Volpe Co. v. Sausal Corp. CA1/5

CourtCalifornia Court of Appeal
DecidedSeptember 29, 2021
DocketA157577
StatusUnpublished

This text of Volpe Co. v. Sausal Corp. CA1/5 (Volpe Co. v. Sausal Corp. CA1/5) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Volpe Co. v. Sausal Corp. CA1/5, (Cal. Ct. App. 2021).

Opinion

Filed 9/29/21 Volpe Co. v. Sausal Corp. CA1/5 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION FIVE

VOLPE CO., INC., Plaintiff and Respondent, A157577, A159372 v. SAUSAL CORP., (Marin County Super. Ct. No. CIV1402511) Defendant and Appellant.

Numerous laws regulate disputes between a primary contractor and its subcontractors in the construction of public projects. Two such laws are at issue in this case: Public Contract Code section 4107,1 which, among other things, regulates the authority of a prime contractor to substitute a new subcontractor in place of the subcontractor listed in the original bid; and Business and Professions Code section 7108.5, a prompt payment statute. In a jury trial, the plaintiff subcontractor prevailed on a breach of contract claim resting on section 4107, and a prompt payment claim, and was awarded prejudgment interest and attorney fees. We reverse judgment on the subcontractor’s breach of contract claim, direct modification of the award pursuant to the prompt payment statute, and remand for further proceedings.

1 All undesignated section references are to the Public Contract Code.

1 BACKGROUND2 In the summer of 2012, the City of Novato (City) awarded a contract to build a new City office building (Project) to Sausal Corporation (Prime Contractor). Prime Contractor entered into a subcontract (Contract) with Volpe Co., Inc. (Subcontractor) to perform grading, paving, and underground utility work on the Project, for a payment of approximately $400,000. Over the course of the Project, the Contract amount grew to more than $650,000 because of change orders approved by the City. Subcontractor began work on the Project in August 2012. It continued working through the spring of 2013, and then paused its work on the Project as other Project work was performed. In late summer, Prime Contractor reached out to Subcontractor to schedule its return to the Project site. The Subcontractor’s return did not comply with the Prime Contractor’s timeframe, and the parties dispute the reasons for this. In September, Subcontractor did return but its work progressed more slowly than Prime Contractor wanted; the parties submitted conflicting evidence as to whether the delays were primarily due to Subcontractor’s failure to return to the Project sooner and to sufficiently staff the Project work when it did return, or to mistakes by other subcontractors and unforeseen conditions that impeded Subcontractor’s progress. In October 2013, Prime Contractor brought in another party, G.D. Nielson Construction (Nielson), to perform some of the work remaining on the Project. Subcontractor also continued to work on the Project in October and November. However, Prime Contractor did not pay Subcontractor for any of the work it performed following its return to the Project in September 2013.

2We recite only those background facts relevant to our resolution of the appeals.

2 Prime Contractor took the position that Subcontractor owed it the amount it paid Nielson for work within the scope of the Contract, and that the amount it paid Nielson was greater than the remaining amount it owed to Subcontractor. In 2014, Subcontractor filed the underlying lawsuit for breach of contract and other claims. Following a jury trial, the jury found that Prime Contractor had breached the Contract, and that Subcontractor had incurred approximately $380,000 in damages. The jury also found that as of December 31, 2013, approximately $260,000 of this damages amount had been paid to Prime Contractor by the City for work performed by Subcontractor. Prime Contractor filed a motion for judgment notwithstanding the verdict or a new trial, which the trial court denied. The court granted Subcontractor’s motions for prejudgment interest, prompt payment penalties (Bus. & Prof. Code, § 7108.5), and attorney fees, and issued judgment for more than $1 million. Prime Contractor appealed separately from the judgment and the attorney fee order, and this court consolidated the appeals.3

3 Subcontractor complains that Prime Contractor failed to provide Subcontractor with copies of the reporter’s transcripts designated as part of the record on appeal and suggests Prime Contractor improperly submitted these transcripts to this court. Prime Contractor’s designation of the record permissibly requested reporter’s transcripts be provided by the reporters. Pursuant to the Rules of Court, the reporter files the original and one copy of the requested transcripts with the superior court, which in turn provides the original to this court and the copy to the appellant. (Cal. Rules of Court, rules 8.130(f)(1), 8.150(a).) Prime Contractor was not obligated to provide Subcontractor with a copy. (See Eisenberg et al., Cal. Practice Guide: Civil Appeals and Writs (The Rutter Group 2021) ¶ 4:273 [“Respondent and other parties can make arrangements with the clerk and/or reporter to purchase additional copies of the record.”].)

