D. A. Parrish & Sons v. County Sanitation District Number 4

344 P.2d 883, 174 Cal. App. 2d 406, 1959 Cal. App. LEXIS 1714
CourtCalifornia Court of Appeal
DecidedOctober 13, 1959
DocketCiv. 18228
StatusPublished
Cited by22 cases

This text of 344 P.2d 883 (D. A. Parrish & Sons v. County Sanitation District Number 4) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. A. Parrish & Sons v. County Sanitation District Number 4, 344 P.2d 883, 174 Cal. App. 2d 406, 1959 Cal. App. LEXIS 1714 (Cal. Ct. App. 1959).

Opinion

TOBRINER, J.

We find no merit in appellant’s claim of error in the trial court’s- award to a contractor of damages for breach of contract covering installation of sewer pipe, upon any of the three suggested grounds: that the evidence does not support the judgment, that two subcontractors should not have been joined as plaintiffs, and that the findings and judgment should have been in the form urged by appellant.

The case arises from breach of contract. Respondent contracted to install main and lateral sewer pipe; appellant in turn promised to provide rights of way upon which the work was to be done. Indeed the standard practice in the industry is that easements be ready when a contractor is to lay pipe. Finding in the latter part of September, 1952, that matters beyond its control would prevent its meeting its deadline, respondent subcontracted, upon the written consent of appellant, portions of the job to Bryan B. Wall and B. Miles Thomas Company. On January 29, 1953, appellant’s chief project engineer reported to its board of directors that respondent had diligently and satisfactorily prosecuted the work.

After a trial without a jury the court found appellant failed to perform its obligation to provide rights of way prerequisite to the performance of respondent’s work, and, as a result of that failure, granted respondent D. A. Parrish and *410 Sons a judgment of $40,323.49 against appellant; Bryan B. Wall, a judgment of $4,080.22 against respondent; and B. Miles Thomas Company, a judgment of $3,304.67 against respondent. The court provided that the latter two judgments be conditional upon respondent’s collecting its judgment from appellant.

We consider each of appellant’s triple grounds of appeal under separate headings :

1. The sufficiency of the evidence.

Appellant urges five contentions in this respect: (1) the contract did not require appellant to provide easements; (2) appellant did not in any event breach such a duty, even if it existed; (3) respondent proved no damages; (4) respondent failed to give the notices required by the contract as to any claims for damages; and (5) appellant did not wrongfully deduct engineering or inspection fees. We proceed to point out why appellant’s contentions cannot be upheld.

First. Was appellant’s duty to provide easements sufficiently established? As we have stated, both appellant’s contract and the standard practice in the industry so provided. Although the contract did not specify the precise time appellant was to have the rights of way ready, Civil Code, section 1657, cited by appellant, establishes that if the time of performance is not specified in a contract, the courts will imply a reasonable time. A reasonable time must be determined by “the situation of the parties, the nature of the transaction and the circumstances of the particular ease. ...” (Kersch v. Taber (1945), 67 Cal.App.2d 499, 506 [154 P.2d 934].) Moreover, the contract carried a deadline of 120 days for completion of the job. Therefore, the court properly found that appellant faced the obligation of promptly obtaining easements in order that Parrish could expeditiously lay pipe.

Second. Did appellant breach its duty? Appellant analyzes in detail each item of damage found for the three respondents, and we are therefore compelled to a factual analysis to dispose of a plea that in substance asks this appellate court to retry the ease.

Parrish Claim Number 1. (City Park-Raiseh Easement.)

Because it was the most difficult portion of the job, respondent informed appellant that respondent would first *411 start work here. After obtaining permission of appellant’s engineer, respondent began benching operations, consisting of leveling the land for staking out the line for pipe, in the City Park area of the job. When appellant demanded wider benching than was originally undertaken, respondent sent out a bulldozer, only to be then told by appellant to cease operations totally because the city of Los Gatos objected.

