Coac, Inc. v. Kennedy Engineers

67 Cal. App. 3d 916, 136 Cal. Rptr. 890, 1977 Cal. App. LEXIS 1285
CourtCalifornia Court of Appeal
DecidedMarch 9, 1977
DocketCiv. 38987
StatusPublished
Cited by15 cases

This text of 67 Cal. App. 3d 916 (Coac, Inc. v. Kennedy Engineers) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coac, Inc. v. Kennedy Engineers, 67 Cal. App. 3d 916, 136 Cal. Rptr. 890, 1977 Cal. App. LEXIS 1285 (Cal. Ct. App. 1977).

Opinion

Opinion

GOOD, J. *

COAC, Inc. (appellant) filed its complaint against Kennedy Engineers (respondents) alleging that appellant was the successful bidder and had entered into a written contract with Coastside County Water District (District) for the construction of a water treatment plant known as Denniston Creek Project—Phase I; that a few months before the contract’s award, District had executed a contract with respondents for the preparation of engineering plans and specifications as well as an environmental impact report (EIR) for the project; that respondents breached said contract with District, “which contract was for the benefit of [appellant], by failing to prepare and provide” an EIR; and, that by reason of such breach appellant was damaged by a 65-day delay in construction. A second cause of action alleges that when appellant thereafter furnished the EIR it was defective and did not comply with the requirements of the California Environmental Quality Act (CEQA), and, that appellant was again forced to suspend construction for 163 days. Respondents demurred generally and upon the ground of uncertainty because there was no allegation of whether the contract sued upon was express or implied or whether it was written or oral. The general *919 demurrer was sustained without leave to amend. Judgment of dismissal was entered and this appeal ensued.

Where a general demurrer to a complaint is sustained without leave to amend “the issues presented are whether the complaint states a cause of action, and if not, whether there is a reasonable possibility that it could be amended to do so.” (MacLeod v. Tribune Publishing Co. (1959) 52 Cal.2d 536, 542 [343 P.2d 36].) Appellant has attached to its opening brief a proposed amended complaint which amplifies the substance of the complaint filed and alleges that the contract between respondents and District was “expressly” for the benefit of appellant; that appellant had relied thereon in preparing its bid and further relied on respondents’ continuing expertise in the engineering services and supervision that respondents were required to furnish during the course of construction to the end that “all the plans, specifications, environmental impact reports . . . were properly prepared and all clearances and permits obtained and in order” so that appellant, as general contractor, could perform its contract in a timely manner without hindrance or delay.

It is not important that the original complaint failed to use the word express in reciting that the respondent-District contract was for its benefit. The proposed amendment shows that it could have easily been amended so as to bring appellant under Civil Code section 1559 which reads: “A contract, made expressly for the benefit of a third person, may be enforced by him at any time before the parties thereto rescind it.” Martinez v. Socoma Companies, Inc. (1974) 11 Cal.3d 394, at page 400 [113 Cal.Rptr. 585, 521 P.2d 841], states: “This section excludes enforcement of a contract by persons who are only incidentally or remotely benefited by it. [Citation.] American law generally classifies persons having enforceable rights under contracts to which they are not parties as either creditor beneficiaries or donee beneficiaries.” Section 133 of the Restatement of Contracts is cited for its definitions of donee, creditor and incidental beneficiaries. A creditor beneficiary status arises “if no purpose to make a gift appears from the terms of the promise in view of the accompanying circumstances and performance of the promise will satisfy an actual or supposed or asserted duty of the promisee to the beneficiary. . . .” Martinez further says: “A person cannot be a creditor beneficiary unless the . . . contract will discharge some form of legal duty owed to the beneficiary by the promisee.” (Rest., Contracts, § 133, subd. (1)(b); Hartman Ranch Co. v. Associated Oil Co. (1937) 10 Cal.2d 232, 244 [73 P.2d 1163]; R. J. Cardinal Co. v. Ritchie *920 (1963) 218 Cal.App.2d 124, 135-136 [32 Cal.Rptr. 545].) But it is not necessary that the contract be exclusively for the benefit of the third party to give him a right thereunder nor that he be named and identified as an individual. (Ralph C. Sutro Co. v. Paramount Plastering, Inc. (1963) 216 Cal.App.2d 433, 437 [31 Cal.Rptr. 174].)

