Suffolk Construction Co. v. L.A. Unified School District CA2/7

CourtCalifornia Court of Appeal
DecidedAugust 27, 2025
DocketB314311
StatusUnpublished

This text of Suffolk Construction Co. v. L.A. Unified School District CA2/7 (Suffolk Construction Co. v. L.A. Unified School District CA2/7) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Suffolk Construction Co. v. L.A. Unified School District CA2/7, (Cal. Ct. App. 2025).

Opinion

Filed 8/27/25 Suffolk Construction Co. v. L.A. Unified School District CA2/7 NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION SEVEN

SUFFOLK CONSTRUCTION B314311 COMPANY, INC., (Los Angeles County Plaintiff and Appellant, Super. Ct. No. BC494389)

v.

LOS ANGELES UNIFIED SCHOOL DISTRICT,

Defendant and Appellant.

APPEAL from a judgment of the Superior Court of Los Angeles County, Maren Nelson, Judge. Affirmed with modifications. KP LAW, Zareh A. Jaltorossian, Pierce Kavcioglu Espinosa & Cesar, Timothy L. Pierce and Hector H. Espinosa for Plaintiff and Appellant. Theodora Oringher, Kevin A. Dorse, Panteha Abdollahi, Brian J. Headman, Erich R. Luschei and Timothy J. Heggem; Office of the General Counsel, Devora Navera Reed and Mark Fall for Defendant and Respondent. ________________________

INTRODUCTION

Suffolk Construction Company, Inc. sued the Los Angeles Unified School District (District or LAUSD) for breach of contract related to its construction of the Bell Education and Career Center. Suffolk recovered significant damages on several of its contract claims and judgment was entered in its favor, but the jury found against it with regard to certain amounts Suffolk claimed were wrongfully retained by the District. Suffolk argues the trial court erred by entering judgment notwithstanding the verdict in favor of the District (rather than Suffolk) on the retention claim, and that it is entitled to a limited new trial on that issue because the jury returned an inconsistent verdict and the special verdict form included a “legally problematic” question. Suffolk also challenges the trial court’s ruling it was not entitled to recover from the District attorney fees Suffolk incurred in related litigation with its subcontractors. We affirm the judgment as it relates to Suffolk’s appeal. The District cross-appeals from the trial court’s award of attorney fees, costs, and prejudgment interest. The District contends the trial court applied incorrect legal criteria to determine that Suffolk was the prevailing party for purposes of attorney fees and costs. The District also contests the trial court’s award of prejudgment interest on three payments the District made to Suffolk after Suffolk filed suit. We modify the judgment to reduce the prejudgment interest award and otherwise affirm the judgment as modified.

2 FACTUAL AND PROCEDURAL BACKGROUND

A. The Prime Contract On November 10, 2010, the District contracted with Suffolk to build the Bell Education and Career Center (the project) for approximately $25 million.1 Suffolk hired subcontractors Best Contracting Services, Inc. and Quality Production Services, Inc. (QPS), among others, in connection with the project. The prime contract required the project to be substantially completed by June 26, 2012, but the project was delayed 141 days. Although the school was opened and students began to use some of the facilities in August 2012, the project was not substantially completed until November 14, 2012.2 The prime contract authorized liquidated damages of $3,000 per day up to 180 calendar days if Suffolk failed to meet the substantial completion deadline. Article 12 of the General Conditions and Supplementary Conditions and sections 3.06 and 3.07 of Specification 01360 in the Construction Schedule set out procedures by which Suffolk could seek extensions of time or additional compensation for extra work. Article 12.1 stated, “All time limits in the Contract are of the essence. The Contract Time and/or Milestones can only be adjusted by a Change order.” Article 12.3 entitled Suffolk to compensation for delays to the project caused by the District. Articles 12.4 and 12.5 required Suffolk to provide written notice

1 We adopt the parties’ reference to this contract as the prime contract. 2 The record indicates the school was completed and all work finished by March 2013.

3 on a form provided by the District of any “issue, event condition, circumstance and/or cause of a perceived and/or actual delay, disruption, interference, hindrance, and/or acceleration” within three working days after first encountering the issue and within three working days of the end of the issue. If Suffolk then wanted an adjustment to the timeline or additional payment, it was required under Article 12.6 to submit a change order proposal (COP) within 35 days of the Article 12.5 notice. Sections 3.06 and 3.07 set out requirements for monetary recovery for delays and requests for extensions of time. In pertinent part, section 3.06 provided: “Prior to submitting any time extension request to the Owner, the Contractor shall first demonstrate the impact by use of a detailed pre-delay and post- delay time impact analysis fragnet with an accompanied written narrative as outlined in Section 01360—Construction Schedule.”3 Section 3.07 provided detailed requirements for time extension requests. Section 3.07 also emphasized, “Adjustments to Milestones and/or Contract Time will only be authorized by Change Order.”

