Sehulster Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp.

4 Cal. Rptr. 3d 655, 111 Cal. App. 4th 1328
CourtCalifornia Court of Appeal
DecidedSeptember 12, 2003
DocketD036734
StatusPublished
Cited by25 cases

This text of 4 Cal. Rptr. 3d 655 (Sehulster Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sehulster Tunnels/Pre-Con v. Traylor Brothers, Inc./Obayashi Corp., 4 Cal. Rptr. 3d 655, 111 Cal. App. 4th 1328 (Cal. Ct. App. 2003).

Opinion

Opinion

BENKE, Acting P. J.

These appeals involve a $90 million contract (the Prime Contract) to build the South Bay Ocean Outfall Project (the Project), a 3.5-mile tunnel under the Pacific Ocean to discharge treated sewage at sea. The City of San Diego (City) was the Project owner, Traylor Brothers, Inc./Obayashi Corporation, a joint venture (TBO), was the general contractor and Sehulster Tunnels/Pre-Con, a joint venture (Sehulster), was the subcontractor that supplied to TBO the precast concrete ring segments lining the tunnel. The tunnel was built and apparently works flawlessly. However, disputes arose between City, TBO and Sehulster for cost overruns incurred by Sehulster in manufacturing the tunnel ring segments as a result of certain design changes in the Project. Following a jury trial on Sehulster’s complaint for breach of contract and related causes of action against TBO and TBO’s cross-complaint against City for indemnity, the jury awarded Sehulster $2.8 million in damages against TBO and determined that TBO was entitled to 30 *1332 percent indemnity from City. The trial court awarded Sehulster $1.6 million in attorney fees against TBO but no attorney fees to TBO against City.

TBO and City separately appeal the judgment. TBO contends the trial court erred by ruling that Sehulster’s claims were not barred as a matter of law because Sehulster did not comply with the Dispute Review Board (DRB) process contained in the Prime Contract between City and TBO before pursuing litigation. TBO further contends the trial court erroneously decided the parties’ postjudgment motions pertaining to the scope of the release in the parties’ May 1997 settlement agreement. TBO also contends it cannot be liable under an abandonment theory, reasoning that if City cannot be held hable under an abandonment theory on a pubhc works contract then it cannot be held liable for abandonment under circumstances in which City is required to indemnify it. TBO’s remaining contentions assert the trial court erred by denying its motion for judgment notwithstanding the verdict (JNOV) on its indemnity claims against City, its motion for attorney fees against City and its motion to require City to indemnify it for a portion of Sehulster’s attorney fees awarded against TBO. City’s appeal presents a multifaceted attack on the portion of the judgment awarding indemnity to TBO. City contends that as a matter of law TBO has no cause of action for equitable or imphed contractual indemnity against it; the trial court prejudicially erred in instructing the jury regarding indemnity; the trial court prejudicially misinterpreted the special verdict form; the judgment entered is inconsistent with the verdict; and in any event the judgment against City must be reversed because it cannot be held liable for cost overruns on a pubhc works project under an abandonment, quantum meruit or other equitable theory, including imphed contractual indemnity. 1

We conclude that if the interests of the general contractor and the owner are adverse to those of the subcontractor, the contractually mandated DRB process contained in the Prime Contract between City and TBO is presumptively biased and unenforceable as a condition precedent to the subcontractor pursuing htigation. We further hold the trial court correctly interpreted the scope of the release in the parties’ May 1997 settlement agreement and TBO can be hable to Sehulster under an abandonment theory. We also conclude that because City did not breach its contract with TBO, as a matter of law City cannot be held hable to TBO under the equitable theory of imphed contractual indemnity on a pubhc works contract for cost overruns incurred *1333 by a subcontractor under a purchase order agreement with the general contractor. To permit TBO to recover under the equitable theory of implied contractual indemnity would ignore the provisions of the Prime Contract that govern modification of the originally negotiated contract price and the parties’ mutual understanding the tunnel ring segment design changes would have no cost impact on the Prime Contract. Accordingly, we reverse the indemnity portion of the judgment in favor of TBO against City. In all other respects, we affirm the judgment. 2