When respondent found itself unable to do the work in City Park, which is the lower part of the canyon, it attempted to work the Raisch property and moved some equipment to this location. Upon commencing operations, respondent notified Raisch Company that the road used by its trucks was about to be cut. Immediately thereafter appellant’s engineers ordered respondent to cease operations on the company’s property.

Some two months later appellant cleared the easement across the property but directed respondent not to proceed for over one month because of the possibility of establishing a cheaper alternate route. When appellant finally told respondent to proceed on the City Park job, it was raining. The rain, besides slowing down construction, required respondent to use rock in the trench bottoms to stabilize the base for laying the pipe.

Respondent claimed damages of $28,179.79, attributable to this fiasco. Respondent adduced testimony as to damages based upon actual extra labor costs, equipment standing idle, supervision and overhead, plus inspection and engineering fees withheld by appellant.

Appellant merely reargues the evidence. It also alleges that the Health and Safety Code, section 4759, gave appellant a right of way across any public property, i.e., City Park of Los Gatos. However, appellant thus does no more than establish a conflict in the evidence since appellant was coincidentally negotiating with Los Gatos for an easement and respondent had actually been ordered from the park property. The point adds nothing to appellant’s position.

Parrish Claim- Number 2.

Prior to starting work on San Tomas Road, respondent had obtained maps from the San Jose Water Works, but these maps did not indicate that there was a water main in the center of the street; nor did the engineering plans furnished by appellant indicate this pipe.

*412 Upon digging along the center of San Tomas Road respondent hit the water main. Appellant’s inspector then told respondent to halt operations; appellant’s engineers informed respondent that a new course would have to be laid out, and meanwhile ordered respondent to move to another location to enable appellant to obtain an easement along the side of the road. Prom San Tomas Road respondent moved to Bruce Street, approximately one block away. Claim Number 2, for $426.77, was limited to the expenses incident to making this extra move. Ample testimony supported the costs involved in making such a move.

Appellant argues that the contract provided that the 11 Contractor shall notify the utility companies before proceeding with construction and should familiarize himself with the location of underground pipes, ducts or manholes. The location of the utilities where shown on the plans are approximate only and are not to be taken as final,” and hence no allowance should be made for the move by Parrish.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Visa Inc. v. Sally Beauty Holdings, Inc.
Court of Appeals of Texas, 2021
FTR Internat., Inc. v. Rio School Dist.
California Court of Appeal, 2015
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Superior Gunite v. Ralph Mitzel Inc.
12 Cal. Rptr. 3d 423 (California Court of Appeal, 2004)
Alamo Community College District v. Browning Construction Co.
131 S.W.3d 146 (Court of Appeals of Texas, 2004)
Sehulster Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp.
4 Cal. Rptr. 3d 655 (California Court of Appeal, 2003)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
Amelco Electric v. City of Thousand Oaks
98 Cal. Rptr. 2d 159 (California Court of Appeal, 2000)
Howard Contracting, Inc. v. G.A. MacDonald Construction Co.
83 Cal. Rptr. 2d 590 (California Court of Appeal, 1999)
Frank Briscoe Co., Inc. v. County of Clark
772 F. Supp. 513 (D. Nevada, 1991)
Farrell Construction Co. v. Jefferson Parish
693 F. Supp. 490 (E.D. Louisiana, 1988)
Walton v. Guinn
187 Cal. App. 3d 1354 (California Court of Appeal, 1986)
Board of County Commissioners v. CAM Construction Co.
480 A.2d 795 (Court of Appeals of Maryland, 1984)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Bilardi Construction, Inc. v. Spencer
6 Cal. App. 3d 771 (California Court of Appeal, 1970)
Shelly v. Hansen
244 Cal. App. 2d 210 (California Court of Appeal, 1966)
Ace Stone, Inc. v. Township of Wayne
221 A.2d 515 (Supreme Court of New Jersey, 1966)
People v. Lopez
384 P.2d 16 (California Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
344 P.2d 883, 174 Cal. App. 2d 406, 1959 Cal. App. LEXIS 1714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-a-parrish-sons-v-county-sanitation-district-number-4-calctapp-1959.