B. Change Order Proposal 199.3 On July 6, 2012, Suffolk submitted COP 199, which sought an unspecified delay to the substantial completion date. COP 199 stated the delay was “TBD” or to be determined. The District rejected COP 199 and two subsequent versions for, among other

3 At trial, one of the District’s witnesses testified that a “fragnet is a detailed explanation of what you did to get to where you say you got; so . . . it’s a cookbook tactic. It’s a blow by blow here is what I did. I had to move this in front of that. We had overtime. It shows how you got to where you say you got.”

4 things, failure to comply with the procedures outlined in Article 12 and sections 3.06 and 3.07. On May 24, 2013, after the November 14, 2012 substantial completion date, Suffolk submitted COP 199.3. COP 199.3 was the final iteration of COP 199 and the version at issue at trial. In COP 199.3, Suffolk requested a time extension of 111 days and over $4 million it asserted was incurred due to District-caused delays. In particular, COP 199.3 requested acceleration and delay costs primarily related to problems with the installation of commercial kitchen hoods and a marquee sign. On June 6, 2013, the District rejected COP 199.3, noting it was “as equally inconclusive as the previous versions.” The District asserted, “Suffolk’s claim that the delay to the project’s completion was District caused is not supported.” Instead, the District attributed the delay to the default of Suffolk’s steel subcontractor at the beginning of the project which had a ripple effect on subsequent deadlines, as well as the defaults of other “critical” trades. The District further asserted Suffolk failed to adhere to Suffolk’s own proposals to recover time by utilizing overtime, resequencing work, allowing for concurrent work, and furnishing and maintaining a sufficient workforce.

C. The Lawsuit On January 24, 2012, Suffolk sued the District, alleging three causes of action. In the first cause of action for breach of contract, Suffolk alleged the District failed to pay all sums due under the prime contract, including progress payments and

5 retention amounts.4 The prime contract contained a 10 percent retention provision. The District was required to release the retention amounts withheld from each progress payment within 60 days of completion of the project. Here, the District withheld $423,000 of the retention amount as liquidated damages ($3,000 per day x 141-day delay).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maynard v. BTI Group, Inc.
216 Cal. App. 4th 984 (California Court of Appeal, 2013)
Mangini v. Aerojet-General Corp.
912 P.2d 1220 (California Supreme Court, 1996)
Platt Pacific, Inc. v. Andelson
862 P.2d 158 (California Supreme Court, 1993)
Brandt v. Superior Court
693 P.2d 796 (California Supreme Court, 1985)
Lemons v. Regents of University of California
582 P.2d 946 (California Supreme Court, 1978)
Davis v. Air Technical Industries, Inc.
582 P.2d 1010 (California Supreme Court, 1978)
Buck v. Barb
147 Cal. App. 3d 920 (California Court of Appeal, 1983)
Yamanishi v. Bleily & Collishaw, Inc.
29 Cal. App. 3d 457 (California Court of Appeal, 1972)
Helzel v. Superior Court
123 Cal. App. 3d 652 (California Court of Appeal, 1981)
Kawasho International, U.S.A., Inc. v. Lakewood Pipe Service, Inc.
152 Cal. App. 3d 785 (California Court of Appeal, 1983)
A & M PRODUCE CO. v. FMC Corp.
135 Cal. App. 3d 473 (California Court of Appeal, 1982)
Kossler v. Palm Springs Developments, Ltd.
101 Cal. App. 3d 88 (California Court of Appeal, 1980)
Vanguard Recording Society, Inc. v. Fantasy Records, Inc.
24 Cal. App. 3d 410 (California Court of Appeal, 1972)
Howard v. Schaniel
113 Cal. App. 3d 256 (California Court of Appeal, 1980)
Harbor City Discount Auto Center, Inc. v. Firestone Tire & Rubber Co.
95 Cal. App. 3d 886 (California Court of Appeal, 1979)
Denver D. Darling, Inc. v. Controlled Environments Construction, Inc.
108 Cal. Rptr. 2d 213 (California Court of Appeal, 2001)
MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Arntz Builders v. City of Berkeley
166 Cal. App. 4th 276 (California Court of Appeal, 2008)
Shaw v. Hughes Aircraft Co.
100 Cal. Rptr. 2d 446 (California Court of Appeal, 2000)
Trujillo v. North County Transit Dist.
63 Cal. App. 4th 280 (California Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Suffolk Construction Co. v. L.A. Unified School District CA2/7, Counsel Stack Legal Research, https://law.counselstack.com/opinion/suffolk-construction-co-v-la-unified-school-district-ca27-calctapp-2025.