3 DISCUSSION I. Public Contract Code Section 4107 The jury’s verdict finding Prime Contractor breached the Contract was based on a provision in Prime Contractor’s contract with the City, incorporated by reference into the Contract, obliging Prime Contractor to comply with section 4107. Section 4107 provides that a prime contractor may not “[s]ubstitute a person as subcontractor in place of the subcontractor listed in the original bid, except that the awarding authority, or its duly authorized officer, may . . . consent to the substitution of another person as a subcontractor in [certain enumerated situations],” with exceptions not relevant here. (§ 4107, subd. (a).) The statute further provides, “Prior to approval of the prime contractor’s request for the substitution, the awarding authority, or its duly authorized officer, shall give notice in writing to the listed subcontractor of the prime contractor’s request to substitute and of the reasons for the request. . . . The listed subcontractor who has been so notified has five working days within which to submit written objections to the substitution to the awarding authority. Failure to file these written objections constitutes the listed subcontractor’s consent to the substitution. [¶] If written objections are filed, the awarding authority shall give notice in writing of at least five working days to the listed subcontractor of a hearing by the awarding authority on the prime contractor’s request for substitution.” (Ibid.) Prime Contractor raises several arguments challenging the judgment in favor of Subcontractor on this claim. We agree with one of its arguments, and reverse and remand the breach of contract claim.

4 A. Additional Factual Background Prime Contractor’s contract with the City included the following provision: “7.6. No Contractor whose Bid is accepted shall, without consent of the awarding authority and in full compliance with section 4100, et seq, of the Public Contract Code, including, without limitation, sections 4107, 4107.5, and 4109 of the Public Contract Code . . . : [¶] 7.6.1. Substitute any person as a Subcontractor in place of the Subcontractor designated in the original Bid . . . .” Prime Contractor does not dispute that this provision was incorporated by reference into the Contract.4 Subcontractor was designated in Prime Contractor’s original bid. On October 18, 2013—the day Nielson started working on the Project— Prime Contractor emailed the City’s city manager, “Just want to let you know that we had the new crews start augmenting [Subcontractor’s] forces today.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

W. J. Lewis Corp. v. C. Harper Construction Co.
116 Cal. App. 3d 27 (California Court of Appeal, 1981)
Merced County Taxpayers' Ass'n v. Cardella
218 Cal. App. 3d 396 (California Court of Appeal, 1990)
Vogelsang v. Wolpert
227 Cal. App. 2d 102 (California Court of Appeal, 1964)
E. F. Brady Co. v. M. H. Golden Co.
58 Cal. App. 4th 182 (California Court of Appeal, 1997)
Titan Elec. v. La Unified School Dist.
72 Cal. Rptr. 3d 570 (California Court of Appeal, 2008)
Manriquez v. Gourley
130 Cal. Rptr. 2d 209 (California Court of Appeal, 2003)
Tellez v. Rich Voss Trucking, Inc.
240 Cal. App. 4th 1052 (California Court of Appeal, 2015)
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.
416 P.3d 792 (California Supreme Court, 2018)
Southern California Acoustics Co. v. C. V. Holder, Inc.
456 P.2d 975 (California Supreme Court, 1969)
FEI Enterprises Inc. v. Yoon
194 Cal. App. 4th 790 (California Court of Appeal, 2011)
Avalos v. Perez
196 Cal. App. 4th 773 (California Court of Appeal, 2011)
County of Kern v. Jadwin
197 Cal. App. 4th 65 (California Court of Appeal, 2011)
JMS Air Conditioning & Appliance Serv., Inc. v. Santa Monica Cmty. Coll. Dist.
242 Cal. Rptr. 3d 197 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Volpe Co. v. Sausal Corp. CA1/5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/volpe-co-v-sausal-corp-ca15-calctapp-2021.