Galeb Paving v. D.L. Falk Construction CA1/2

CourtCalifornia Court of Appeal
DecidedJuly 31, 2014
DocketA139527
StatusUnpublished

This text of Galeb Paving v. D.L. Falk Construction CA1/2 (Galeb Paving v. D.L. Falk Construction CA1/2) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Galeb Paving v. D.L. Falk Construction CA1/2, (Cal. Ct. App. 2014).

Opinion

Filed 7/31/14 Galeb Paving v. D.L. Falk Construction CA1/2 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION TWO

GALEB PAVING, INC., Plaintiff and Appellant, A139527 and A139708 v. D.L. FALK CONSTRUCTION INC. et al., (Alameda County Super. Ct. No. HG12621201) Defendants and Respondents.

Respondent D.L. Falk (Falk) was the general contractor on a public works project for the Campbell Unified School District, a project to be completed in a short time frame in the summer of 2011, before the students returned from vacation. Appellant Galeb Paving, Inc. (Galeb) was one of the subcontractors. Issues quickly arose between Falk and Galeb regarding Galeb’s performance—more accurately, nonperformance—under the subcontract. On August 17, the day Galeb’s president assaulted Falk’s project manager at the job site, Galeb was terminated. Galeb sued Falk (and the surety), asserting four causes of action: (1) breach of contract; (2) common count; (3) waiting time penalties; and (4) action on payment bond. The case came on for a nonjury trial and, following Galeb’s case, the trial court granted Falk’s motion for judgment as to all four causes of action. We affirm.

1 FACTUAL BACKGROUND1 The Projects and the Parties In 2011, the Campbell Union School District (District) issued general conditions, dated March 21, 2011, for the Blackford Elementary School Modernization and Construction, Phase 1 (Blackford project). The general conditions were to govern any prime contract the District might award for work on that project and any subcontract the prime contractor might award in connection with that work. By agreement effective May 6, the District awarded the prime contract for the Blackford project to Falk. The contract price was $3,543,000. Shortly after execution of the prime contract, Falk executed a payment bond on the project, with Liberty Mutual Insurance Company (Liberty Mutual) as surety. The prime contract required Falk to perform all work on the project, directly or through subcontractors; it also incorporated the general conditions. The prime contract stated that, pursuant to Labor Code section 1770 et seq., Falk had to pay, and to cause any subcontractors to pay, the prevailing wage in the locality. It also stated that Falk had to keep, and to cause any subcontractors to keep, accurate payroll records showing they had paid the prevailing wage. The prime contract stated that time was of the essence, which was particularly apt here, as the project was to be completed before the students returned from summer vacation. The specific time to complete the project, beginning to end, was to be 56 days from the date the District issued its “Notice to Proceed.” This in fact issued on June 11, making the deadline August 8. In addition to the Blackford project, the District was involved in another project to be completed that summer, at Rolling Hills school (Rolling Hills project). The general

1 Galeb’s position, discussed in more detail below in connection with the standard of review, is that there is no dispute as to the facts that are material to the issues here. While many facts are undisputed, many other facts are not. Thus, we set forth the evidence, “in the light most favorable to the judgment.” (Kinney v. Overton (2007) 153 Cal.App.4th 482, 487; San Diego Metropolitan Transportation Development Bd. v. Handlery Hotel, Inc. (1999) 73 Cal.App.4th 517, 528.)

2 contractor on the Rolling Hills project was Sausal. Falk (and apparently Sausal) went about awarding the subcontracts for the projects, which led to the relationship pertinent here. Galeb was formed as a corporation in 1975, by Slobodan Galeb.2 Slobodan owned 99 percent of the shares, and was president and the “responsible managing officer” of Galeb, a position he held since inception. Slobodan’s son, Tomo, was vice-president, and, as will be seen, was an important actor here. Tomo’s sister, Lepa Galeb-Roskopp, also worked at Galeb.3 Galeb submitted bids on both the Blackford and Rolling Hills projects. Tomo testified at length about how Galeb came to bid on the projects, describing how they were attractive to Galeb for “multiple reasons.” The first is that Galeb did not have any “work lined up for the summer.” The second was that Tomo “had a very good handle on the market and through experience what was going on with pricing.” And, as he put it, “when these jobs came, I recognized in real life, because I was tracking and following the bidding that was going on, that our competitors and their crews were most likely—their best crews were most likely tied up. [¶] Well, . . . when these two jobs came, Rolling Hills and Blackford, I saw a great opportunity, one, to increase margins, two, this is a site work project. And this is what we specialize in. We’re very, very good at doing site work projects. [¶] So, being that it was tailor made for us, and being that we needed work, being that it’s literally, I think maybe 15, 20 minutes from my home, and my father’s place of residence, it became a very attractive job for us to bid on.” Galeb got both jobs. As pertinent here, on May 20, Falk prepared a “Short Form Standard Subcontract,” which short form was in fact 30 pages long. Greg Schmidt, Falk’s director of operations, forwarded it to Galeb, and on May 24, Tomo signed it and returned it—but not as it had been presented to him. 2 Slobodan Galeb had formed an earlier company, Galeb Company, in 1968. 3 Since we refer to appellant as Galeb, to avoid confusion we will refer to the three members of the Galeb family by their first names. No disrespect is intended.

