Tesco Controls, Inc. v. Monterey Mechanical Co.

21 Cal. Rptr. 3d 751, 124 Cal. App. 4th 780, 2004 Daily Journal DAR 14466, 2004 Cal. Daily Op. Serv. 10688, 2004 Cal. App. LEXIS 2059
CourtCalifornia Court of Appeal
DecidedDecember 6, 2004
DocketC042184
StatusPublished
Cited by18 cases

This text of 21 Cal. Rptr. 3d 751 (Tesco Controls, Inc. v. Monterey Mechanical Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tesco Controls, Inc. v. Monterey Mechanical Co., 21 Cal. Rptr. 3d 751, 124 Cal. App. 4th 780, 2004 Daily Journal DAR 14466, 2004 Cal. Daily Op. Serv. 10688, 2004 Cal. App. LEXIS 2059 (Cal. Ct. App. 2004).

Opinion

Opinion

NICHOLSON, J.

Plaintiff sought to recover money owed it on a contract under which it supplied electrical equipment for a public works project. Defendants claimed plaintiff was barred from recovering because it had waived its mechanic’s lien rights up through a date when the funds should have been paid. By grant of summary adjudication, the trial court determined plaintiff’s conditional waiver and release of its mechanic’s lien rights under Civil Code section 3262, subdivision (d)(1), released lien rights only to the extent plaintiff had received payment and not up through the date stated on the release.

At trial on plaintiff’s remaining causes of action, the court granted judgment in favor of plaintiff on its claim for breach of a joint check agreement and also awarded statutory penalties. The trial court also dismissed a cross-complaint filed by defendants.

Except to reverse and remand the award of statutory penalties, we affirm the judgment in all respects, but do so on different grounds than those relied upon by the trial court.

UNDISPUTED FACTS AT SUMMARY ADJUDICATION MOTION

In February 1998, defendant City of Chico (the City) contracted with defendant Monterey Mechanical Company, Inc. (Monterey), to expand the City’s wastewater treatment control plant at a cost of approximately $29 million. The agreement called for the City to pay Monterey by means of progress payments and a final payment. The City agreed not to retain any amounts from the progress payments because Monterey agreed to file a performance bond in lieu of agreeing to retentions.

The City’s contract also required Monterey to furnish a bond in the amount of the contract price to guarantee payment of all claims filed against the *785 project for labor and materials. Monterey obtained the labor and materials bond from defendant Fireman’s Fund Insurance Company.

In April 1998, Monterey entered into a subcontract agreement with defendant Stratton Electric, Inc. (Stratton), to complete electrical work for the project at a cost of roughly $3.6 million. The subcontract called for Stratton to submit monthly invoices, and for Monterey to make monthly progress payments to Stratton in the amount of 90 percent of the City’s estimate of the amount of work done on the project during the month. Monterey would withhold the remaining 10 percent of the amount owed as a retention to be paid upon final completion and acceptance of the work.

Also, Monterey was not required to pay Stratton unless Stratton provided releases executed by everyone who might have mechanic’s lien, stop notice or labor and material bond rights against the project arising out of work performed to that date under the subcontract with Stratton. Monterey did not require Stratton to post a labor and materials bond to cover such claims. Instead, the parties agreed Stratton would “use the ‘Joint Check’ policy.”

Finally, the subcontract expressly required Stratton and plaintiff Tesco Controls, Inc. (Tesco), to provide jointly a complete and operable installation of certain electrical work in accordance with Monterey’s specifications.

By a purchase order dated February 1998, Stratton retained Tesco to furnish certain electrical instruments and controls for the project at a cost of roughly $800,000. Subsequent change orders increased the cost to $847,558.

In the purchase order, Stratton agreed to pay Tesco in monthly progress payments equal to 90 percent “of labor and materials which have been placed in position, with funds received by [Stratton] from [City] for work performed by [Tesco] as reflected in [Stratton’s] applications for payment.” (Capitalization omitted, italics added.) The purchase order also awarded attorney fees to the prevailing party in a dispute arising under its terms.

In March 1998, Monterey and Stratton entered into a joint check agreement for the express benefit of Tesco by which Monterey and Stratton agreed to a method for paying Tesco different from that established in the purchase order. According to the joint check agreement, any Tesco invoice sent to Stratton would be copied to Monterey. Monterey would pay Tesco by negotiable check “in the amount of such invoice” and made payable to both Tesco and Stratton. (Italics added.) Stratton then would endorse the check and make it payable to Tesco “as payment in full of the related invoice.” Payments would be made when normal progress payments were due. The joint check agreement said nothing about retentions.

