Morton Engineering & Construction, Inc. v. Patscheck

104 Cal. Rptr. 2d 815, 87 Cal. App. 4th 712, 2001 Cal. Daily Op. Serv. 1923, 2001 Daily Journal DAR 2413, 2001 Cal. App. LEXIS 163
CourtCalifornia Court of Appeal
DecidedMarch 7, 2001
DocketF033184
StatusPublished
Cited by22 cases

This text of 104 Cal. Rptr. 2d 815 (Morton Engineering & Construction, Inc. v. Patscheck) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morton Engineering & Construction, Inc. v. Patscheck, 104 Cal. Rptr. 2d 815, 87 Cal. App. 4th 712, 2001 Cal. Daily Op. Serv. 1923, 2001 Daily Journal DAR 2413, 2001 Cal. App. LEXIS 163 (Cal. Ct. App. 2001).

Opinion

*714 Opinion

CORNELL, J.

Respondent Morton Engineering & Construction, Inc. (Morton), was hired by appellant Stanley Douglas Patscheck (Patscheck), as a subcontractor on a public works project. Patscheck failed to pay Morton for its work. Morton obtained a judgment that included penalties for failure to pay progress payments and retention proceeds within the time required by Business and Professions Code section 7108.5 1 and Public Contract Code section 7107.

Patscheck appeals asserting the penalty provision in section 7108.5 can only be awarded in a disciplinary action before the Contractors’ State License Board (CSLB), the trial court miscalculated the interest and penalties, and Morton was not entitled to payment for the extra work.

In the published portion of this opinion we conclude the penalty provision found in section 7108.5 is recoverable in either a disciplinary action before the CSLB or in a civil action filed by the subcontractor. We will affirm the judgment.

Statement of Facts and the Case

El Tejón Unified School District (School District) contracted with Patscheck for what appears to be the construction of a gymnasium and football stadium (Prime Contract). Patscheck hired various subcontractors including Raul Gonzales (Gonzales). Gonzales, who was to provide the concrete and structural steel for the project, apparently breached the subcontract and was overpaid, causing Patscheck financial problems on the project.

After Gonzales abandoned the project, Patscheck entered into an oral agreement with plaintiff to complete the concrete work for the sum of $112,800. Morton completed the work in accordance with the plans and specifications.

By September 1996, Patscheck received payment for the entire contract amount from the School District, less the 10 percent retention. Patscheck failed to pay Morton $31,520 admittedly due under the contract. The reason given by Patscheck was the financial problems caused by Gonzales.

Morton filed a complaint in February 1998 containing five causes of action including breach of contract and various common counts to recover *715 the same sum of money. Penalties pursuant to section 7108.5 and Public Contract Code section 7107 were requested. Patscheck timely filed an answer asserting various affirmative defenses.

Patscheck was paid all retention proceeds by July 1998. When Patscheck received the retention proceeds from the School District, he apparently offered Morton $42,800 as full and final settlement of all claims arising out of the project. 2 This was the amount Patscheck admitted was due Morton under the contract, but excluded the extra work, interest and penalties. Morton rejected the offer.

A one-half-day court trial resulted in judgment for Morton in the amount of $111,316.73 which included all sums due under the contract plus the extra work, interest, penalties, attorney fees and costs. Neither side requested a statement of decision.

Discussion

I. The Penalty in Section 7108.5 Is Recoverable in a Civil Action

Section 7108.5 3 provides that upon receipt of a progress payment, the contractor must pay any subcontractor within 10 days the amounts allowed the contractor for the work performed by the subcontractor. The contractor may withhold from a progress payment up to 150 percent of any amount over which a good faith dispute exists. Two sanctions are provided in the event that a contractor fails to pay the subcontractor as required: a *716 disciplinary proceeding and/or a penalty of 2 percent per month on the outstanding balance payable to the subcontractor (2 percent penalty). In the event an action is instituted to collect funds wrongfully withheld, the prevailing party is entitled to recover attorney fees and costs. The issue raised by this appeal is whether the subcontractor can recover the 2 percent penalty in a disciplinary proceeding before the CSLB, or in a civil action, or in both. There is no published authority interpreting the statute.