3 On page 21 of the subcontract, entitled “Schedule E; Scope of Work,” Tomo made a handwritten interlineation, boldfaced in the quotation below, the effect of which is that Schedule E read in pertinent part as follows: “The subcontractor shall perform all work necessary to complete the contract in a satisfactory manner in accordance with, and as defined in the contract drawings and specifications . . . . The subcontractor shall provide all labor, materials, equipment, tools and incidentals necessary to complete all of the Demolition, Site Work and Asphalt work. The work performed under this subcontract shall include, but not be limited to the following: “Scope of work clarifications as detailed in Galeb Paving, Inc. Revised Bid Proposal dated 4/28/11. “1. Specification Section 02 41 16—Building Demolition “2. Specification Section 31 05 13—Soils for Earthwork. . . .” (For convenience and consistency with the briefing, we will refer to this as the Tomo subcontract.) On June 6, Schmidt emailed Galeb: “We received your subcontract for the . . . project, unfortunately there were unauthorized modifications made to it. You added your proposal to the contract. We do not allow proposals to be included in subcontracts; there are no exceptions. We will however allow, if warranted and agreed to, that exclusions/clarifications be added to . . . the subcontract that were included in the proposal. Before we can add exclusions/clarifications to the subcontract, information needs to be provided as to where the items in question are included in the work covered by your specification section. . . . Please get back to me ASAP with further information about the exclusions/clarifications so that we can finalize your subcontract.” Schmidt apparently heard nothing, as two days later he sent Galeb another email: “[I]n the interest of time I went ahead and included your exclusions form [sic] your proposal to your contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universities Research Assn., Inc. v. Coutu
450 U.S. 754 (Supreme Court, 1981)
Los Angeles County Department of Children v. Superior Court
215 Cal. App. 4th 962 (California Court of Appeal, 2013)
Lusardi Construction Co. v. Aubry
824 P.2d 643 (California Supreme Court, 1992)
Roesch v. De Mota
150 P.2d 422 (California Supreme Court, 1944)
Associated Lathing & Plastering Co. v. Louis C. Dunn, Inc.
286 P.2d 825 (California Court of Appeal, 1955)
Wal-Noon Corp. v. Hill
45 Cal. App. 3d 605 (California Court of Appeal, 1975)
Acoustics, Inc. v. Trepte Construction Co.
14 Cal. App. 3d 887 (California Court of Appeal, 1971)
Kinney v. Overton
63 Cal. Rptr. 3d 136 (California Court of Appeal, 2007)
Sanchez v. County of San Bernardino
176 Cal. App. 4th 516 (California Court of Appeal, 2009)
California Medical Ass'n v. Aetna U.S. Healthcare of California, Inc.
114 Cal. Rptr. 2d 109 (California Court of Appeal, 2001)
Durell v. Sharp Healthcare
183 Cal. App. 4th 1350 (California Court of Appeal, 2010)
Morton Engineering & Construction, Inc. v. Patscheck
104 Cal. Rptr. 2d 815 (California Court of Appeal, 2001)
San Diego Metropolitan Transit Development Board v. Handlery Hotel, Inc.
86 Cal. Rptr. 2d 473 (California Court of Appeal, 1999)
STATE BUILDING AND CONSTRUCTION TRADES COUNCIL v. Duncan
76 Cal. Rptr. 3d 507 (California Court of Appeal, 2008)
S&S Cummins Corp. v. West Bay Builders, Inc.
71 Cal. Rptr. 3d 828 (California Court of Appeal, 2008)
Combs v. SKYRIVER COMMUNICATIONS, INC.
72 Cal. Rptr. 3d 171 (California Court of Appeal, 2008)
Consolidated World Investments, Inc. v. Lido Preferred Ltd.
9 Cal. App. 4th 373 (California Court of Appeal, 1992)
Hedging Concepts, Inc. v. First Alliance Mortgage Co.
41 Cal. App. 4th 1410 (California Court of Appeal, 1996)
Willman v. Gustafson
147 P.2d 636 (California Court of Appeal, 1944)
Freedman v. Rector, Wardens & Vestrymen of St. Matthias Parish
230 P.2d 629 (California Supreme Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
Galeb Paving v. D.L. Falk Construction CA1/2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/galeb-paving-v-dl-falk-construction-ca12-calctapp-2014.