United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.

416 P.3d 792, 232 Cal. Rptr. 3d 428, 4 Cal. 5th 1082
CourtCalifornia Supreme Court
DecidedMay 14, 2018
DocketS231549
StatusPublished
Cited by60 cases

This text of 416 P.3d 792 (United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co., 416 P.3d 792, 232 Cal. Rptr. 3d 428, 4 Cal. 5th 1082 (Cal. 2018).

Opinion

CUÉLLAR, J.

*1085 This case is about construction-both physical and statutory. Spurred by late payment problems in the construction industry, the Legislature established statutory payment deadlines and imposed penalties on owners who delay paying their direct contractors, and on direct contractors who delay paying their subcontractors. But these strict deadlines include an exception relevant to this case: Direct contractors can withhold monies from subcontractors in circumstances where a dispute *430 has arisen between the parties. ( Civ. Code, § 8814, subd. (c).) What we must decide is whether this exception allows withholding when there is any dispute between the parties, or only when there is a dispute directly relevant to the specific payment that would otherwise be due.

The Court of Appeal adopted the narrower construction. We agree. The dispute exception excuses payment only when a good faith dispute exists over a statutory or contractual precondition to that payment, such as the adequacy of the construction work for which the payment is consideration. Controversies concerning unrelated work or additional payments above the amount both sides agree is owed will not excuse delay; a direct contractor cannot withhold payment where the underlying obligation to pay those specific monies is undisputed. We affirm.

*1086 I.

In 2010, Universal City Studios LLLP (Universal) entered agreements to build a new ride at its theme park, Universal Studios Hollywood. For the new attraction that would become Transformers: The Ride , Universal selected defendant Coast Iron & Steel Co. (Coast Iron) as the direct contractor to design, furnish, and install metal work. Universal agreed to pay Coast Iron on a monthly basis for amounts billed, minus a 10 percent withholding-referred to in the construction **794 industry as a retention or retainage-as protection against nonperformance and potential liens. Upon receipt, Coast Iron was contractually responsible for making corresponding payments to its subcontractors.

One such subcontractor was plaintiff United Riggers & Erectors, Inc. (United Riggers), which was responsible for installing the metal work Coast Iron fabricated and supplied. The contract between Coast Iron and United Riggers called for United Riggers to receive $722,742 for its work. Because of change orders submitted by United Riggers and approved by Universal, the amount Coast Iron owed United Riggers eventually rose to just under $1.5 million.

United Riggers completed its work to Coast Iron's satisfaction. In March 2012, once all work on the project was finished, Coast Iron asked for a final bill from its subcontractor. United Riggers demanded additional amounts that would have brought its pay to $1.85 million: $274,158.40 for increased expenses attributed to Coast Iron's mismanagement, and $78,384 based on outstanding change order requests. Coast Iron refused payment, responding instead that it would "see [United Riggers] in court!!"

In August 2012, Universal paid out the 10 percent withheld as a retention to Coast Iron, which in turn owed $149,602.52 of that amount to United Riggers. Although United Riggers requested payment, Coast Iron declined to pay forward any part of the retention.

United Riggers sued in January 2013. Its complaint alleged various common law claims and one statutory claim, for failure to make prompt payment of the retention monies Coast Iron had received from Universal and in turn owed United Riggers. ( Civ. Code, §§ 8814, 8818.) In February 2013, Coast Iron made a partial payment of the retention, and in December 2013, it paid the remainder. These payments did not moot United Riggers's statutory claim because the statutory scheme imposes a penalty for delay and awards attorney fees and costs to the prevailing party in any action over late payment of a retention. ( Id. , § 8818, subds. (a), (b).)

After a bench trial, the trial court issued a statement of decision denying relief on all claims and entered judgment for Coast *431 Iron. The Court of Appeal *1087 affirmed as to the common law claims but reversed on the statutory claim for failure to make timely retention payments. The appellate court explained that in its view, limiting withholding to disputes specifically related to the withheld monies was more consonant with what the Legislature had contemplated in enacting the prompt payment statute. Accordingly, Coast Iron could not use the parties' dispute over project mismanagement to justify withholding United Riggers's portion of the retention.

The Court of Appeal's decision contributed to a split of authority over whether the Legislature's prompt payment statutes should be interpreted to permit withholding where there is any dispute between a contractor and subcontractor, or only when there is a dispute regarding entitlement to the retention monies themselves. (Compare Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 , 102 Cal.Rptr.3d 419 ( Martin Brothers Construction ) [any bona fide dispute can justify withholding retention payment] with East West Bank v. Rio School Dist. (2015) 235 Cal.App.4th 742 , 185 Cal.Rptr.3d 676 [only disputes related to the retention's security functions can justify withholding payment].)

II.

Construction contracts often call for payment in installments-known commonly as progress payments-due when a project reaches various stages of completion. (9 Miller & Starr, Cal. Real Estate (4th ed. 2016) § 31:91, p. 31-370.) By arranging for progress payments, participants in a construction-related transaction build in an incentive for contractors to complete work and provide an owner some protection against the risk of nonperformance ( Cates Construction, Inc. v. Talbot Partners (1999) 21 Cal.4th 28 , 55, 86 Cal.Rptr.2d 855 , 980 P.2d 407

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anton's Services v. Hagen
California Court of Appeal, 2025
Anton's Services v. Hagen CA4/1
California Court of Appeal, 2025
Van Muers-Bradley v. AutoNation CA3
California Court of Appeal, 2025
P. ex rel. Soto v. Group IX BP Properties
California Court of Appeal, 2025
People v. Group IX BP Properties CA2/4
California Court of Appeal, 2025
Charlie L. v. Kangavari
California Court of Appeal, 2025
People v. Johnson CA2/3
California Court of Appeal, 2024
Schneider v. Lane
California Court of Appeal, 2024
McCurdy v. County of Riverside
California Court of Appeal, 2024
City of Alameda v. Sheehan
California Court of Appeal, 2024
Robinson v. Gutierrez
California Court of Appeal, 2023
City of Gilroy v. Super Ct.
California Court of Appeal, 2023
City of Gilroy v. Superior Court
California Court of Appeal, 2023
McConnell v. Advantest America
California Court of Appeal, 2023
McConnell v. Advantest America CA4/1
California Court of Appeal, 2023
Davis v. Fresno Unified School Dist.
California Supreme Court, 2023
In re Jenkins
California Supreme Court, 2023

Cite This Page — Counsel Stack

Bluebook (online)
416 P.3d 792, 232 Cal. Rptr. 3d 428, 4 Cal. 5th 1082, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-riggers-erectors-inc-v-coast-iron-steel-co-cal-2018.