Upon the complaint before us, whether or not appellant is a creditor beneficiary of the contract as alleged between District and respondents depends upon the District’s duties to appellant under the construction contract. Under that contract, District owed appellant a legal duty not to hinder, delay, interfere with or prevent his performance. (Gray v. Bekins (1921) 186 Cal. 389, 394 [199 P. 767]; Tanner v. Title Ins. & Trust Co. (1942) 20 Cal.2d 814, 825 [129 P.2d 383]; 5 Williston on Contracts (3d ed.) § 677, p. 224.) For construction contract cases wherein derelictions of an owner have prevented full performance or made it impossible to complete construction within the time specified in the contract and the contractor was allowed full recovery, we need cite only Lowy v. United Pacific Ins. Co. (1967) 67 Cal.2d 87 [60 Cal.Rptr. 225, 429 P.2d 577]; E. H. Morrill Co. v. State of California (1967) 65 Cal.2d 787 [56 Cal.Rptr. 479, 423 P.2d 551]; and Lapp-Gifford Co. v. Muscoy Water Co. (1913) 166 Cal. 25 [134 P. 989]. The latter case involved the construction of a pipeline across a government reservation and a railroad right-ofrway. Construction was delayed for 47 days because of complications that arose when the owner attempted to secure the railroad’s permission to cross the right-of-way. The owner attempted to deduct for this delay. The appellate opinion adopted by the Supreme Court said at page 30 (166 Cal.): “No duty devolved upon plaintiff [contractor], in the absence of an express agreement, to procure the right to cross the railroad [property]____ Immediately upon the performance by defendant [owner] of the implied covenant upon its part [to secure the railroad’s permission]; plaintiff proceeded to a completion of the contract.”

In general, where plans, specifications and conditions of contract do not otherwise provide, there is an implied covenant that the owner of the project is required to furnish whatever easements, permits or other documentation are reasonably required for the construction to proceed in an orderly manner. In Visintine & Co. v. New York, Chicago & St. Louis R. Co. (1959) 169 Ohio St. 505 [160 N.E.2d 311], the plaintiff construction company had a contract with the State of Ohio involving a project of railroad grade crossing elimination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berger Foundation v. Perez
California Court of Appeal, 2013
H.N. & Frances C. Berger Foundation v. Perez
218 Cal. App. 4th 37 (California Court of Appeal, 2013)
Lake Almanor Associates L.P. v. Huffman-Broadway Group, Inc.
178 Cal. App. 4th 1194 (California Court of Appeal, 2009)
Superior Gunite v. Ralph Mitzel Inc.
12 Cal. Rptr. 3d 423 (California Court of Appeal, 2004)
Johnson v. Superior Court
95 Cal. Rptr. 2d 864 (California Court of Appeal, 2000)
Mariani v. Price Waterhouse
82 Cal. Rptr. 2d 671 (California Court of Appeal, 1999)
MISSION OAKS v. County of Santa Barbara
77 Cal. Rptr. 2d 1 (California Court of Appeal, 1998)
Mission Oaks Ranch, Ltd. v. County of Santa Barbara
65 Cal. App. 4th 713 (California Court of Appeal, 1998)
Alling v. Universal Manufacturing Corp.
5 Cal. App. 4th 1412 (California Court of Appeal, 1992)
Technicable Video Sys. v. Americable
479 So. 2d 810 (District Court of Appeal of Florida, 1985)
Shurpin v. Elmhirst
148 Cal. App. 3d 94 (California Court of Appeal, 1983)
Friends Of" B" Street v. City of Hayward
106 Cal. App. 3d 988 (California Court of Appeal, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
67 Cal. App. 3d 916, 136 Cal. Rptr. 890, 1977 Cal. App. LEXIS 1285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coac-inc-v-kennedy-engineers-calctapp-1977.