FTR Internat., Inc. v. Rio School Dist.

CourtCalifornia Court of Appeal
DecidedJanuary 27, 2015
DocketB238618
StatusPublished

This text of FTR Internat., Inc. v. Rio School Dist. (FTR Internat., Inc. v. Rio School Dist.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FTR Internat., Inc. v. Rio School Dist., (Cal. Ct. App. 2015).

Opinion

Filed 1/27/15

CERTIFIED FOR PARTIAL PUBLICATION*

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION SIX

FTR INTERNATIONAL, INC., 2d Civil No. B238618 (Super. Ct. Nos. CIV201015, 01CC05901, Plaintiff and Respondent, 01HL05281, 204779, 205936, 207742, 207744, 207994, 208016, 223403) v. (Ventura County)

RIO SCHOOL DISTRICT,

Defendant and Appellant;

EAST WEST BANK,

Intervener and Respondent.

Public Contract Code section 7107 (section 7107) allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. Here we conclude that a dispute over the contract price does not entitle a public entity to withhold funds due a contractor. We disagree with Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 (Martin Brothers), which holds otherwise. We also conclude the doctrine of unclean hands does not apply to section 7107.

* Pursuant to California Rules of Court, rules 8.1105(b) and 8.1110, this opinion is certified for partial publication. The portions of this opinion to be deleted from publication are identified as those portions between double brackets, e.g., [[/]]. This case arises from a contract for the construction of a school. After the school was completed, the school district and its general contractor engaged in a decade-long legal battle. The result was a judgment for the contractor FTR International, Inc. (FTR) against the Rio School District (District) exceeding $9 million. District appeals. We conclude: the trial court properly assessed penalties against District because it did not timely release retained funds required by section 7107; [[the trial court properly rejected District's action under the False Claims Act (FCA) Government Code1 section 12650 et seq.; the trial court properly assessed prejudgment interest, subject to adjustment for any extra work claims found untimely on remand.]] We also conclude: [[the trial court erred in its interpretation of a contract provision imposing time limitations to submit the contractor's claims for extra work as requiring a showing of prejudice; and]] the trial court erred in awarding fees for work not solely related to FTR's cause of action pursuant to section 7107. We reverse and remand with instructions in the instances where the trial court erred and affirm in all other respects. FACTS FTR has constructed buildings for public entities, including schools, courthouses and libraries for 15 years. In 1999, FTR submitted the winning bid in the amount of $7.345 million to construct a school for District. During construction, FTR submitted approximately 150 proposed change orders (PCO). FTR claimed some of the PCOs were necessary because the plans provided by District were inadequate or misleading. District denied most of the PCOs on the grounds that the work was covered under the basic contract, the amounts claimed were excessive or that a PCO was not timely under the contract. The construction was completed in June 2001. District filed a notice of completion on August 7, 2001. The school has been occupied since May 2001.

1 All statutory references are to the Government Code unless stated otherwise.

2 Pursuant to the contract, District retained 10 percent of each progress payment. At the completion of the work, District held a reserve of $676,436.49. That amount, however, was subject to stop notices filed by FTR's subcontractors. The last of the stop notices was released on September 28, 2004. District refused to pay the balance due under the contract, refused to pay any but a small portion of the amounts claimed by FTR in its PCOs, refused to release any of the retention and refused to compensate FTR for damages allegedly caused by delay and disruption. FTR sued District to recover damages for breach of contract, 2 statutory penalties under section 7107 , attorney fees, interest and costs. District filed a

2 Section 7107 states: "a) This section is applicable with respect to all contracts entered into on or after January 1, 1993, relating to the construction of any public work of improvement. [¶] (b) The retention proceeds withheld from any payment by the public entity from the original contractor, or by the original contractor from any subcontractor, shall be subject to this section. [¶] (c) Within 60 days after the date of completion of the work of improvement, the retention withheld by the public entity shall be released. In the event of a dispute between the public entity and the original contractor, the public entity may withhold from the final payment an amount not to exceed 150 percent of the disputed amount. For purposes of this subdivision, 'completion' means any of the following: [¶] (1) The occupation, beneficial use, and enjoyment of a work of improvement, excluding any operation only for testing, startup, or commissioning, by the public agency, or its agent, accompanied by cessation of labor on the work of improvement. [¶] (2) The acceptance by the public agency, or its agent, of the work of improvement. [¶] (3) After the commencement of a work of improvement, a cessation of labor on the work of improvement for a continuous period of 100 days or more, due to factors beyond the control of the contractor. [¶] (4) After the commencement of a work of improvement, a cessation of labor on the work of improvement for a continuous period of 30 days or more, if the public agency files for record a notice of cessation or a notice of completion. [¶] (d) Subject to subdivision (e), within seven days from the time that all or any portion of the retention proceeds are received by the original contractor, the original contractor shall pay each of its subcontractors from whom retention has been withheld, each subcontractor's share of the retention received. However, if a retention payment received by the original contractor is specifically designated for a particular subcontractor, payment of the retention shall be made to the designated subcontractor, if the payment is consistent with the terms of the subcontract. [¶] (e) The original contractor may withhold from a subcontractor its portion of the retention proceeds if a bona fide dispute exists between the subcontractor and the original contractor. The amount withheld from the retention payment shall not exceed 150 percent of the

