Thompson Pacific Construction Inc. v. City of Sunnyvale

66 Cal. Rptr. 3d 175, 155 Cal. App. 4th 525, 2007 Cal. App. LEXIS 1585
CourtCalifornia Court of Appeal
DecidedSeptember 21, 2007
DocketH029818
StatusPublished
Cited by104 cases

This text of 66 Cal. Rptr. 3d 175 (Thompson Pacific Construction Inc. v. City of Sunnyvale) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson Pacific Construction Inc. v. City of Sunnyvale, 66 Cal. Rptr. 3d 175, 155 Cal. App. 4th 525, 2007 Cal. App. LEXIS 1585 (Cal. Ct. App. 2007).

Opinion

Opinion

PREMO, J.

Thompson Pacific Construction, Inc. (Thompson), entered into a contract with the City of Sunnyvale (City) for construction of a public building. Disputes arose leading to this lawsuit in which the parties sued each other for breach of contract and various statutory violations. A jury rendered a verdict in favor of City, awarding damages for breach of the covenant of good faith and fair dealing and statutory penalties under the Subletting and Subcontracting Fair Practices Act (Pub. Contract Code, § 4100 et seq.) (FPA) 1 and California’s False Claims Act (Gov. Code, § 12651) (CFCA). Thompson appeals.

*533 We conclude that the trial court did not have jurisdiction to impose penalties under the FPA. We also conclude that the evidence was insufficient to support the amount of damages the jury awarded for breach of the covenant of good faith but since the trial court subtracted the full amount of those damages from the judgment the error does not warrant reversal. We reject Thompson’s remaining claims, modify the judgment to strike the FPA penalties, and as modified, affirm.

I. Factual and Procedural Background

A. Introduction

On April 5, 2002, Thompson and City entered into a contract under which Thompson was to build the Sunnyvale Senior Center. The contract provided that Thompson would substantially complete the project by May 27, 2003, and have it finally completed 30 days later.

Problems arose during construction and the building was not substantially complete by the end of May 2003. City moved its administrative staff into the building in June and held a grand opening on July 19, 2003. Thompson submitted its final billing immediately thereafter but City refused to release the full contract price, maintaining that the project was still incomplete and did not conform to the quality standards of the contract. There followed a contentious dispute about the work that remained to be done accompanied by Thompson’s repeated demands for full payment.

Thompson completely ceased work in November 2003 without completing the project. City filed a notice of cessation, stating that work on the project had ceased on November 21, 2003, and completed the project itself.

Pursuant to the contract, City had retained 10 percent of each progress payment it made to Thompson during the course of construction. The total amount withheld is referred to as the “retention.” City eventually released all but $279,428 of the retention, which City withheld for work it claimed was either not complete or completed improperly and as liquidated damages for delayed completion.

B. Thompson’s Second Amended Complaint

Thompson sued City to recover the unpaid retention and additional damages for extra work. Thompson’s first cause of action for breach of contract alleged that City’s plans and specifications were deficient, which caused Thompson to perform extra work outside the scope of the contract, delayed performance, and caused Thompson to incur additional costs. Thompson also *534 alleged that City purposefully delayed the issuance of change orders, withheld payment for work performed under the contract, and failed to pay interest on the improperly withheld payments. A second cause of action alleged violation of section 7107, which requires prompt payment for the construction of any public work of improvement.

C. City’s Cross-complaint

City filed a cross-complaint in which it alleged that Thompson had falsified its bid documents, failed to pursue the project diligently, failed to complete the project, refused to cooperate in closing out the project, harassed City staff, improperly substituted subcontractors, and submitted pay requests for work that had not been completed. The cross-complaint contained five causes of action: (1) breach of contract, (2) breach of the implied covenant of good faith and fair dealing, (3) breach of express warranty, (4) declaratory relief, and (5) violation of the FPA. The FPA cause of action sought damages and statutory penalties.

D. City’s Amended Cross-complaint

On September 30, 2005, the Friday before trial was set to begin, City filed a request for leave to amend its cross-complaint to add six causes of action for violation of the CFCA. Thompson opposed the request but declined the trial court’s invitation to continue the trial date. The trial court granted the motion. City filed the amended cross-complaint on October 11, 2005, while trial was underway. Thompson promptly filed a demurrer. The trial court overruled the demurrer, finding that Thompson had waived its right to demur by agreeing to go to trial.

E. The Judgment

The jury rejected Thompson’s two causes of action, finding that City had not breached the contract and that it had not improperly withheld the retention beyond the date allowed by section 7107. As to City’s cross-complaint, the jury found that Thompson had breached the implied covenant of good faith and fair dealing. (The special verdict form did not ask the jury to decide whether Thompson had also breached the express terms of the contract.) The jury determined that as a result of Thompson’s breach of the covenant City suffered damages of $279,428—the exact amount Thompson claimed City had wrongfully withheld from payment under the contract. The jury also found that Thompson had submitted three false claims in violation of the CFCA, that City suffered no compensatory damages, and that Thompson should be assessed a penalty of $10,000 for each false claim. Finally, the jury found that Thompson had violated the FPA by substituting *535 subcontractors it had not listed in its bid documents but that City had suffered no compensatory damages as a result. The jury assessed a total penalty of $91,067.09 for the FPA violations.

Thompson moved for a new trial arguing, among other things, that the trial court did not have jurisdiction over the FPA claims because the Public Contract Code vests that jurisdiction in the “awarding authority.” (§4110.) The trial court denied the motion, concluding that a new trial would not remedy a lack of jurisdiction.

The trial court entered judgment for City. The court calculated the amount of the judgment by adding the jury’s award for breach of the covenant of good faith and fair dealing ($279,428) and the CFCA and FPA penalties ($30,000 and $91,067.09). Presumably intending to avoid giving City a double recovery, the trial court then subtracted $279,428, the amount City already held, from the total of the jury’s award, maiding the net judgment $121,067.09 plus attorney fees and costs. Pursuant to section 7107, the trial court awarded attorney fees of $377,799 to City. Thompson has timely appealed.

II. Contentions

Thompson raises the following contentions on appeal:

A. The trial court lacked jurisdiction to consider City’s FPA claim;
B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nguyen v. Tran CA4/3
California Court of Appeal, 2025
Marriage of Corso CA4/1
California Court of Appeal, 2025
Haacke v. Pfister CA4/2
California Court of Appeal, 2025
Soliz v. California Highway Patrol CA5
California Court of Appeal, 2025
West Sacramento Hospitality v. S.A.V. Texas CA3
California Court of Appeal, 2025
Chavez v. Cal. Collision
California Court of Appeal, 2024
Diaz-Magana v. Diaz CA5
California Court of Appeal, 2024
Kaneko v. Masui CA2/5
California Court of Appeal, 2024
Liu v. Shapero CA1/5
California Court of Appeal, 2023
Buckman v. City of Los Angeles CA2/2
California Court of Appeal, 2023
Dupree v. CIT Bank
California Court of Appeal, 2023
People v. Daniels CA1/5
California Court of Appeal, 2023
SASCO vo CSI Electrical Contractors, Inc. 2/4
California Court of Appeal, 2022
Jogani v. Jogani CA2/3
California Court of Appeal, 2021
Vedros v. Consumer Services of Walnut Creek CA5
California Court of Appeal, 2021
Paterra v. Hansen CA4/1
California Court of Appeal, 2021

Cite This Page — Counsel Stack

Bluebook (online)
66 Cal. Rptr. 3d 175, 155 Cal. App. 4th 525, 2007 Cal. App. LEXIS 1585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-pacific-construction-inc-v-city-of-sunnyvale-calctapp-2007.