Our primary task in construing a statute is to determine the Legislature’s intent. (Brown v. Kelly Broadcasting Co. (1989) 48 Cal.3d 711, 724 [257 Cal.Rptr. 708, 771 P.2d 406].) We first turn to the words themselves for the answer. {People v. Knowles (1950) 35 Cal.2d 175, 182 [217 P.2d 1].) When statutory language is clear and unambiguous there is no need for construction, and we will not indulge in it. {Solberg v. Superior Court (1977) 19 Cal.3d 182, 198 [137 Cal.Rptr. 460, 561 P.2d 1148].) We will not speculate that the Legislature meant something other than what it said. Nor will we rewrite a statute to posit an unexpressed intent. {Woodmansee v. Lowery (1959) 167 Cal.App.2d 645, 652 [334 P.2d 991].) If the intent of the Legislature cannot be gleaned from the language of the statute, we may consider the legislative history of the statute. {People v. Snook (1997) 16 Cal.4th 1210, 1219 [69 Cal.Rptr.2d 615, 947 P.2d 808]; Dyna-Med, Inc. v. Fair Employment & Housing Com. (1987) 43 Cal.3d 1379, 1387 [241 Cal.Rptr. 67, 743 P.2d 1323].)

Neither of the two sanctions found in section 7108.5 states the forum in which it can be recovered. Naturally, only the CSLB can discipline a contractor. (§ 7090.) However, it does not automatically follow that the 2 percent penalty can only be recovered in proceedings before the CSLB. Since section 7108.5 does not limit recovery of the 2 percent penalty only to disciplinary proceedings, the plain meaning of the statute would appear to allow recovery of the 2 percent penalty in either a disciplinary proceeding or a civil action.

Patscheck contends that had the Legislature intended the 2 percent penalty to be recoverable in a civil action, it would have included the provision in the sentence that authorizes recovery of attorney fees and costs to the successful civil litigant. According to Patscheck, by including the penalty in the sentence that also exposes a violating contractor to discipline before the CSLB, the Legislature evinced the intent to allow recovery of the 2 percent penalty only in actions before the CSLB. In other words, the first sentence is limited to proceedings before the CSLB and the second sentence is applicable to civil actions.

*717 We do not find the emphasis on which sentence the 2 percent penalty is included to be justified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Fredrick CA5
California Court of Appeal, 2026
People v. Salgado CA5
California Court of Appeal, 2025
People v. Mendoza CA5
California Court of Appeal, 2025
Rab v. Weber
California Court of Appeal, 2023
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.
416 P.3d 792 (California Supreme Court, 2018)
Hayes v. Temecula Valley Unified Sch. Dist.
California Court of Appeal, 2018
Hayes v. Temecula Valley Unified Sch. Dist.
230 Cal. Rptr. 3d 576 (California Court of Appeals, 5th District, 2018)
California State University, Fresno Ass'n v. County of Fresno
9 Cal. App. 5th 250 (California Court of Appeal, 2017)
People v. Mary H.
5 Cal. App. 5th 246 (California Court of Appeal, 2016)
Blois Construction v. FCI/Fluor/Parsons
California Court of Appeal, 2016
Blois Construction, Inc. v. FCI/Fluor/Parsons
245 Cal. App. 4th 1091 (California Court of Appeal, 2016)
United Riggers & Erectors v. Coast Iron & Steel
California Court of Appeal, 2015
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co.
196 Cal. Rptr. 3d 161 (California Court of Appeals, 2nd District, 2015)
Fiorini v. City Brewing Company
231 Cal. App. 4th 306 (California Court of Appeal, 2014)
Galeb Paving v. D.L. Falk Construction CA1/2
California Court of Appeal, 2014
FEI Enterprises Inc. v. Yoon
194 Cal. App. 4th 790 (California Court of Appeal, 2011)
Hinerfeld-Ward, Inc. v. Lipian
188 Cal. App. 4th 86 (California Court of Appeal, 2010)
Yassin v. Solis
184 Cal. App. 4th 524 (California Court of Appeal, 2010)
Leader v. Cords
182 Cal. App. 4th 1588 (California Court of Appeal, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
104 Cal. Rptr. 2d 815, 87 Cal. App. 4th 712, 2001 Cal. Daily Op. Serv. 1923, 2001 Daily Journal DAR 2413, 2001 Cal. App. LEXIS 163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morton-engineering-construction-inc-v-patscheck-calctapp-2001.