FACTUAL AND PROCEDURAL BACKGROUND

The Project is located north of the Mexican border in Southern San Diego County, and was designed for City by Parsons Engineering (Parsons). On completion of the plans, City solicited bids for construction of the Project. TBO was the lowest bidder at approximately $90 million. The Project was intended to facilitate cleanup of the beaches polluted from raw sewage entering into the Tijuana River Valley. It connects the South Bay International Water Treatment Plant with an ocean outfall through a 200-foot drop shaft to a three and one-half mile long, 11-foot diameter tunnel approximately 100 feet under the ocean floor. The tunnel was designed to be drilled by a tunnel-boring machine and lined with precast concrete rings, originally designed to be four feet wide, consisting of five segments of equal size transported in pieces to form a ring behind the boring machine. The ring segments were to be bolted to each other and to the preceding ring as the tunnel-boring machine progressed through the ground. In August 1995 TBO and City entered into the Prime Contract. On October 9 TBO entered into a written purchase order with Sehulster to manufacture the tunnel rings specified in the Prime Contract for $16,604,000.

During negotiations for the purchase order with Sehulster, TBO discovered that the tunnel-boring machine it ordered was not compatible with the bid design of the tunnel ring segments. After bidding, TBO advised City that it believed the tunnel-boring machine was not compatible with the original ring design and the machine would have to be made longer, increasing the risk that it would lodge in the tunnel, jeopardizing the entire project. Although City’s engineers did not concur with TBO’s assessments, they agreed that the longer boring machine shield would increase skin friction and might inhibit advancement of the shield. TBO then requested City to redesign the tunnel ring segments to be compatible with the unmodified tunnel boring machine, prompting the parties to meet and confer. TBO advised City that if it did not redesign the tunnel ring segments, TBO would immediately start to build an extended version of the tunnel-boring machine at a cost of between $300,000 *1334 and $1 million. It cautioned City that proceeding in that manner would be “technically imprudent.” Apparently deciding to work with TBO, which was responsible for providing the boring machine, and to not risk the machine becoming lodged in the tunnel, City elected to redesign the tunnel ring segments and directed Parsons to do so. As a result, the tunnel ring design changed from five equal segments measuring 72 degrees each, to two 82 1/2 degree segments, two 80 degree segments and one 35 degree “key” segment. City issued the new design drawings as a change order on December 15, 1995, and directed TBO to build them. TBO advised City there might be additional costs caused by the new design.

TBO entered into the purchase order with Sehulster before City had completed its revised ring design.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yu v. Kaiser Foundation Health Plan CA1/1
California Court of Appeal, 2026
(PS) Halajian v. Yost
E.D. California, 2024
Henreid v. Skaggs CA2/7
California Court of Appeal, 2024
Visa Inc. v. Sally Beauty Holdings, Inc.
Court of Appeals of Texas, 2021
Epstein v. Vision Service Plan
California Court of Appeal, 2020
Sciarratta v. U.S. Bank National Ass'n
247 Cal. App. 4th 552 (California Court of Appeal, 2016)
Conservatorship of P.S. CA2/1
California Court of Appeal, 2015
Housing Reform Coalition of Los Angeles CA2/4
California Court of Appeal, 2015
Nishimura v. Gentry Homes, Ltd.
325 P.3d 634 (Hawaii Intermediate Court of Appeals, 2014)
Heather Newton v. American Debt Services, Inc.
549 F. App'x 692 (Ninth Circuit, 2013)
J.R. Marketing v. Hartford Casualty
California Court of Appeal, 2013
Trompeter v. Ally Financial, Inc.
914 F. Supp. 2d 1067 (N.D. California, 2012)
Newton v. American Debt Services, Inc.
854 F. Supp. 2d 712 (N.D. California, 2012)
Exxon Mobil Corp. v. New West Petroleum L.P.
566 F. Supp. 2d 1148 (E.D. California, 2008)
City of Los Angeles v. Glair
63 Cal. Rptr. 3d 280 (California Court of Appeal, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
4 Cal. Rptr. 3d 655, 111 Cal. App. 4th 1328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sehulster-tunnelspre-con-v-traylor-brothers-incobayashi-corp-calctapp-2003.