Superior Gunite v. Ralph Mitzel Inc.

12 Cal. Rptr. 3d 423, 117 Cal. App. 4th 301, 2004 Daily Journal DAR 3966, 2004 Cal. Daily Op. Serv. 2759, 2004 Cal. App. LEXIS 419
CourtCalifornia Court of Appeal
DecidedMarch 30, 2004
DocketB158824
StatusPublished
Cited by5 cases

This text of 12 Cal. Rptr. 3d 423 (Superior Gunite v. Ralph Mitzel Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Superior Gunite v. Ralph Mitzel Inc., 12 Cal. Rptr. 3d 423, 117 Cal. App. 4th 301, 2004 Daily Journal DAR 3966, 2004 Cal. Daily Op. Serv. 2759, 2004 Cal. App. LEXIS 419 (Cal. Ct. App. 2004).

Opinion

Opinion

MOSK, J.

INTRODUCTION

Defendant and appellant Ralph Mitzel Inc. (Mitzel), a general contractor, appeals from a judgment after a court trial awarding its sub-subcontractor, plaintiff and respondent Superior Gunite (Superior), $413,177 in damages for breach of contract and negligence, $299,000 in attorney fees, $45,334 in prejudgment interest and $85,000 in costs. The court awarded Superior damages for its claim of Mitzel’s negligence and for claims assigned to Superior by Mitzel’s subcontractor, Pinnacle Concrete Construction (Pinnacle). Superior had entered into a sub-subcontract with Pinnacle and had no *304 contractual privity with Mitzel. Pinnacle’s breach of contract claim assigned to Superior consisted of two elements: (i) Pinnacle’s claim for breach of the Mitzel-Pinnacle subcontract by Mitzel resulting in $7,015 in damages; and (ii) Superior’s claim for $406,163 in labor cost overruns caused by Mitzel’s acts and omissions.

Mitzel does not challenge the negligence award in favor of Superior, except as to the calculation of damages. The trial court used the same methodology to calculate Superior’s labor cost overrun damages at $406,163 under both the contract claim and the negligence claim. Mitzel contends that Superior lacks privity with Mitzel and that there was no justification for the $406,163 in damages to Superior for a breach of contract claim. These contentions bear on whether Superior is entitled to interest on, and attorney fees attributable to, the $406,163 award, but do not affect the compensatory award of $406,163 based on negligence, which we affirm.

In the published portion of this opinion, we hold that the trial court’s conclusion based on a contract claim by Superior against Mitzel was incorrect because they were not in privity. At the close of evidence the trial court dismissed as not proven a claim that Pinnacle had the right to assert Superior’s claim on a “pass-through” theory, which theory, if applicable, could justify a circumvention of the privity requirement. Superior, the assignee of Pinnacle’s claims, failed to challenge this dismissal. Under the trial court’s rationale, the only contractual claim that Pinnacle could and did assign to Superior was Pinnacle’s claim against Mitzel for $7,015 for breach of the Pinnacle-Mitzel subcontract, and we affirm that award. Thus, Superior is entitled to contractual interest and attorney fees only on the $7,015 award and not on the $406,163 award. We remand the matter to the trial court to determine how much interest, if any, should be awarded with respect to the $406,163 negligence award and to assess attorney fees in connection with the $7,015 award.

In the unpublished portion of this opinion, we hold that the trial court’s judgment is not inconsistent with its earlier summary adjudication of issues; that the trial court did not err in the methodology used to compute damages; that the damages were supported by substantial evidence; that the statement of decision was legally adequate; and that there were no evidentiary errors.

BACKGROUND 1

Mitzel contracted with the Pomona School District to perform foundation work and grading at the Diamond Ranch High School in the City of Pomona *305 for $11,146,270 and served as the general contractor on this project. Mitzel subcontracted the structural concrete work for the project to Pinnacle for a contract price of $1,968,875. Under the terms of its subcontract, Pinnacle was responsible for constructing a retaining wall and various concrete flatwork. As the general contractor for the project, Mitzel was responsible for providing access and power to the site.