*786 Defendants admit Tesco fully performed its obligations under the purchase order. However, after the project was completed, Tesco remained underpaid by $194,762. Defendants claim Tesco released its lien rights to recover that amount by a release dated March 15, 1999—an assertion which Tesco denies. The disagreement arose as follows:

Tesco began shipping equipment to the project site in November 1998. Its first invoice, dated November 10, 1998, was in the amount of $14,980. Contrary to the terms of the joint check agreement, Stratton paid this invoice in full by its own check dated January 8, 1999. However, by that time, Tesco had invoiced additional shipments. As of January 31, 1999, $244,762.13, billed on invoices from December 1998 through January 1999, remained unpaid.

Tesco continued shipping equipment in February 1999, but received no payments that month. By March 11, 1999, Tesco’s invoicing of equipment resulted in a balance owed of $468,946.13. On March 12, 1999, Tesco received a check drawn directly by Stratton in the amount of $194,762.13, but Stratton asked Tesco not to deposit the check for as long as 30 days. The check never cleared the bank.

Meanwhile, on March 15, 1999, Tesco gave Monterey a lien waiver and release conditioned upon receiving a progress payment of $50,000. The release, made under Civil Code section 3262, subdivision (d)(1), “cover[ed] a progress payment for labor, services, equipment or material furnished to Stratton Electric through 01/31/99 only.” 1 , 2

By joint check dated March 16, 1999, Monterey paid $50,000 to Stratton and Tesco, which Tesco deposited in its bank. Had Stratton’s check for $194,762.13 cleared the bank, it, along with Monterey’s $50,000 payment, would have brought Tesco’s account current through January 31, 1999 (assuming no retentions were withheld by defendants), and left an outstanding balance of $224,184 owed Tesco for materials and services invoiced as of March 31, 1999. Instead, without that check clearing, unpaid invoices since *787 December 1998 through March 31, 1999, totaled $418,946.13. If a 10-percent retention was assumed on all of what Tesco had invoiced up to March 31, 1999, Tesco as of that date was owed $370,553.52.

During April and May, there were communications between Tesco, Stratton and Monterey regarding the failure of Stratton’s $194,762.13 check to clear the bank and Stratton’s inability to bring its accounts payable current. By letter dated May 3, 1999, Tesco informed Stratton it had to be paid $370,553.52 for materials furnished through March 31, 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rados v. Travelers Casualty and Surety Co. CA2/5
California Court of Appeal, 2026
Active Properties LLC v. Cabrera
California Court of Appeal, 2016
Active Properties, LLC v. Cabrera
6 Cal. App. Supp. 5th 6 (Appellate Division of the Superior Court of California, 2016)
Picerne Construction Corp. v. Castellino Villas
244 Cal. App. 4th 1201 (California Court of Appeal, 2016)
Moorefield Constr. v. Intervest-Mortgage
California Court of Appeal, 2014
Moorefield Construction, Inc. v. Intervest-Mortgage Investment Co.
230 Cal. App. 4th 146 (California Court of Appeal, 2014)
Magnum Builders v. Preferred Bank CA2/7
California Court of Appeal, 2014
People v. Wahidi
222 Cal. App. 4th 802 (California Court of Appeal, 2013)
Mt. Hawley Ins. Co. v. Lopez
California Court of Appeal, 2013
Mt. Hawley Insurance v. Lopez
215 Cal. App. 4th 1385 (California Court of Appeal, 2013)
FEI Enterprises Inc. v. Yoon
194 Cal. App. 4th 790 (California Court of Appeal, 2011)
Turner v. Ass'n of American Medical Colleges
193 Cal. App. 4th 1047 (California Court of Appeal, 2011)
CALIFORNIA CORRECTIONAL PEACE OFFICERS ASSN. v. State of California
189 Cal. App. 4th 849 (California Court of Appeal, 2010)
Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc.
179 Cal. App. 4th 1401 (California Court of Appeal, 2009)
MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Faulder v. Mendocino County Board of Supervisors
51 Cal. Rptr. 3d 251 (California Court of Appeal, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
21 Cal. Rptr. 3d 751, 124 Cal. App. 4th 780, 2004 Daily Journal DAR 14466, 2004 Cal. Daily Op. Serv. 10688, 2004 Cal. App. LEXIS 2059, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tesco-controls-inc-v-monterey-mechanical-co-calctapp-2004.