact that it speaks of the amount of the check as being the “final payment, less a deduction.” In other words, the expression “final payment” is applied, not to the balance remaining after the deduction, but to the entire sum claimed, the amount tendered being reached by subtracting $970.20 from this “final payment.” The check itself contained nothing to indicate that it was intended to operate as a payment in full. Accompanying the letter and the cheek was a statement itemizing the defendant’s. claim for damages. This statement added nothing to the letter. It was merely a more specific declaration of the grounds upon which the right to a deduction was asserted. (See Fremont Foundry Co. v. Norton, 3 Neb. (Unof.) 804, [92 N. W. 1058].) Upon the whole case, it was certainly open to the court to find that there had not been such meeting of minds as to constitute an accord and satisfaction, and, while we do not say that a finding to the contrary would be without support, the finding made cannot be said to be contrary to the evidence.

The judgment is, accordingly, affirmed.

The opinion of the district court of appeal, above referred to, is as follows:

“The action was one to recover a balance due upon a contract dated March 20, 1909, alleged to have been entered into between defendant, party of the first part, and plaintiff of the second part, through which the second party agreed to furnish all the materials and construct a pipe-line upon a certain designated location shown by a map attached. The pipe-line exceeded two miles in length, the head of which was in and traversed a portion of the government reservation, and near the foot thereof the same was shown to cross the right of way of the Sante Fe Railroad. The contract provided that the work should be commenced within ten days after the first party shall have procured a permit to construct such pipeline through the reservation, and should be completed within thirty days thereafter. Partial payments were provided for, upon an engineer’s estimate, during the progress of the work, *29 and twenty-five per cent of the contract price was to he retained as a final payment until thirty-six days after completion. It is averred that on March 24th notice was given of the issuance of a permit to construct the line across the public lands, and work was commenced April second and prosecuted with due diligence; that shortly after the commencement of the work the defendant entered into negotiations with the railroad company for permission to construct its pipe-line across the right of way of the railroad, and notified plaintiff that certain restrictions relative to a cement culvert were imposed by the railroad company as a condition precedent to crossing such right of way, and that it would require sixty days’ time to construct such culvert; that defendant notified plaintiff that while time was of the essence of the contract it need not hurry with the work, only to the extent of having the line completed to the right of way by the time that defendant had completed its cement culvert; that plaintiff had completed its work up to the line of the right of way by the time defendant had commenced work on its culvert; that the culvert was not completed until the first of July; that on the second of July plaintiff proceeded to and did complete the construction of the pipe-line and the same was inspected- and accepted by defendant on July 8th. Defendant made all payments, other than the completion payment, provided for in the contract, but on August 14, 1909, a balance of $1786.46 was unpaid upon such completion payment; that of such sum defendant had only paid $816.26, and a balance of $970.20 remained unpaid, for which plaintiff asked judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kurtin v. Elieff
California Court of Appeal, 2013
Coac, Inc. v. Kennedy Engineers
67 Cal. App. 3d 916 (California Court of Appeal, 1977)
Petroleum Collections Inc. v. Sulser
265 Cal. App. Supp. 2d 976 (Appellate Division of the Superior Court of California, 1968)
Conderback, Inc. v. Standard Oil Co.
239 Cal. App. 2d 664 (California Court of Appeal, 1966)
Dietl v. Heisler
188 Cal. App. 2d 358 (California Court of Appeal, 1961)
Rankin v. Miller
179 Cal. App. 2d 133 (California Court of Appeal, 1960)
Wilmeth v. Lee
1957 OK 232 (Supreme Court of Oklahoma, 1957)
Mainieri v. Magnuson
272 P.2d 557 (California Court of Appeal, 1954)
Potter v. Pacific Coast Lumber Co.
234 P.2d 16 (California Supreme Court, 1951)
D. E. Sanford Co. v. Cory Glass Coffee Brewer Co.
194 P.2d 127 (California Court of Appeal, 1948)
Owens v. Noble
175 P.2d 241 (California Court of Appeal, 1946)
Biaggi v. Sawyer
170 P.2d 678 (California Court of Appeal, 1946)
Robertson v. Robertson
93 P.2d 175 (California Court of Appeal, 1939)
Coats v. General Motors Corp.
39 P.2d 838 (California Court of Appeal, 1934)
Messer v. Tait's, Inc.
9 P.2d 536 (California Court of Appeal, 1932)
Everhardy v. Union Finance Co.
1 P.2d 1024 (California Court of Appeal, 1931)
F. J. Lewis Mfg. Co v. Snyder
37 F.2d 299 (Sixth Circuit, 1930)
Work v. Associated Almond Growers of Paso Robles
282 P. 965 (California Court of Appeal, 1929)
Shortell v. Evans-Ferguson Corp.
277 P. 519 (California Court of Appeal, 1929)
Russell v. Riley & Peterson
256 P. 557 (California Court of Appeal, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
134 P. 989, 166 Cal. 25, 1913 Cal. LEXIS 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lapp-gifford-co-v-muscoy-water-co-cal-1913.