3 separate action seeking damages for 416 alleged violations of the FCA (§ 12650 et seq.). [[FTR cross-complained in that action alleging District violated the Federal Civil Rights Act (42 U.S.C.A. § 1981). All the actions were consolidated by the trial court.]] After a 243-day court trial, the trial court found in favor of FTR. It awarded $9,356,124.81 to FTR, which includes damages for the balance due under the contract, extra work performed by FTR, delay and disruption caused by District, statutory penalties pursuant to section 7107, attorney fees, prejudgment interest and costs.3 DISCUSSION Section 7107 Penalties District contends the trial court erred in awarding penalties under section 7107. Subdivision (c) of this section provides, in part: "Within 60 days after the date of completion of the work of improvement, the retention withheld by the public entity shall be released. In the event of a dispute between the public entity and the original

estimated value of the disputed amount. [¶] (f) In the event that retention payments are not made within the time periods required by this section, the public entity or original contractor withholding the unpaid amounts shall be subject to a charge of 2 percent per month on the improperly withheld amount, in lieu of any interest otherwise due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D. A. Parrish & Sons v. County Sanitation District Number 4
344 P.2d 883 (California Court of Appeal, 1959)
Serrano v. Priest
569 P.2d 1303 (California Supreme Court, 1977)
Reynolds Metals Co. v. Alperson
599 P.2d 83 (California Supreme Court, 1979)
Booth v. Robinson
147 Cal. App. 3d 371 (California Court of Appeal, 1983)
Polster, Inc. v. Swing
164 Cal. App. 3d 427 (California Court of Appeal, 1985)
In Re Brandie W.
157 Cal. App. 3d 110 (California Court of Appeal, 1984)
Fed-Mart Corp. v. Pell Enterprises, Inc.
111 Cal. App. 3d 215 (California Court of Appeal, 1980)
Bentz Plumbing & Heating v. Favaloro
128 Cal. App. 3d 145 (California Court of Appeal, 1982)
Blain v. Doctor's Co.
222 Cal. App. 3d 1048 (California Court of Appeal, 1990)
Mendoza v. Ruesga
169 Cal. App. 4th 270 (California Court of Appeal, 2008)
Crosstalk Productions, Inc. v. Jacobson
76 Cal. Rptr. 2d 615 (California Court of Appeal, 1998)
Unilogic, Inc. v. Burroughs Corp.
10 Cal. App. 4th 612 (California Court of Appeal, 1992)
Yassin v. Solis
184 Cal. App. 4th 524 (California Court of Appeal, 2010)
Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc.
179 Cal. App. 4th 1401 (California Court of Appeal, 2009)
Ticconi v. Blue Shield of California Life & Health Insurance
72 Cal. Rptr. 3d 888 (California Court of Appeal, 2008)
Thompson Pacific Construction Inc. v. City of Sunnyvale
66 Cal. Rptr. 3d 175 (California Court of Appeal, 2007)
S&S Cummins Corp. v. West Bay Builders, Inc.
71 Cal. Rptr. 3d 828 (California Court of Appeal, 2008)
Crestview Cemetery Ass'n v. Dieden
356 P.2d 171 (California Supreme Court, 1960)
Fassberg Construction Co. v. Housing Authority
152 Cal. App. 4th 720 (California Court of Appeal, 2007)
FEI Enterprises Inc. v. Yoon
194 Cal. App. 4th 790 (California Court of Appeal, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
FTR Internat., Inc. v. Rio School Dist., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ftr-internat-inc-v-rio-school-dist-calctapp-2015.