FEI Enterprises Inc. v. Yoon

194 Cal. App. 4th 790, 124 Cal. Rptr. 3d 64, 2011 Cal. App. LEXIS 482
California Court of Appeal·Decided April 25, 2011·No. No. B209862·Published·Cited by 43 cases

Opinion

Opinion

ALDRICH, J.

Owner Kee Man Yoon (Yoon) and general contractor Pacific Construction Co., a general partnership et al. (Pacific Construction), refused to pay the low-voltage electrical subcontractor FEI Enterprises, Inc. (FEI), for work performed under two subcontracts. FEI brought this action against Pacific Construction1 seeking, among other things, breach of contract damages and prompt payment penalties. Pacific Construction responded with a cross-complaint alleging that FEI had breached the subcontracts. The trial court entered judgment for FEI on both its complaint and on Pacific Construction’s cross-complaint. Pacific Construction appeals, contending the trial court erred in construing the subcontracts’ language. In the unpublished portion of this opinion, we conclude that the trial court did not err in its interpretation of the contractual provisions. We will therefore affirm the judgment.

FEI cross-appeals, contending that the trial court erred in declining to order Pacific Construction to pay prompt payment penalties. In the published portion of this opinion, we hold that the record contained evidence sufficient to support the trial court’s finding under Business and Professions Code section 7108.5, subdivision (c), that there was a “good faith dispute” between Pacific Construction and FEI as to the money owed. Determined by an objective standard, this justified Pacific Construction’s withholding of progress payments and the denial of the statutory prompt payment penalties. We will therefore also affirm the trial court’s order.

FACTUAL AND PROCEDURAL BACKGROUND2

Pacific Construction was the general contractor for two separate construction projects, a 19-unit residential building on Gramercy Drive and a seven-unit residential structure on Manhattan Place in Los Angeles (respectively, the [795] Gramercy Project and Manhattan Place Project). Defendant Jong Woon Kim was the owner of the Gramercy Project and Yoon was the owner of the Manhattan Place Project.

1.-3.*

4. The Trial Court’s Ruling

As is relevant here, the trial court ruled, with respect to both parties’ breach of contract claims, that FEI did not breach the subcontracts because FEI had completed 90 to 100 percent of the rough installation that fell within its scope of work. Further, FEI was excused from performing the remainder of the subcontracts’ work because Yoon terminated FBI’s contract. The court also ruled that FEI did not delay the projects because other trades were still performing their rough work after FEI finished. In addition, the court found that, although FEI had properly submitted its requests for payment to Pacific Construction, the latter had breached the subcontracts by failing to process FEI’s properly submitted payment requests. The trial court, however, denied FBI’s request for prompt payment penalties based upon its finding that a good faith dispute existed as to the sums owed. Pacific Construction appealed and FEI cross-appealed.

DISCUSSION

A. Pacific Construction’s Appeal*

B. PEPS Cross-appeal

1. The Prompt Payment Statutes

“California has a series of so-called ‘prompt payment’ statutes that require general contractors to pay their subcontractors within specified, short time periods, and that impose monetary penalties for violations.” (Tesco Controls, Inc. v. Monterey Mechanical Co. (2004) 124 Cal.App.4th 780, 800 [21 Cal.Rptr.3d 751] (Tesco Controls) [involving Bus. & Prof. Code, [796] § 7108.5 & Pub. Contract Code, § 7107; see also Civ. Code, § 3260].) These prompt payment statutes serve a “ ‘remedial purpose: to encourage general contractors to pay timely their subcontractors and to provide the subcontractor with a remedy in the event that the contractor violates the statute.’ [Citation.]” (S&S Cummins Corp. v. West Bay Builders, Inc. (2008) 159 Cal.App.4th 765, 777 [71 Cal.Rptr.3d 828].)

One such statute is Business and Professions Code section 7108.5,4 which requires a general contractor to pay its subcontractors their respective shares of a progress payment within 10 days of receiving that payment from the project’s owner, unless the parties agree otherwise in writing. If the general contractor fails to timely pay, the subcontractor may recover a penalty fixed at 2 percent of the amount due per month for every month the payment is not made. (Id., subd. (b); see also Civ. Code, § 32605 & Pub. Contract Code, § 7107.)6

[797] However, a contractor may withhold progress payments from a subcontractor without exposure to the 2 percent penalty if there is a good faith dispute between the general contractor and the subcontractor over the amount owed. Specifically, subdivision (c) of section 7108.5 provides that “[i]f there is a good faith dispute over all or any portion of the amount due on a progress payment from the prime contractor or subcontractor to a subcontractor, the prime contractor or subcontractor may withhold no more than 150 percent of the disputed amount.” (Italics added.) Thus, to deny penalties under this prompt payment statute, the trial court must conclude that the parties had a “good faith dispute” over amounts due on a progress payment. (Alpha Mechanical, Heating & Air Conditioning, Inc. v. Travelers Casualty & Surety Co. of America (2005) 133 Cal.App.4th 1319, 1339 [35 Cal.Rptr.3d 496] (Alpha Mechanical).)

2. Proper Interpretation of the Term “Good Faith Dispute ”

The problem is that the statute does not define the term “good faith dispute” and the parties disagree as to how it is to be interpreted. FEI contends that an objective standard should be applied while Pacific Construction argues that the standard should be subjective; that is, it would be sufficient if Pacific Construction had a good faith belief in the merits of its position with respect to its claimed right to withhold payments due to FEI.

Free access — add to your briefcase to read the full text and ask questions with AI

FEI Enterprises Inc. v. Yoon, 194 Cal. App. 4th 790, 124 Cal. Rptr. 3d 64, 2011 Cal. App. LEXIS 482 (Cal. Ct. App. 2011).

194 Cal. App. 4th 790 (FEI Enterprises Inc. v. Yoon) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rados v. Travelers Casualty and Surety Co. CA2/5
California Court of Appeal, 2026
Yan v. Rhoads CA1/4
California Court of Appeal, 2026
ANE Holdings v. Purity Preserved CA4/1
California Court of Appeal, 2025
Marcus v. Farsai CA6
California Court of Appeal, 2024
Bocchieri v. Farmers Insurance Exchange CA2/3
California Court of Appeal, 2023
Li v. Yu CA6
California Court of Appeal, 2023
Padilla v. Jakubaitis CA4/3
California Court of Appeal, 2022
Li v. Chiu CA1/3
California Court of Appeal, 2022
P.M. v. S.S. CA4/1
California Court of Appeal, 2022
Veeva Systems v. Medidata Solutions CA1/3
California Court of Appeal, 2022
SBI Builders v. Hartford Fire Insurance CA6
California Court of Appeal, 2021
Marriage of Karen and Jason H. CA4/2
California Court of Appeal, 2021
Volpe Co. v. Sausal Corp. CA1/5
California Court of Appeal, 2021