Blois Construction v. FCI/Fluor/Parsons

CourtCalifornia Court of Appeal
DecidedApril 12, 2016
DocketB262310M
StatusPublished

This text of Blois Construction v. FCI/Fluor/Parsons (Blois Construction v. FCI/Fluor/Parsons) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blois Construction v. FCI/Fluor/Parsons, (Cal. Ct. App. 2016).

Opinion

Filed 4/12/16 Unmodified opinion attached CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION ONE

BLOIS CONSTRUCTION, INC., B262310

Plaintiff and Appellant, (Los Angeles County Super. Ct. No. BC488623) v. ORDER MODIFYING OPINION FCI/FLUOR/PARSONS, (NO CHANGE IN THE JUDGMENT)

Defendant and Respondent.

THE COURT: It is ordered that the opinion filed herein on March 23, 2016, be modified in the following manner: In the third paragraph on page two, the following sentence is deleted: “FFP is a joint venture of Flatiron Construction, Fluor Corporation, and Parsons Corporation.” That sentence is replaced with the following sentence: “FFP is a joint venture of Flatiron West, Inc.; Fluor Enterprises, Inc.; and Parsons Transportation Group, Inc.” This modification does not constitute a change in the judgment. CERTIFIED FOR PUBLICATION.

ROTHSCHILD, P. J. JOHNSON , J. LUI, J. Filed 3/23/16 (unmodified version) CERTIFIED FOR PUBLICATION

Plaintiff and Appellant, (Los Angeles County Super. Ct. No. BC488623) v.

FCI/FLUOR/PARSONS,

APPEAL from a judgment of the Superior Court of Los Angeles County. Mitchell L. Beckloff, Judge. Affirmed. Lax & Stevens and Paul A. Lax for Plaintiff and Appellant. Musick, Peeler & Garrett, Jack W. Fleming and Peter J. Diedrich for Defendant and Respondent.

____________________________________________ This case involves the interpretation of prompt payment statutes intended to guarantee timely payments to contractors and subcontractors in construction projects. As is typical in the construction industry, here the contract between the owner of the project and the contractor allowed the owner to withhold as “retentions” a percentage of the payments due pending successful completion of the project. Similarly, the contract between the contractor and the subcontractor allowed the contractor to withhold retentions from the payments due the subcontractor. Pursuant to Public Contract Code section 7107 (section 7107), when a project owner pays a direct contractor the amount it had previously withheld as retentions, the direct contractor must pay its subcontractors their share of the retention within seven days or face penalties. In this case, when the project was half complete, the project owner began making full progress payments to its direct contractor without withholding any retentions. The owner, however, continued to withhold the past retentions from the contractor, and the contractor continued to withhold the past retentions from the subcontractor. The question here is a narrow one: Was the decision by the owner to stop withholding future retentions and pay full progress payments to the contractor equivalent to a payment by the owner of past retentions under section 7107? We answer that question, no, and therefore conclude that the subcontractor is not entitled to late payment penalties under section 7107. FACTS AND PROCEEDINGS BELOW In 2006, the Exposition Metro Line Construction Authority (Expo)1 contracted with defendant FCI/Fluor/Parsons (FFP) to serve as the general contractor for the Exposition light rail line, connecting downtown Los Angeles with Culver City and ultimately with Santa Monica. FFP is a joint venture of Flatiron Construction, Fluor Corporation, and Parsons Corporation. Plaintiff Blois Construction, Inc. (Blois) agreed to serve as a subcontractor on the project, responsible for underground work. Both the

1 Because the Legislature granted Expo authority over the project during construction, we treat Expo as the owner of the project for purposes of the prompt payment statutes. (Pub. Util. Code, § 132610, subd. (a).)

2 primary contract and subcontract contained a provision allowing for portions of the progress payments due under the contract to be retained pending successful completion of the work. Expo was permitted to withhold 10 percent of the payments owed to FFP, and FFP was entitled to withhold 10 percent of the payments owed to Blois. The retention provision in the general contract provided that, “after fifty percent (50%) of the Work has been completed, [Expo] may elect to not make further retentions from the remaining Progress Payments if it determines, in its sole discretion, that progress on the Work is satisfactory.” Accordingly, in December 2009, FFP requested that Expo cease withholding retentions. Expo acceded to FFP’s request, and although Expo reserved the right to resume withholding at a later date, it never withheld retention funds from a payment to FFP after December 7, 2009. It did not, however, release the previously withheld retention funds until May 30, 2014 or later. By the time Blois finished its work on the project in 2011, FFP had withheld over $500,000 in retentions from Blois. In 2012, Blois filed suit against FFP and its sureties, alleging that FFP had failed to pay Blois for (1) the extra work that Blois performed on the project, and (2) the retentions it had withheld. Pursuant to FFP’s motion, the court referred the case to a dispute review board (Board) for arbitration. In the fall of 2013, while the case was still pending before the Board, FFP paid Blois $534,909.89, the full amount that Blois claimed it was owed in retentions. The Board ruled in favor of Blois, finding among other things that under the terms of the subcontract, FFP had been required to pay the retentions it had withheld by September 2011. But the Board left for the trial court to decide whether Blois was entitled to penalties from FFP for late payment of retained amounts. After a court trial, the court ruled Blois was not entitled to penalties because Expo had not released the retained funds to FPP until 2014 and FFP had paid Blois the full amount of its retention by the end of 2013.

3 DISCUSSION California has a series of laws known as “prompt payment” statutes which govern the timing of payments from project owners to general contractors and from general contractors to subcontractors. 2 The purpose of these statutes is to ensure that contractors and subcontractors, who may have less leverage than project owners and contractors, respectively, are paid for their work on a timely basis. (Morton Engineering & Construction, Inc. v. Patscheck (2001) 87 Cal.App.4th 712, 720.) The primary prompt payment statute at issue here is section 7107. This section requires public entities to release retention proceeds to contractors within 60 days of the completion of a project. (§ 7107, subd. (c).) Furthermore, “within seven days from the time that all or any portion of the retention proceeds are received by the original contractor, the original contractor shall pay each of its subcontractors from whom retention has been withheld, each subcontractor’s share of the retention received.” (Id., subd. (d).) An original contractor who fails to pay a subcontractor “within the time periods required by this section . . . shall be subject to a charge of 2 percent per month on the improperly withheld amount.” (Id., subd. (f).) The only dispute in this case is whether Expo’s practice, beginning in February 2010, of paying FFP the full amount of progress payments and not withholding any retentions triggered an obligation by FFP under section 7107 to pay Blois retentions that it had previously withheld. Blois contends that the answer is yes. It argues that, after December 2009, when Expo made its regular progress payments to FFP without withholding any amount in retention, “retention proceeds [were] received by the original contractor” (§ 7107, subd. (d)), and FFP was thus required to pay Blois its share of the retention proceeds within seven days or face penalties.3 Because this case is a matter of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Yassin v. Solis
184 Cal. App. 4th 524 (California Court of Appeal, 2010)
McAndrew v. HAZEGH
27 Cal. Rptr. 3d 836 (California Court of Appeal, 2005)
Morton Engineering & Construction, Inc. v. Patscheck
104 Cal. Rptr. 2d 815 (California Court of Appeal, 2001)
S&S Cummins Corp. v. West Bay Builders, Inc.
71 Cal. Rptr. 3d 828 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Blois Construction v. FCI/Fluor/Parsons, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blois-construction-v-fcifluorparsons-calctapp-2016.