Pinnacle expected to commence its work on the project in February 1996 and began mobilizing on the site at that time. Mitzel’s acts precluded Pinnacle from commencing work until June or July 1996. During this time, Pinnacle experienced financial difficulties that caused it to seek help in fulfilling its contractual obligations. Pinnacle eventually filed a petition in bankruptcy.

Pinnacle first sought to have another concrete subcontractor take over Pinnacle’s subcontract with Mitzel. Mitzel, however, refused to allow the substitution. Pinnacle then proposed to enter into a joint venture with Superior to complete the work. Mitzel would not permit a joint venture, in part because doing so would cause it to be in violation of the minority-owned business requirements of Mitzel’s contract with the Pomona School District. With Mitzel’s knowledge and consent, Pinnacle then entered into a subcontract with Superior for Superior to construct the foundation and retaining wall (referred to as “Bid item No. 20”). Pinnacle retained the obligation to perform the concrete flatwork (referred to as “Bid item No. 21”). Superior completed all of the work for the project, including the concrete flatwork covered by Bid item No. 21, even though the flatwork was not expressly covered by its written contract with Pinnacle; there was evidence of an understanding among Pinnacle, Mitzel and Superior for Superior to do this work.

Superior encountered conditions caused by Mitzel that made its construction work more difficult and time-consuming than anticipated. These conditions included uncommunicated changes to the project; inadequate staffing; improper scheduling; requiring construction out of the planned sequence; failing to provide access to the site; the presence of a haul road used by Mitzel to transport dirt and gravel through the area where the retaining wall was to be constructed; the absence of temporary power in Superior’s construction site; stockpiling of soil by Mitzel in a location that hindered construction; and insufficient site drainage that hampered site access during wet weather. Superior claimed that these conditions caused it to incur damages that consisted primarily of labor cost overruns.

Superior filed a complaint against Pinnacle, Mitzel and the Pomona School District, asserting causes of action for breach of contract, unjust enrichment, *306 negligence and negligent interference with economic relationship. Superior dismissed with prejudice its complaint against the Pomona School District and elected not to pursue its claim against Pinnacle. 2 Superior and Pinnacle entered into a Claim Consolidation and Assignment Agreement (assignment agreement) that provided as follows: “In consideration of Superior Gunite’s agreement to assert the rights of Pinnacle against Ralph D. Mitzel, including any and all pass-through claims of Superior Gunite against Ralph D. Mitzel, Pinnacle hereby sells, transfers and assigns to Superior the right, title and interest in all claims held by Pinnacle, or which may be asserted by Pinnacle, including the rights of Superior Gunite against Ralph D. Mitzel on a pass through basis as a subcontractor to Pinnacle. Pinnacle hereby grants to Superior Gunite full power to collect, sue for (either in its own or Superior’s name), compromise, or in any other manner enforce the rights to the above-described claims of Pinnacle and Superior Gunite in Superior Gunite’s name or otherwise. Pinnacle shall cooperate and assist Superior in any reasonable manner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Visa Inc. v. Sally Beauty Holdings, Inc.
Court of Appeals of Texas, 2021
People v. Sanders CA2/7
California Court of Appeal, 2016
People v. Nelson CA2/7
California Court of Appeal, 2016
Pringle v. Water Quality Insurance Syndicate
646 F. Supp. 2d 1161 (C.D. California, 2009)
Green Wood Industrial Co. v. Forceman International Development Group, Inc.
67 Cal. Rptr. 3d 624 (California Court of Appeal, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
12 Cal. Rptr. 3d 423, 117 Cal. App. 4th 301, 2004 Daily Journal DAR 3966, 2004 Cal. Daily Op. Serv. 2759, 2004 Cal. App. LEXIS 419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/superior-gunite-v-ralph-mitzel-inc-calctapp-2004.