Culjak v. Better Built Homes, Inc.

137 P.2d 492, 58 Cal. App. 2d 720, 1943 Cal. App. LEXIS 102
CourtCalifornia Court of Appeal
DecidedMay 21, 1943
DocketCiv. 13996
StatusPublished
Cited by20 cases

This text of 137 P.2d 492 (Culjak v. Better Built Homes, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Culjak v. Better Built Homes, Inc., 137 P.2d 492, 58 Cal. App. 2d 720, 1943 Cal. App. LEXIS 102 (Cal. Ct. App. 1943).

Opinion

MOORE, P. J.

Defendant appeals from a judgment in the sum of $9,746.82 as the reasonable value of labor and materials for the construction of a sewer. The principal grounds of appeal are that the findings made are contradictory and irreconcilable; that they do not support the judgment; that they are not supported by the evidence; that the court failed to find on a material issue.

About the 20th day of February, 1941, after extended negotiations, the parties executed a writing bearing the date of January 20, 1941, whereby, for the sum of $3,306.80, the plaintiffs agreed to furnish all labor and materials and construct a sanitary sewer in lot 372 of tract 1000, in San Fernando Valley, in the city of Los Angeles. According to certain plans and profiles prepared by defendant subsequent to the execution of the writing, the engineering department of the city declined to permit the construction according to the plans adopted by the contract and changes were made requiring additional construction and the addition of metal gasket forms wherever water should be encountered. By reason of the new requirements the parties agreed upon the additional costs of construction according to the modified plans and on or about the 13th day of March, defendant agreed in writing to pay plaintiffs the additional sum of $234.20. After the last mentioned date, San Fernando Valley experienced continuous and heavy rains as a result of which the water level in the area of tract 1000 rose approximately 20 feet higher than the level which obtained in Feb *722 ruary. Such rise in the water level caused the area in which the sewer was to be constructed to be filled with water. Thereafter on the 12th day of May, Mr. Culjak stated to the officers of defendant that by reason of the water-soaked condition of the ground, plaintiffs could not proceed with the work for the price stipulated in the written contract; that if defendant would wait until the water level should subside, the construction could be done at the price originally named but otherwise not by plaintiffs. In reply to Mr. Culjak, defendant’s officers stated that the job had to be done immediately and directed plaintiffs to proceed. Mr. Culjak declined to proceed without some written authorization to do so, whereupon Mr. Joel B. Moss, president of the defendant, wrote Mr. Culjak as follows: “Please continue with your contract for sewer recognizing additional water that may entail additional expense.” Following the last mentioned conference on May 12, plaintiffs began the construction of the sewer which they completed on July 11. During the course of construction the use of numerous materials and devices as well as of the services of workmen in addition to that which would have been required prior to the excessive rainfall were utilized in the construction of the sewer according to the plans and the city’s specifications.

Defendant having refused to pay the bill presented by plaintiffs, they later filed this action on the 28th day of August, 1941. The amended complaint contains four separate causes of action. Bach of them alleges the performance of the work and the cost in the sum of $9,746.82. The first count alleges the written contract and the amendment thereto on the 12th of May, the reasonable cost of additional material and of the use of other equipment necessitated by changes in the plans and rise of the water level in the sum of $6,440.02. The second count alleges a verbal agreement on the 12th of May, 1941, to construct the sewer according to new plans and profiles submitted by defendant to and recognized by the city of Los Angeles; that such plans and profiles required the construction of the sewer at a depth of about 12 feet below the level originally specified and which plans comprehended the rise of the water level into the area where the sewer was to be constructed which required “the use of water pumps, tight sheathing, rock shield, gaskets and equipment adapted to use in such water-bearing soil, all of said work would be done to the satisfaction and approval of the engineering department *723 of the city of Los Angeles; that in consideration of the performance of said work by plaintiffs, said defendant agreed to pay to plaintiffs the cost of construction plus 10 per cent of the cost of construction for social security, public liability, property damage and workman’s compensation plus 15 per cent of the cost of construction to cover the plaintiff’s overhead and profit.”

The third count alleges an implied agreement arising out of the construction of the sewer pursuant to the request of defendant, the construction and its value, and the refusal of defendant to pay.

The fourth count adopts the allegations of the first count and in addition thereto makes appropriate allegations for the foreclosure of their mechanic’s lien.

In Finding II the court determined the facts in accordance with the allegations of Count II in that the parties entered into a verbal agreement on May 12, 1941; that between the 12th day of May, 1941, and the 23rd of July, 1941, plaintiffs constructed the sanitary sewer and house connections; that the cost of such construction is $9,646.82. Appellant contends that it was prejudiced by the failure of the court to show by its finding “the calculation by which the court arrived at its judgment.” Evidently appellant desires to have the court’s opinion or a picture of the court’s mental process by which the ultimate fact of the aggregate cost was derived. To such contention we do not yield. While it is essential that the “reasonable values” be alleged and that they be proved by competent evidence yet the function of the finding is to declare only the ultimate fact determined. (Forman v. Hancock, 3 Cal.App.2d 291 [39 P.2d 249]; Brea v. McGlashan, 3 Cal.App.2d 454, 467 [39 P.2d 877]; Mammoth Gold Dredging Co. v. Forbes, 39 Cal.App.2d 739, 753 [104 P.2d 131].) The trial court is not required to incorporate evidentiary facts in its findings. In its brief appellant says that “each one of the items of labor and materials together with the costs therefor was in evidence.” We must assume that, because of the presence of evidence of “each item” and the identity of their aggregate amount with the total found ultimately to have been incurred and to be unpaid, the items so proved establish the basis of the court’s computation. Since the pleadings and the evidence both warrant the finding of the amount to which plaintiffs are entitled more details of fact in the finding would be surplusage.

*724

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Overholser v. Glynn
267 Cal. App. 2d 800 (California Court of Appeal, 1968)
Kaneko v. Okuda
195 Cal. App. 2d 217 (California Court of Appeal, 1961)
Brown v. Higbee
175 Cal. App. Supp. 2d 917 (Appellate Division of the Superior Court of California, 1959)
Skipitar v. Munro
345 P.2d 508 (California Court of Appeal, 1959)
D. A. Parrish & Sons v. County Sanitation District Number 4
344 P.2d 883 (California Court of Appeal, 1959)
Lewis v. Firestone
338 P.2d 953 (California Court of Appeal, 1959)
Richards v. Oliver
328 P.2d 544 (California Court of Appeal, 1958)
Wolff v. Wolff
320 P.2d 596 (California Court of Appeal, 1958)
Hollywood Wholesale Electric Co. v. Jack Baskin, Inc.
303 P.2d 1049 (California Court of Appeal, 1956)
Thomasset v. Thomasset
264 P.2d 626 (California Court of Appeal, 1953)
Lawrence Barker, Inc. v. Briggs
248 P.2d 897 (California Supreme Court, 1952)
American Enterprise, Inc. v. Van Winkle
246 P.2d 935 (California Supreme Court, 1952)
Alonso v. Hills
214 P.2d 50 (California Court of Appeal, 1950)
Simmons v. California Institute of Technology
209 P.2d 581 (California Supreme Court, 1949)
Brand v. Riemer
199 P.2d 736 (California Court of Appeal, 1948)
Cleverdon v. Gray
145 P.2d 95 (California Court of Appeal, 1944)
Younis v. Hart
138 P.2d 323 (California Court of Appeal, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
137 P.2d 492, 58 Cal. App. 2d 720, 1943 Cal. App. LEXIS 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/culjak-v-better-built-homes-inc-calctapp-1943.